TERMS OF REFERENCE OF

OWNER’S ENGINEER

(AC SECTION)

This TOR is arranged in two parts. The first part gives broad information about CASA-1000 project which includes history, description and the institutional arrangements for its construction and operation. It also provides details of the various components of the CASA- 1000 project and a separate sub-section which covers the detailed description of AC section of the CASA-1000 project. The second part contains the objective and scope of services of the Owner’s Engineer which are limited to the AC facilities of the CASA-1000 project. For ease of understanding, the responsibilities have been divided into pre-construction phase (which is expected to last up to 6 months) and construction phase (expected to be of 21 months’ duration).

At the end, details of the reporting relationships and other physical arrangements have been addressed. It may be noted that information about DC network, wherever provided in this document, is to provide an overall picture of the project while the scope of services under this TOR is limited only to the AC facilities.

1. Project information

Background:

Project Rationale and History

1. The Central Asia-South Asia Electricity Transmission and Trade Project (CASA-1000) aims to facilitate electricity trade between hydropower surplus countries in Central Asia and electricity deficient countries in South Asia by putting in place the commercial and institutional arrangements and the transmission infrastructure required for this trade. The four countries participating in the project – Afghanistan, Kyrgyz Republic, Pakistan and Tajikistan – are of considerable geostrategic importance by virtue of their location at the crossroads of China, India, Russia and the Middle East. Sustained efforts to promote institutional development and socio-economic prosperity in the CASA-1000 countries are therefore a very high priority, not only for the countries themselves, but also for the stability of the Central and South Asia regions. The CASA-1000 countries vary significantly in terms of population numbers, economic size and development trajectories, but also share several key characteristics and have complementary development needs and goals, especially in the energy sector, which form the basis for the CASA-1000 project.

2. The project envisages a transmission interconnection between the Central Asia and South

Asia Regions that would be used to export surplus electricity in the summer from existing generation capacity in Kyrgyz Republic and Tajikistan to energy-deficient Afghanistan and Pakistan. The feasibility confirmed the soundness of the considerations that: (i) sufficient quantities of surplus electricity are available in the Central Asian countries (the Kyrgyz Republic and Tajikistan), even under conservative estimates of no new generation project; (ii) a significant need for electricity imports exists in South Asia (particularly Pakistan) to meet existing and projected demand; and (iii) the differences in the cost of electricity between the importing and exporting countries potentially provide a justifiable rationale to make transmission investments to support the electricity trade.

Project Description

3. The project will build a cross-border power trade facility, comprising about 475 km of 500kV HVAC transmission lines to carry power from Kyrgyz Republic to Tajikistan at Khodjant; a 1300 MW HVDC converter in Tajikistan (at Sangtuda) and thereafter a 750km long ±500kV HVDC transmission link via a 300 MW HVDC converter in Kabul, to a 1,300 MW terminal with HVDC converter facilities in Pakistan. The AC to DC convertor station would be designed to help power trade in any direction and would offer significant emergency system support to the national grids of the countries connected through HVDC system.

4. The CASA-1000 feasibility study proposes a route for the line that takes into consideration cost effectiveness, security (especially in Afghanistan and Pakistan to avoid areas that would require significant demining), terrain to facilitate easier operations and maintenance and minimizing social and environmental impacts. For the most part the line traverses a manageable topography with the exception of a narrow and high mountain range in Afghanistan known as the Salang Pass which offers the most direct route linking the North East Power System (NEPS) with Kabul. In the possible scenario of space constraint in that area, alternative options to bypass the Salang pass will be adopted. The final route of transmission line will be designed by the transmission line contractor within the first year of the contractor’s scope of work. Figure 1 gives the project schematic and shows the route of the HVAC and HVDC transmission lines.

