Copy of Pricing Sheet.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- 75F40126Q00351
About this file
This is a pricing sheet template for the Regulatory Science Tool for Transcranial Ultrasound Modeling solicitation (75F40126Q00351) issued by the Department of Health and Human Services Food and Drug Administration Office of Acquisition and Grant Services. The template is designed to capture contractor cost proposals across a base period and four option periods.
The pricing sheet requires contractors to provide detailed cost estimates organized into seven cost categories: Direct Labor (with specified labor categories including Post Doc Fellow and Software Engineer positions with hourly rates), Overhead Rate applied to total labor costs, Materials/Services excluding Information Technology, Information Technology Support, Travel, Subcontractor(s)/Consultant(s), and Other Direct Costs including freight. Each cost category must be broken out separately for the Base period and Options I through IV, with columns for estimated hours, hourly rates, and estimated costs as applicable. All cost fields currently display zero values, indicating this is an unfilled template awaiting contractor pricing data. The template includes a final calculation row for Total Estimated Cost across all periods and cost categories.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_QR_75F40126Q00351.pdf | ||
| 75F40126Q00351.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pricing Sheet Pricing Sheet
| Base | Option I | Option II | Option III | Option IV | TOTAL | |||||||||||
| 1. DIRECT LABOR (List Labor Categories) | ESTIMATED HOURS | RATED PER HOUR ($) | ESTIMATED COST ($) | ESTIMATED HOURS | RATED PER HOUR ($) | ESTIMATED COST ($) | ESTIMATED HOURS | RATED PER HOUR ($) | ESTIMATED COST ($) | ESTIMATED HOURS | RATED PER HOUR ($) | ESTIMATED COST ($) | ESTIMATED HOURS | RATED PER HOUR ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) |
| Post Doc Fello | 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||||
| Software Engineer | 0 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||||||
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||||||
| TOTAL DIRECT LABOR | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| 2. OVERHEAD | RATE (%) | TOTAL LABOR ($) | ESTIMATED COST ($) | RATE (%) | TOTAL LABOR ($) | ESTIMATED COST ($) | RATE (%) | TOTAL LABOR ($) | ESTIMATED COST ($) | RATE (%) | TOTAL LABOR ($) | ESTIMATED COST ($) | RATE (%) | TOTAL LABOR ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) |
| $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | |||||||||||
| 3. MATERIALS/SERVICES (Excluding Information Technology (IT) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) | ||||||||||
| $0.00 | ||||||||||||||||
| 4. INFORMATION TECHNOLOGY SUPPORT | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) | ||||||||||
| $0.00 | ||||||||||||||||
| $0.00 | ||||||||||||||||
| TOTAL IT SUPPORT | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||||||
| 5. TRAVEL | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) | ||||||||||
| $0.00 | ||||||||||||||||
| 6. SUBCONTRACTOR (S) CONSULTANT (S) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | ESTIMATED COST ($) | TOTAL ESTIMATED COST ($) | ||||||||||
| $0.00 | ||||||||||||||||
| $0.00 | ||||||||||||||||
| TOTAL SUBCONTRACTOR (S) CONSULTANT(S) | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | ||||||||||
| 7. OTHER DIRECT COSTS | ESTIMATED COST (S) | ESTIMATED COST (S) | ESTIMATED COST (S) | ESTIMATED COST (S) | ESTIMATED COST (S) | TOTAL ESTIMATED COST ($) | ||||||||||
| FREIGHT |
| TOTAL ESTIMATED COST | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
| TOTAL ESTIMATED COST (BASE) | $0.00 |