This document outlines an award fee evaluation plan for a federal contract to provide technical assistance to implement the USAID Maintained Epidemic Control of HIV Activity in Zambia. The contractor will support access to and utilization of quality HIV services in three provinces to achieve and sustain HIV epidemic control. The contract term is five years from award with an estimated cost of $ excluding a maximum available award fee of $. Contractor performance will be evaluated periodically based on management effectiveness, deliverable quality, and achievement of public health targets. Evaluation criteria include treatment coverage indicators, screening levels, and prevention measures. The contractor's performance determination will consider reports from government monitors and an Award Fee Board. Determinations will be made by a Fee Determining Official within 60 days of each evaluation period.
View the file
Other files for this federal contract opportunity
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT J.1
AWARD FEE EVALUATION PLAN
Contract No. With
Contents
I. Introduction
II. Organizational Structure for Award Fee Administration
III. Evaluation Requirements
IV. Method for Determining Award Fee
V. Changes in Plan Coverage
VI. Schedule
I. Introduction
1. This plan covers the administration of the award fee provisions of Contract No. , dated
, with . The contract was awarded after completion of negotiations in accordance with the provisions of RFP No. .
2. The following matters, among others, are covered in the contract:
(a) The contractor is required to provide technical assistance to implement USAID
Maintained Epidemic Control of HIV (MECH) Activity.
(b) The term of the contract is from through .
(c) The total estimated cost, exclusive of award fee, of performing the contract is $ .
(d) The maximum available award fee is $ .
(e) The estimated cost and award fee may be subject to equitable adjustments arising from changes or other contract modifications.
(f) The award fee payable will be determined periodically by the Fee Determination Official
(FDO) in accordance with this plan.
(g) Award fee determinations are not subject to the Disputes clause of the contract.
(h) The FDO may unilaterally change the matters in this plan, as covered in Part V and not otherwise requiring mutual agreement under the contract, provided the contractor receives notice of the changes at least 30 calendar days PRIOR TO the beginning of the evaluation period to which the changes apply.
II. Organizational Structure for Award Fee Administration
The following organizational structure is established for administering the award fee provisions of the contract.
1. Fee Determination Official (FDO)
(a) The FDO is the Director of USAID/Zambia’s Office of Acquisition and Assistance.
(b) Primary FDO responsibilities are:
a. Determining the award fee earned and payable for each evaluation period as addressed in Part IV.
b. Changing the matters covered in this plan as addressed in Part V as appropriate.
2. Award Fee Board (AFB)
(a) The Contracting Officer’s Representative (COR), with input from the contractor, will serve as the performance monitor. The Contracting Officer will serve as the Fee Determining Official.
A senior Health Office representative, a representative from the Program Office, and the cognizant Acquisition and Assistance Specialist will serve as the Award Fee Evaluation Board
(AFEB). The Health Office Director (or Deputy Mission Director in his/her absence) will be the Chair of the AFEB.
(b) The Chair may recommend the appointment of non-voting Members to assist the AFB in performing its functions.
(c) Primary responsibilities of the Board are:
a. Conducting periodic evaluations of contractor performance and the submission of a
Award Fee Board Report (AFBR) to the FDO covering the Board's findings and recommendations for each evaluation period, as addressed in Part IV.
b. Considering changes in this plan and recommending those it determines appropriate for adoption by the FDO, as addressed in Part V.
3. Performance Monitoring
(a) The Contracting Officer’s Representative (COR) will prepare Performance
Monitoring Reports, as well as written comments on the Contractor’s self-assessment. The COR will also elicit feedback from beneficiaries and stakeholders to include in the written comments. These written documents will be part of the record for the AFB.
(b) The Contractor will submit, as part of its regular quarterly report, a self-assessment of progress toward achieving indicators and milestones as established in its Annual
Work Plan. These written documents will be part of the record for the
Performance Evaluation Board.
III. Evaluation Requirements
The applicable evaluation requirements are attached as indicated below.
