Questions and Answers for ESIA Solicitation.docx

DOCX document 14 KB Posted

Attached to
Environmental and Social Impact Assessment (ESIA) Gap Analyses
Solicitation number
77344420R0001
Issued by

View the file

Other files

File Type Posted
77344420R0001000002_US (6).pdf PDF
77344420R0001000001_US (3).pdf PDF
77344420R0001_0_US (1) (2).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers (Q&A) for Solicitation 77344420R0001 Environmental and Social Impact Gap Analyses

1. Question 1: The consultant’s duty of care - Can we insert duty of care e.g. “The IC shall provide the services exercising reasonable skill care and diligence”?

Answer 1: Yes, but it will be a Time and Materials contract and DFC will determine if the work is satisfactory. Repeated provision of unacceptable work by the consultant could result in termination of the contract.

1. Question 2: What are the required Insurance levels?

Answer 2: The consultant should decide to carry what they deem necessary in insurance for the work it performs. DFC will not require additional insurance.

1. Question 3: Limitation of the consultant’s liability? For example, would 10 x fee value be acceptable to DFC?

Answer 3: There won’t really be any financial liability to the consultant, as the liability to the DFC from the consultant’s work is political. This is a Time and Materials contract, the dollar amount for any one task order will be relatively small, and DFC’s main remedy would be termination of the contract, not litigation.

1. Question 4: What is the Governing Law – would the Laws of England be acceptable?

Answer 4: Governing law would be U.S., as any disputes would revolve around the contract and the FAR.

1. Question 5: What dispute resolution procedures (if any) are there? If there are none then can we suggest a clear dispute resolution procedure?

Answer 5: Dispute resolution would fall under the government claims disputes 52.233-1 Disputes 41 U.S.C chapter 71 as defined in FAR part 33. FAR Clause 52.233-1 has been added to the solicitation.

1. Question 6: In our proposal response, are we also able to offer our Company T&Cs for review by DFC?

Answer 6: No other terms and conditions will be considered. Any proposals that deviate from the contract terms and conditions will not be considered and the proposals will be deemed non-responsive.