751.22391.MAA_Add1 Write Up.pdf
PDF 96 KB Posted
- Solicitation number
- RFQ - 171 - 230000000179
- Issued by
- Alcona County, Michigan
About this file
This document is an addendum to the bidding documents for the 751/22391.MAA Harrisville State Park Footbridge Replacement project in Harrisville, Michigan. The addendum clarifies that the bridge will be fabricated by the Industrial Arts Institute in Onaway, MI, and the contractor shall be responsible for picking up and transporting the bridge to the site and installing it on the abutments. The addendum includes attachments such as the sign-in sheet from the pre-bid walkthrough, revised drawings, and photos of the original benchmark elevations.
The related state and local contract opportunity is for the 751/22391.MAA Harrisville State Park - Foot Bridge project. All questions should be emailed to the designated contact, and bid attachments must be uploaded to SIGMA VSS, as hard copies will not be accepted. The deadline for submission is 2:00 p.m., and emailed submissions will be handled on a case-by-case basis and require approval from the Department of Design and Construction.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 20230130_084240.jpg | JPG image | |
| 22528_230120_Bid Documents with Seal.pdf | ||
| DCSpec_751-22391 01.19.23.pdf | ||
| 22391_DTMB-0415 Advertisement.pdf | ||
| Addendum 1.pdf | ||
| Sign in Sheet.pdf | ||
| 20230130_084228.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
757 S. WISCONSIN AVENUE ▪ GAYLORD MI 49735
p h o n e 989.705.8400 ▪ f a x 989.705.8403
-1-
Up
Addendum Number: 1
Date: 2/2/23
Project Name: 751/22391.MAA Harrisville SP Footbridge Replacement
SG Project Number: 522528
This Addendum is being issued for the purpose of clarifying and/or modifying the original Bidding Documents and shall take precedence over them. Each Bidder’s proposal shall include the Work described herein. All requirements contained in the Contract Documents shall apply to this Addendum. All incidental work necessary to complete the Work shall be included in the Contractor’s quotation even though not particularly mentioned. Parts of the Specifications and Drawings referred to herein supersede previously issued data and form a part of this Addendum.
CLARIFICATIONS:
1. It has been confirmed that the bridge will be fabricated by the Industrial Arts Institute in Onaway, MI. The
Contract SHALL be responsible to pick up and transport the bridge from Onaway to the site in Harrisville, and then install the bridge on the abutments that will have been installed at that point.
ATTACHMENTS:
The following documents are a part of this Addendum:
1. Sign In sheet from the Pre-Bid Walk thru
2. Revised drawings, issued as Addendum No. 1
3. Photos of original Benchmark Elevations as requested during the Pre-bid Walk thru.
File details come from the government source that posted it. Updated .