1. Evaluation Periods and Maximum Available Award Fee for Each Period
Period of Performance Period*
(Start/End date)
Amount of Award
Fee
Available
First Year TBD at award TBD Second Year TBD at award TBD Third Year TBD at award TBD Fourth Year TBD at award TBD Fifth Year TBD at award TBD Maximum Award Fee Available TBD
2. Award Fee Criteria and Weights
For each of the award fee periods (end of year 1, year 2, year 3, year 4 and year 5):
Factors Assigned % of
Overall Award Fee
Pool
1. Management: How responsive and effective is the relationship between the contractor’s personnel and USAID.
15%
2. Quality of Deliverables: The quality of the contractor’s deliverables and the degree to which the contractor utilizes the Quality Assurance Surveillance Plan (QASP) to assess the effectiveness of planned interventions and evaluates the project progress towards meeting objectives.
15%
3. Achievement of Targets: The extent to which the contractor’s interventions have, at the completion of each award fee period, led to achieving project results.
70%
3. Adjectival Grading Table
Adjectival
Rating
Range of
Perf.
Points
Description
Excellent 91-100% Contractor has exceeded almost all of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate.
Very Good 76-90% Contractor has exceeded many of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate.
Good 51-75% Contractor has exceeded some of the significant award-fee criteria and has met overall cost, schedule, and technical performance requirements of the contract in the aggregate.
Satisfactory No
Greater
Than 50%
Contractor has met overall cost, schedule, and technical performance requirements of the contract in the aggregate.
Unsatisfactory 0% Contractor has failed to meet overall cost, schedule, and technical performance requirements of the contract in the aggregate.
The percentage weights indicated and the grading table above is quantifying devices. Their sole purpose is to provide guidance in arriving at a general assessment of the amount of interim or final award fee earned. In no way do they imply an arithmetical precision to any judgmental determination of the contractor's overall performance and amount of interim or final award fee earned. The Adjectival Grading Table will be used for Factors 1, 2, and 3.
4. Achievement of Targets grading table
For Factor 3. Achievement of Targets, the indicators in the table below will be used to determine the percentage of the fee paid. The percentages listed for each indicator and year indicates the maximum percentage of the Achievement of Target fee that will be paid for completion of each indicator. Partial completion of a specific target will be awarded a pro-rated fee based on the percentage of the target completed. Indicators and percentage weights for each indicator are subject to change on an annual basis based on prior year performance and emerging priorities. Results must be entered into the PEPFAR DATIM system where they will be verified via the annual program report data cleaning process. The fee will be based on the official, cleaned numbers that are approved in the system. The percentages below add up to a total of 70% for each year and represent the composition of the 70% of the award fee for
Achievement in Targets in the table in Section II.2 above titled “Award Fee Criteria and
Weights.”
Achievement of Target Fee
Ref # Deliverable/Targets Yr1 Yr2 Yr3 Yr4 Yr5
XX TX_CURR 30% 30% 30% 30% 30%
XX TX_PVLS (N) 6% 6% 6% 6% 6%
XX TX_PVLS (D) 4% 4% 4% 4% 4%
XX VMMC_CIRC 4% 4% 4% 4% 4%
XX CXCA_SCRN 4% 4% 4% 4% 4%
XX CXCA_TX 4% 4% 4% 4% 4%
XX TB_PREV 4% 4% 4% 4% 4%
XX TX_TB 4% 4% 4% 4% 4%
XX PrEP_NEW 4% 4% 4% 4% 4%
XX PMTCT_EID 6% 6% 6% 6% 6%
IV. Method for Determining Award Fee
A determination of the award fee earned for each evaluation period will be made by the FDO within 60 calendar days after the end of the period. The method to be followed in monitoring, evaluating and assessing contractor performance during the period, as well as for determining the award fee earned or paid, is described below.
1. The COR will evaluate and assess contractor performance and discuss the results with contractor personnel as appropriate, in accordance with the General Instructions for
Performance Monitoring, below, and the specific instructions and guidance furnished by the AFB Chair. Achievement of targets will be determined by officially validated numbers submitted in DATIM, the PEPFAR reporting system.
2. The COR will submit biannual Performance Monitoring Reports and, if required, make verbal presentations to the AFB.
3. The AFB Chair will request and obtain performance information from other units or personnel normally involved in observing contractor performance, as appropriate.
4. Promptly after the end of each evaluation period, the AFB will meet to consider all the performance information it has obtained. At the meeting, the AFB will hear from the
COR, the contractor, and any other appropriate personnel. At this meeting, the contractor is given an opportunity to submit information on its behalf, including an assessment of its performance during the evaluation period. This meeting is to inform the AFB’s recommendation to the FDO.
