This Statement of Work (SOW) details a renovation project for the Department of Veterans Affairs Consolidated Mail Outpatient Pharmacy (CMOP) located in Murfreesboro, Tennessee. The project involves renovating a manual pharmaceutical filling area for different operations including NIOSH, Bulk, Cold Chain, and Controlled Drugs storage at 3209 Elam Farms Parkway. The project is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 236220 and has a 120-calendar day performance period after Notice to Proceed.
Key project requirements include comprehensive deliverables such as a Contractor Quality Control Plan, Critical Path Method schedule, comprehensive safety plan, weekly progress reports, permit coordination, operations and maintenance manuals, and on-site training. The solicitation is expected to be released with a response date of 11/26/2025 at 1500 CST, with the contractor responsible for all aspects of construction including labor, materials, equipment, permits, installation, and commissioning. Normal work hours are 7:00 AM to 4:00 PM Monday through Friday, with potential for weekend work with prior VA approval, and strict requirements to ensure CMOP operations are not impacted during construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 764-24-101_Renovate_Manual_Area_Drawings_20241010.pdf | ||
| 764-24-101_Renovate_Manual_Area_Specs_20241010_Rev.pdf | ||
| 36C77026R0005.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
MID-SOUTH CMOP (ELAM FARMS)
RENOVATE MANUAL AREA
CONSTRUCTION PROJECT
PROJECT # 764-24-101
1. PROJECT OVERVIEW
1.1 PURPOSE:
A. The Department of Veterans Affairs (VA) Consolidated Mail Outpatient Pharmacy (CMOP) intends to perform construction at the Mid-South CMOP, located at 3209 Elam Farms Parkway, Murfreesboro, TN, 67127.
B. The construction includes general requirements, existing conditions, metals, fire suppression, HVAC, electrical, and low voltage.
The contractor shall be responsible for all aspects of the project and each phase shall be subject to VA approval at designated project milestones. This project includes (but not limited to) all labor, materials, supplies, equipment, services, communications, security, operation and maintenance manuals, as built drawings, permits, construction, installation, and commissioning.
1.2 PROJECT ACTIVITIES:
The entire activity of the project will follow the following sequence of events:
A. Pre-proposal Site Visit B. Request for Proposal Submission C. Award D. Post Award Kick-off Meeting E. Notice to Proceed F. Bonding & Insurance G. Plans – Security, Schedule, H. Progress Reports (Bi-Weekly or Weekly depending on activities) I. Permits, If Necessary J. Demolition, Construction, Installation, Commissioning, and Training K. Final Inspection and Punch List L. Acceptance M. Operations and Maintenance Manuals N. AutoCAD Drawings (Design, Construction, As Built) O. Progress Payments P. Warranty
2. SCOPE OF WORK
2.1 GENERAL: The Contractor shall provide all necessary services to meet the program objectives and requirements and to provide the required outcome in terms of overall quality, timeliness, and documentation, per Construction Documents & Specifications titled “764-24-101_Renovate_Manual_Area_Drawings_20241010” and “764-24-101_Renovate_Manual_Area_Specs_20241010_Rev”. The Contractor shall be responsible for obtaining and coordinating the services of all Sub-Contractors performing other services on site and other entities as part of the contract to ensure the expected quality, timely, and documented final product.
A. Location: 3209 Elam Farms Parkway, Murfreesboro, TN, 67127.
B. Normal work hours are 7:00AM to 4:00PM, local time, Monday through Friday except for Federal Holidays. If the Contractor desires to work on Saturday, Sunday, holidays, or outside the project site’s normal working hours the contractor must submit a written request for approval to the VA-COR at least seven (7) working days prior to the proposed start of such work.
C. CMOP operations shall not be impacted. If any activities would potentially impact operations, then they must occur on a Saturday or Sunday when CMOP is not work overtime shifts.
2.2 DESCRIPTION OF WORK
The manual pharmaceutical filling area will be renovated for different operations such as NIOSH, Bulk, Cold Chain and Controlled Drugs storage.
2.3 DELIVERABLES
A. Period of Performance: 120 Calendar days after Notice to Proceed
B. Performance and Payment bonds: Due 10 Calendar days after award
C. Proof of Insurance: Due 10 Calendar days after award
D. Contractor Quality Control Plan (CQCP): The contractor shall develop a quality control plan and shall furnish to VA for review no later than 30 calendar days after the receipt of notice to proceed. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. VA will consider an interim plan for the first 45 calendar days of operation. Installation will be allowed to begin only after acceptance of the CQCP or acceptance of an interim plan applicable to the particular feature of the work to be started. Work outside of the features of the work included in an accepted interim plan will not be permitted to begin until acceptance of a CQCP or another interim plan containing the additional features of the work to be started. After acceptance of the CQCP, the Contractor shall notify the Contracting Officer’s Representative (COR) in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
E. Schedule: The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements (Project Schedule) and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). See the Specifications for details.
F. Safety Plan: Comprehensive safety plan, AKA the Accident Prevention Plan or Construction Safety & Health Plan, shall be implemented by the Contractor in accordance with the Specifications prior to mobilization. The plan shall be site and job specific, and address all prime and subcontractor work operations. Work cannot proceed without an accepted Safety Plan. The Plan can include Fire Safety rather than having a separate Fire Safety Plan. See the Specifications for details.
G. Progress Reports: Shall be submitted electronically every week to the COR and address, at a minimum, the status of deliverables, project schedule, price and technical performance as they relate to the planned and actual work performed during the past week, work planned for the following two weeks and address any open critical issues.
H. Progress Meetings: Will be held weekly or bi-weekly depending on project status, and 30 minutes to 1 hour in length. The Contractor is responsible for scheduling the meetings, providing the agenda, and documenting minutes. The frequency and duration may change depending on the work activities occurring.
I. Permits: Contractor shall submit all permits associated with this project to the COR. This shall include permits necessary with City of Murfreesboro and local Fire departments. The contractor shall be responsible for coordination with these offices. Although, the facility is operated by the Federal Government, it is leased and privately owned. Installation will be allowed to begin only after VA’s acceptance of all permits.
J. Operations and Maintenance Manuals (O&M): The Contractor shall provide complete sets of O&M manuals in accordance with the Specifications.
K. Operations and Maintenance Training: The Contractor shall provide on-site O&M training in accordance with the Specifications.
O. Warranty Plan: Contractor shall provide a Warranty Management Plan at least thirty (30) days before the planned pre-warranty conference in accordance with the Specifications.
2.4 ACCEPTANCE
A. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all the following:
i. The Contractor has demonstrated/verified that the implemented equipment and measures function as intended at commissioning. All punch list items identified during the commissioning have been resolved.
ii. The Contractor has provided O&M manuals.
iii. The Contractor has provided Record drawings to include a CD with all as builds CAD files, one full set, one half set.
2.5 CONFIDENTIALITY AND NONDISCLOSURE
A. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the COR at the conclusion of the contract.
B. The Contracting Officer will be the sole authorized official to release verbally or in writing, any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract. No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
C. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
D. To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.
2.6 VA PRIVACY POLICY REQUIREMENTS
A. Information Systems Officer, Information Protection: The contractor will not have access to VA Desktop computers nor will they have access to online resources belonging to the government while conducting services in the application of complex adaptive system theory to health care organizations. The certification and accreditation requirements do not apply to this procurement nor is a security accreditation package required.
B. Privacy Officer: The contractor will not have access to Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA. All research data available for Contractor analyses is de-identified.
C. Records Manager: There will be no federal records created, maintained, used or disposition with this contract; regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.]
3. BID ITEMS
Base bid by Division without alternates.