Project Implementation and Commercial Framework

5. The four project countries will be implementing CASA-1000 as a public sector project through their respective NTCs (national transmission companies) with support from IFIs (international financial institutions) and other donors. All the Project assets will be owned by the respective NTCs within the boundaries of their own country which are the following:

a. In Afghanistan - Da Afghanistan Breshna Sherkat (DABS)

b. In the Kyrgyz Republic - Joint Stock Company (JSC) National Electric Grid of

Kyrgyzstan (NEGK)

c. In Pakistan - National Transmission and Despatch Company (NTDC)

d. In Tajikistan - Open Joint Stock Holding Company Barki Tojik (BT)

Procurement Arrangements

6. The project procurement is complex and the nature of major procurement packages requires close coordination among the four implementing countries not only to ensure smooth procurement, but also to synchronize project implementation activities keeping in mind overall project sequencing. Market conditions and security concerns along the route of the proposed transmission line add to the complexity of the procurement plan and structure. Hence the project’s implementation arrangements include an intergovernmental mechanism for the procurement and contract management decision-making process for the joint procurement packages for the countries. The IGC has established through a resolution a Procurement Sub-Committee (PSC), comprising senior technical and procurement staff designated by each country. The PSC will carry out all the work needed on behalf of the parties to oversee and bring to successful closure the entire procurement process leading to award of the contracts by the NTCs. The NTCs will follow their respective corporate procedures for internal clearances of procurement and contract awards and assist the PSC in its work. This arrangement has helped in streamlining the joint procurement process and is expected to lead to timely award of all the major DS&I (design, supply and installation) contracts on the project.

7. The major procurements under the project include the HVDC stations in three countries, HVDC and HVAC transmission lines and O&M contracts. Though all the implementing agencies have some experience in managing such large and complex contracts, they do not have sufficient resources to help with drafting of the Pre-Qualification / bidding documents and the evaluation reports, hence, these functions are being facilitated by an international engineering consultancy company (Power Grid Company of India, or PGCI) that has already been appointed by IFC. Progress in the procurement process has already been made, with the launch of the prequalification process for selection of the EPC contractors for the HVDC Convertor stations. As a result of the PQ announcement, the qualification documents submitted by interested firms are currently under review by PGCI. Following a similar approach, the selection process on the transmission line components will be undertaken by the PSC in due course of time with the assistance of

PGCI.

Project Components

10. The Project has been divided into three broad components: Component A - High Voltage Transmission Infrastructure, Component B – Project Management and Capacity Building, and Component C- Community Support Program. For the purposes of this assignment, which pertains to the responsibilities of Owner’s Engineer, the details of the High Voltage Transmission Infrastructure (Component A) are given hereunder:

(i) Sub-component A1 – High Voltage Direct Current (HVDC) Transmission Line which involves the construction of approximately 750 km of 500 kV HVDC overhead transmission line to interconnect the electricity network of Tajikistan, at the Sangtuda substation (s/s), with the Pakistan network, at the Peshawar substation, via the Kabul substation in Afghanistan. The line will have a transmission capacity of 1,300 MW in either direction, using a bipolar and earth-return configuration and will consist mainly of self-supported lattice tower structures, conductors, and insulators. About 120 km of the line will be in Tajikistan, 560 km in Afghanistan, and 70 km in Pakistan. (Note: This section is not included in the scope of the AC Owner Engineer).

(ii) Sub-Component A2 – HVDC Converter Stations which involve the engineering design, construction, and commissioning of three High Voltage Alternating Current (HVAC) to Direct Current (DC) converter stations at Sangtuda s/s (1,300 MW) in Tajikistan, Kabul s/s (300 MW) in Afghanistan, and Peshawar s/s (1,300 MW) in Pakistan. These convert AC power into DC, and vice versa, as needed. The s/s main equipment package includes specialized converter transformers, breakers, filtering equipment, inverters, controls, ground electrodes, and static and dynamic compensation equipment. (Note: This section is not included in the scope of the AC Owner Engineer).

(iii) Sub-component A3 – Kyrgyz-Tajik HVAC Transmission Interconnection which includes the construction of about 475 km of 500 kV HVAC overhead transmission line to interconnect the electricity network of the Kyrgyz Republic, at Datka s/s, with the Tajikistan network, at the Khudjand s/s. About 450 km of the line will be in the Kyrgyz Republic and 25 km in Tajikistan.