5. Within 5 days after the AFB meeting, the AFB Chair will prepare the AFB Report for the period and submit it to the FDO for use in determining the award fee earned. The report will include an adjectival rating and a recommended performance score with supporting rationale/documentation. The contractor may be notified of the AFB evaluation and recommended rating and score. The contractor may provide additional information for consideration by the FDO. When submitting the report, the Chair will inform the FDO whether the contractor desires to present any matters to the FDO before the award fee determination is made.
6. The FDO will consider the AFB Report and discuss it with the AFB Chair and other personnel, as appropriate.
7. The FDO will consider the recommendations of the AFB, information provided by the contractor, if any, and any other pertinent information in determining the amount of award fee earned for the period. The FDO's determination of the amount of award fee earned and the basis for this determination will be stated in the Award Fee
Determination Report (AFDR).
8. The contractor will be notified by the Contracting Officer of the FDO's determination.
The contractor may be provided a debriefing by the FDO at his/her discretion.
V. Changes in Plan Coverage
1. Right to Make Unilateral Changes
Any matters covered in this plan not otherwise requiring mutual agreement under the contract, may be changed unilaterally by the FDO prior to the beginning of an evaluation period by timely notice to the contractor in writing. The changes will be made without formal modification of the contract if the plan is not incorporated into the contract.
2. Method for Changing the Award Fee Plan
The method to be followed for changing the plan coverage is described below:
(a) Personnel involved in the administration of the award fee provisions of the contract are encouraged to recommend plan changes with a view toward changing management emphasis, motivating higher performance levels or improving the award fee determination process. Recommended changes should be sent to the AFB for consideration and drafting.
(b) Prior to the end of each evaluation period, the AFB will submit its recommended changes, if any, applicable to the next evaluation period for approval by the FDO with appropriate comments and justification.
(c) 30 calendar days before the beginning of each evaluation period, the Contracting
Officer will notify the contractor in writing of any changes to be applied during the next period. If the contractor is not provided with this notification, or if the notification is not provided within the agreed-to number of calendar days before the beginning of the next period, then the existing plan will continue in effect for the next evaluation period.
VI. Schedule for the Award Fee
The following is a summary of the schedule of the principal actions involved in determining the award fee for the evaluation periods.
Action (Calendar days)
1. AFB Chair and members appointed. NLT 30 days prior to first period
2. COR receives orientation and guidance.
NLT 30 days prior to first period
4. COR assesses performance and discusses results with contractor.
Ongoing after start of period
5. COR submits Performance Monitoring
Reports to AFB.
Last day of each period.
6. AFB considers Performance Monitoring
Reports, Contractor Self Assessments and other requested performance information.
Ongoing
7. AFB meets to consider all performance information obtained during the period and establishes findings and recommendations for AFB Report.
NLT 40 days after end of each period
8. AFB Chair submits AFB Report to FDO. NLT 45 days after end of each period
9. FDO considers AFB Report and discusses with AFB, as appropriate.
NLT 50 days after end of each period
10. FDO makes final determination on award fee.
NLT 60 days after end of each period
The AFB will establish lists of subsidiary actions and schedules as necessary to meet the above schedules.
GENERAL INSTRUCTIONS FOR PERFORMANCE MONITORING
(a) The COR will prepare outlines of their assessment plans, discuss them with appropriate contractor personnel to assure complete understanding of the evaluation and assessment process.
(b) The COR will plan and carry out on-site assessment visits, as necessary.
(c) The COR will conduct all assessments in an open, objective and cooperative spirit so that a fair and accurate evaluation is obtained. This will ensure that the contractor receives accurate and complete information from which to plan improvements in performance. Positive performance accomplishments should be emphasized just as readily as negative ones.
(d) The COR will discuss the assessment with contractor personnel as appropriate, noting any observed accomplishments and/or deficiencies. This affords the contractor an opportunity to clarify possible misunderstandings regarding areas of poor performance and to correct or resolve deficiencies.
(e) The COR must remember that contacts and visits with contractor personnel are to be accomplished within the context of official contractual relationships. Monitors will avoid any activity or association which might cause, or give the appearance of, a conflict of interest.
(f) The Contractor will submit, as part of its regular quarterly report, a self-assessment of progress toward achieving indicators and milestones as established in its Annual
Work Plan. These written documents will be part of the record for the Performance Evaluation Board.
[END OF ATTACHMENT J.1]