723202 Bid Tab.pdf

PDF 105 KB Posted

Attached to
234133 Mountain View Drive S Stormwater Improvements
Solicitation number
S-KS0043-00010468
Issued by
Marion County, Oregon

About this file

This document is a Tabulation of Bids for the Mountain View Drive S Stormwater Improvements project, a state and local contract opportunity in Oregon. The project involves various storm sewer improvements including the installation of storm pipes, catch basins, manholes, landscaping, and other associated work. The project has an Engineer's Estimate range of $600,000 to $800,000 and a bid closing date of 6/18/2024. The low bidder is Turney Excavating, LLC with a total bid of $737,610, followed by the 2nd low bidder Gene S. McMurrin, Inc. at $606,155, and the 3rd low bidder M.L. Houck Construction at $645,482.78. The bid items include lump sum and unit price work across various storm sewer infrastructure components.

Pricing terms include a stipulated price for foundation stabilization and rock excavation. There is no information provided about any set asides, incumbents, or specific funding sources. The contract duration and any renewal options are not specified in the provided documentation.

View the file

Other files

File Type Posted
723202 Addendum No. 1.pdf PDF
723202 Project Manual.pdf PDF
ITA- PN 723202.pdf PDF
S-58100-00010469 Attachment A.docx DOCX document
723202 Bid Opening Register.pdf PDF
234133 Bid Opening Zoom Link.pdf PDF
723202 Final Plans.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABULATION OF BIDS FOR:

Average of 3

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

1 Mobilization 1.00 All Req'd Lump Sum 45,000.00 45,000.00 60,000.00 60,000.00 22,892.00 72,900.00 51,930.67

2 Temporary Work Zone Traffic Control a Temporary Work Zone Traffic Control (Complete) 1.00 All Req'd Lump Sum 26,000.00 26,000.00 15,000.00 15,000.00 44,200.00 24,500.00 27,900.00 b Temporary Chain Link Fence 1.00 All Req'd Lump Sum 8,000.00 8,000.00 2,500.00 2,500.00 2,070.00 2,200.00 2,256.67

3 Erosion Control Measures a Erosion Control 1.00 All Req'd Lump Sum 5,000.00 5,000.00 5,000.00 5,000.00 3,470.00 1,150.00 3,206.67 b Sediment Fence 178.00 178 Lin. Ft. 5.00 890.00 4.00 712.00 2.50 5.00 3.83 c Biofilter Bag 39.00 39 Each 55.00 2,145.00 88.00 3,432.00 25.00 41.00 51.33 d Construction Entrance 1.00 1 Each 5,000.00 5,000.00 3,700.00 3,700.00 750.00 2,200.00 2,216.67 e Silt Sacks 13.00 13 Each 175.00 2,275.00 88.00 1,144.00 100.00 93.00 93.67

4 Removal of Structures and Obstructions 1.00 All Req'd Lump Sum 60,000.00 60,000.00 75,000.00 75,000.00 51,654.00 101,000.00 75,884.67

10-inch PVC Storm Pipe, Trench Excavation, and

Crushed Rock Backfill (ASTM D3034, SDR 35) 70.00 70 Lin. Ft. 125.00 8,750.00 108.00 7,560.00 348.93 85.00 180.64

12-inch PVC Storm Pipe, Trench Excavation, and

Crushed Rock Backfill (ASTM D3034, SDR 35) 75.00 75 Lin. Ft. 135.00 10,125.00 140.00 10,500.00 249.73 226.00 205.24

18-inch PVC Storm Pipe, Trench Excavation, and

Crushed Rock Backfill (ASTM D3034, SDR 35) 225.00 225 Lin. Ft. 145.00 32,625.00 137.00 30,825.00 289.86 165.00 197.29

8 Type 3 Catch Basin 1.00 1 Each 5,000.00 5,000.00 3,500.00 3,500.00 1,900.00 6,000.00 3,800.00

9 Type 4 Catch Basin 1.00 1 Each 8,000.00 8,000.00 3,250.00 3,250.00 3,237.00 5,000.00 3,829.00

Mountain View Dr Storm Improvements

Turney Excavating, LLC

PO Box 21597

Low Bidder

Keizer, OR 97307

Project Number:

Bid/Contract Number:

Closing Date:

723202

234133 Jerry Casteel, PE

Project Engineer

Gene S .

McMurrin, Inc

M.L Houck

Contruction 6/18/2024

Engineer's

Estimate

G:\Group\Engineering\Projects\CIP\723202 Mountain View Drive Storm Improvements\11 Ad Bid Award\Contract Book\723202 aba-master\Bid TabulationPage 1 of 3 Tabulation of Bids

Jerry Casteel Snapshot

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

Mountain View Dr Storm Improvements

Turney Excavating, LLC

PO Box 21597

Low Bidder

Keizer, OR 97307

Project Number:

Bid/Contract Number:

Closing Date:

723202

234133 Jerry Casteel, PE

Project Engineer

Gene S .

