QUESTIONS and ANSWERS #2- 02/21/2020 – Mine Waste NIOSH Pittsburgh
1. Can the COR order more than one container on-site at a time for the waste being generated?
Based on our discussions and the proximity to each mine entrance, it would appear that only one container would be needed to meet the storage needs of the waste being generated.
Answer 1. Agreed.
1. Who will be responsible for completing the DEP paperwork and necessary testing for the waste profile?
Answer 2. The vendor/contractor.