SECTION C: STATEMENT OF WORK
IHS PROJECT AL-17-A82
DEBORAH WEINBRENNER AND BRYAN MARTINEZ
MESCALERO APACHE TRIBE, NEW MEXICO
GR 1.01 GENERAL REQUIREMENTS
1. Introduction/Background:
The work to be performed under these provisions shall include the furnishing of all labor, tools, equipment, materials, work facilities, supervisory efforts, testing, and all necessary incidentals for the following:
Deborah Weinbrenner and Bryan Martinez: The Deborah Weinbrenner site shall include the construction of a new on-site septic system which shall include a new sewer service line double cleanout, new 4-inch PVC gravity service line, new septic tank with effluent filter, new distribution box, and new EZ-flow drainfield. The Bryan Martinez site shall include the connection to an existing water main, road cut and patch, traffic control plan, new 6-inc PVC water main, new 6-inc gate valve and box, new flush hydrant and gate valve assembly, new service tap with corp stop, new PE water service line, new pressure boosting system with insulated enclosure, buried electrical cable, electrical controls, electrical connections, and all necessary incidentals for the successful water service installation. Refer to the attached Standard Technical Provisions, Standard Details, Supplemental Technical Provisions, Construction Drawings, List of Quantities (proposal/bid schedule) for detailed requirements of the contract.
2. Project Description:
The work located in Mescalero, New Mexico. The work required for the Deborah Weinbrenner and Bryan Martinez sites include, but is not limited to, the following:
a. Mobilize to Deborah Weinbrenner site
b. Construct new on-site septic system for Deborah Weinbrenner, which includes new sewer service cleanout, new gravity PVC sewer service line, new septic tank with effluent filter, new distribution box, and new EZ-flow drainfield.
c. Mobilize to Bryan Martinez site.
d. Perform road cut for successful connection to existing water main. Contractor shall provide traffic control plan and implementation in accordance with the permitting agency. Owner will submit permit for road crossing.
e. Install new 6-inch gate valve and box.
f. Install new 6-inch PVC water main.
g. Install new 2-inch flush hydrant and gate valve assembly
h. Install new water main tap, service saddle and corp stop. Install new water service line.
i. Install new pressure boosting system, complete with electrical system, controls, pump system and insulated enclosure.
j. Install buried electrical cable to new booster system.
k. Conduct training and startup with the Utility Operations staff for the new pressure boosting system.
l. Submit all required testing, documentation, O&M manuals, certifications, and as-built drawings.
m. Demobilize and clean-up sites
3. Tasks/Deliverables/Services to be Provided:
Contractor shall be responsible for construction of a new on-site septic system, and new water service pressure boosting system in accordance with the IHS/SFC Standard Technical Provisions and Supplemental Technical Provisions, and all necessary incidentals required as shown in the construction drawings, Standard Technical Provisions, and Supplemental Technical Provisions. Testing will include compaction testing for the new water main, pressure testing of the new water main, and disinfection and bacteriological sampling for the new water main. The deliverables to be submitted include O&M manuals, startup and training, final inspections, and as-built drawings.
4. Period of Performance: 45 days from the Notice to Proceed
5. Schedule: Contractor shall submit a proposed construction schedule 10 days prior to the NTP date for review and approval by the COR. Construction schedule shall include all major work items as outlined in the scope of work.
6. Any Attachment to Scope if Applicable: Construction Drawings, dated 8/20/2020 (2 sheets total), Supplemental Technical Provisions (3 sheets total), Technical Provisions for Individual Pressure Boosting System (7 sheets total), IHS/AAO/SFC Standard Technical Provisions (301 pages).
7. Point of Contact
1. Bradley Sherer, P.E., COR-II Indian Health Service OEHE/SFC 801 Vassar Drive NE Albuquerque, NM 87106 505-248-7624 office 505-660-1050 mobile Bradley.sherer@ihs.gov
2. Alternate: Mike Buck Elk, COR-II Indian Health Service OEHE/SFC 801 Vassar Drive NE
| Albuquerque, NM 87106 |
| 505-248-7649 office |
| 505-379-5780 mobile |
| Mike.buckelk@ihs.gov |
File details come from the government source that posted it. Updated .