McMurrin, Inc

M.L Houck

Contruction 6/18/2024

Engineer's

Estimate

48-inch Diameter Stormwater Manhole, 0-8 feet

Deep 1.00 1 Each 6,000.00 6,000.00 8,000.00 8,000.00 5,650.00 1,200.00 4,950.00

60-inch Diameter Stormwater Manhole, 0-8 feet

Deep 2.00 2 Each 8,500.00 17,000.00 12,000.00 24,000.00 7,580.00 9,800.00 9,793.33

48-inch Diameter Flat Top Stormwater Manhole, 0-

8 feet Deep 2.00 2 Each 8,500.00 17,000.00 7,500.00 15,000.00 5,650.00 6,000.00 6,383.33

13 Flow Control Manhole 1.00 1 Each 10,000.00 10,000.00 17,000.00 17,000.00 10,680.00 16,500.00 14,726.67

Extra Manhole Depth (Greater than 8 feet) 60-inch

Diameter 7.00 7 Lin. Ft. 1,000.00 7,000.00 500.00 3,500.00 328.00 900.00 576.00

15 Storm Sewer 10-inch x 10-inch x 10-inch PVC Tee 2.00 2 Each 2,500.00 5,000.00 2,000.00 4,000.00 1,925.00 2,300.00 2,075.00

16 Abandon Storm Mains 25.00 25 Lin. Ft. 100.00 2,500.00 60.00 1,500.00 74.00 115.00 83.00

17 Common Excavation 1.00 All Req'd Lump Sum 30,000.00 30,000.00 52,000.00 52,000.00 36,240.00 86,000.00 58,080.00

18 Landscaping (Complete) 1.00 All Req'd Lump Sum 162,000.00 162,000.00 45,000.00 45,000.00 127,052.00 111,000.00 94,350.67

19 Irrigation Systems 1.00 All Req'd Lump Sum 30,000.00 30,000.00 8,000.00 8,000.00 18,975.00 10,900.00 12,625.00

20 12-inch Mechanical Plug 1.00 1 Each 500.00 500.00 500.00 500.00 400.00 500.00 466.67

21 Chain Link Fence and Gates 1.00 All Req'd Lump Sum 40,000.00 40,000.00 29,000.00 29,000.00 32,492.00 34,000.00 31,830.67

22 Connection to Existing Manhole/Catch Basin 3.00 3 Each 2,500.00 7,500.00 2,200.00 6,600.00 235.00 740.00 1,058.33

23 HDPE Liner 915.00 915 Sq. Yd. 20.00 18,300.00 18.00 16,470.00 19.37 19.20 18.86

24 Class 50 Riprap 4.00 4 Cu. Yd. 200.00 800.00 175.00 700.00 263.53 800.00 412.84

25 Sidewalk Removal and Replacement 875.00 875 Sq. Ft. 20.00 17,500.00 26.00 22,750.00 20.32 21.00 22.44

26 Type A Curb Removal and Replacement 76.00 76 Lin. Ft. 50.00 3,800.00 62.00 4,712.00 44.46 94.00 66.82

G:\Group\Engineering\Projects\CIP\723202 Mountain View Drive Storm Improvements\11 Ad Bid Award\Contract Book\723202 aba-master\Bid TabulationPage 2 of 3 Tabulation of Bids

(*) figures changed to reflect accurate extension or addition 2 nd

Low Bidder 3 rd

Low Bidder Lowest Bidders

NO. QUANTITY

UNIT OF

MEASURE UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE UNIT PRICE UNIT PRICE

Mountain View Dr Storm Improvements

Turney Excavating, LLC

PO Box 21597

Low Bidder

Keizer, OR 97307

Project Number:

Bid/Contract Number:

Closing Date:

723202

234133 Jerry Casteel, PE

Project Engineer

Gene S .

McMurrin, Inc

M.L Houck

Contruction 6/18/2024

Engineer's

Estimate

Type 2 HMAC Pavement Repair 4-inch AC over 6-inch Aggregate Base 260.00 260 Sq. Yd. 150.00 39,000.00 70.00 18,200.00 61.33 77.00 69.44

28 Temporary Trench Patch 300.00 300 Lin. Ft. 12.00 3,600.00 13.00 3,900.00 14.07 18.00 15.02

29 Concrete Retaining Wall 1.00 All Req'd Lump Sum 96,100.00 96,100.00 98,000.00 98,000.00 72,263.00 71,000.00 80,421.00

30 Foundation Stabilization (Stipulated Price) 20.00 20 Cu. Yd. 80.00 1,600.00 80.00 1,600.00 80.00 80.00 80.00

31 Rock Excavation (Stipulated Price) 20.00 20 Cu. Yd. 180.00 3,600.00 180.00 3,600.00 180.00 180.00 180.00

Total 737,610.00 606,155.00

2nd Low Bidder 645,482.78

3rd Low Bidder 734,275.00

951,698.00North Santiam Paving Company

Gene S . McMurrin, Inc

M.L Houck Contruction Company

Remaining Bidders

G:\Group\Engineering\Projects\CIP\723202 Mountain View Drive Storm Improvements\11 Ad Bid Award\Contract Book\723202 aba-master\Bid TabulationPage 3 of 3 Tabulation of Bids

File details come from the government source that posted it. Updated .