Solicitation #75R60220R00023 - QUESTIONS

1) Regarding participating in meetings in Rockville, MD, please clarify “up to three (3) nights” in the sentence “Upon issuance of a task order the Government will direct the contractor to attend up to three (3) nights in Rockville area.”

Answer: HRSA intends for the contractor to stay for the duration of an ACHDNC meeting for three (3) nights total.

2) Is the description of Task 3 intended to refer to an “expert panel” or “Technical Expert Panel,” as is suggested in the Deliverables table?

Answer: An expert panel or technical expert panel is not required for Task 3.

3) In the top line of the Deliverables table, does “expert panel” refer to the “Evidence Review Group (ERG)” and/or the “Technical Expert Panels,” which are to be approved by the COR, noted in Tasks 1, 2, and 6?

Answer: The Deliverables table refers to the Technical Expert Panels.

4) Pursuant to the statements in the RFP that “The contractor shall provide all personnel, materials, facilities, services, and equipment necessary for the performance of work … “and that “Services shall include work in the areas of organization; administration; …” Can you confirm that the five mentions of “Convene and manage” or “convene a one-day meeting” are meant to include arranging facilities, travel, and related logistics for these activities?

Answer: HRSA confirms that the five mentions of “Convene and manage” or “convene a one-day meeting” are meant to include arranging facilities, travel, or related logistics for these activities.

5) On page 51 of the Final IDIQ Sections A through J July 30 (v 3.2), there are typographical errors in the third bullet point and an embedded code (51 repeated across the line). Can you please clarify that?

Answer: Page 51 has been reviewed and the Government has not found any errors.

6) On page 54 of the Final IDIQ Sections A through J July 30 (v 3.2), it says “Evaluation of cost proposals associated with the 4 hypothetical projects….” However, in Attachment A IDIQ ACHDNC 2020 SOW-Final, there are 8 tasks listed. Can you please clarify this as well?

Answer: The Evaluation of cost proposals associated with 4 hypothetical projects has been deleted.