This document is an Addendum #1 for a Department of Natural Resources project involving Bunk House Renovations at the Cusino SWRA/Shingleton Wildlife Office located in Shingleton, Alger County, Michigan. The project was issued by Sanders & Czapski Associates, PLLC, with a file number of 751/24291.JBB, and the bid date is set for Wednesday, October 22, 2025, at 2:00 pm ET. A pre-bid conference and site visit occurred on October 7, 2025, with representatives from five companies in attendance: Ripman Construction, Coastal Construction, WR Construction, LLC, Mark & Sons Plumbing & Heating, and U.P. Abatement Co. Inc.
The addendum document confirms that the bid date remains unchanged and includes an attached Meeting Attendance Record documenting the pre-bid conference attendees. The record provides contact information for representatives from each company, including names, email addresses, and telephone numbers. The meeting was held at the Shingleton Wildlife Office/Bunk House location at 10 am ET, with representatives from various construction and service companies present to discuss the renovation project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of Natural Resources
Cusino SWRA / Shingleton Wildlife Office Bunk House Renovations
Shingleton (Alger County), Michigan
ADDENDUM #1
October 8, 2025
Project: Department of Natural Resources Cusino SWRA / Shingleton Wildlife Office Bunk House Renovations E 12340 Highway M-28 West Shingleton (Alger County), Michigan 49884
File No: 751/24291.JBB
Issued by: Sanders & Czapski Associates, PLLC 105 Country Lane Marquette, Michigan 49855
Date: October 8, 2025
The following information modifies, clarifies, changes or adds to or deletes from the Contract Documents. The Bid Date of Wednesday, October 22, 2025 at 2:00 pm, ET is not changed.
Item #1) The following companies were represented at the Pre-Bid Conference and site visit on October 7, 2025:
• Ripman Construction
• Coastal Construction
• WR Construction, LLC
• Mark & Sons Plumbing & Heating
• U.P. Abatement Co. Inc.
A copy of the Meeting Attendance Record is attached.
END OF ADDENDUM #1