(iv) Sub-component A4 – Tajikistan grid reinforcement which includes reinforcements in Tajikistan including construction of 500 kV line from Regar s/s to Sangtuda s/s and other parts of the network necessary to ensure transfer of Tajikistan and Kyrgyz export power to Sangtuda HVDC station.

11. Two consultancy firms (one for the HVDC network and another for the HVAC system) will be selected through a competitive process to act as Owner’s Engineers. These consultants will be responsible for assisting the CASA-1000 countries in supervising the EPC contracts until handing over and commercial operation of the facilities, certifying contractors’ payments, and assisting the IGC Secretariat with coordination among all relevant institutions. There will be a single EPC contract for the DC stations while it’s anticipated that the DC and AC transmission lines will be divided among a number of EPC contractors depending on the procurement rules of the financiers who will be funding these facilities. In this regard, as a first step, the NTCs, with the assistance of PGCI, are finalizing the selection of the EPC contractor for the various components of the project. Figure 2 shows the institutional arrangements for the implementation of the project and indicates the lines of responsibility of the Owner’s Engineers.

The above is the detailed background and scope of the overall project and from this point onward details relating to the AC Network and the roles and responsibilities of the Owner’s Engineer (The Consultant) for the AC Network are being provided.

Details of the AC Network

AC Transmission Line Description of Scope

1. The scope of work of the 500 KV HVAC network will include components A3 and A4 above, namely the engineering, design, manufacturing, testing, supply, installation and commissioning of the following:

(i) 475 km, 500 KV HVAC from Datka substation in Kyrgyz Republic to substation Khudjand in Tajikstan along with relevant devices for connection to the substations;

(ii) 115 km, 500 KV HVAC transmission line from Regar to Sangtuda within the territory of Tajikistan;

(iii) 500 KV Substations at Sangtuda, Datka and Khudjand;

(iv) AC line termination arrangement at Sangtuda, converter station in Tajikistan.

2. Consulting Services Objective and Scope

Objective

2. The services of an Owner’s Engineer (the Project Consultant) are required for the implementation phase of the CASA-1000 Project for the 475 km 500 KV HVAC Transmission Line (from Datka to Khudjand) traversing the territories of Kyrgyz Republic and Tajikistan. Inside the territory of Tajikistan, a 500KV HVAC transmission line from Regar to Sangtuda is also included (total length 115 km) in the scope of services. The Project Consultant will assist the two implementing agencies of HVAC sections of the CASA-1000 project in construction supervision, support for project implementation, audit and TA.

Specifically, the Consultant’s support would be needed in the design, construction supervision and commissioning of the 500 KV HVAC line and substations.)

Personnel requirements

3. The total level-of-effort is estimated at 77 person-months (3 p.m. in Home-Office and 74 p.m. on site). These services will be needed over a period of approximately 27 calendar months (6 calendar months for EPC contract and transmission line design finalization and 21 calendar months for construction supervision). In addition, approximately 50 person-months of local professional and support effort would be employed.

Pre-Construction Phase

4. This period is expected to last approximately 6 months from the date of award of contract to the Project Consultant. During this period the Consultant will advise and assist the two NTCs in Kyrgyz Republic and Tajikistan in the finalization of detailed design of the project by undertaking the following tasks:

(i) Assist the clients in finalizing the technical and commercial conditions of the EPC contract(s).

(ii) Act as interface between the PIUs and the EPC contractors to reach a final agreement on the route of the HVAC transmission line segments; tower spotting and finalization of type of towers.

(iii) Review and approve the design of AC facilities to be submitted by the EPC contractors and harmonize the design parameters among various EPC contractors.

(iv) Coordinate with the Owner’s Engineer for the DC section the details of the AC/DC interface at Sangtuda so that work-scopes of HVDC converter stations and HVAC facilities complement each other.

(v) Provide inputs to the safeguard specialists in preparing detailed Environment and Social Management plans including resettlement and local communities relations issues.

Construction phase

5. The Consultant shall act as the prime liaison between the EPC contractors and the PIUs for all matters relating to their contracts. He shall manage and provide oversight during manufacturing and installation according to the approved engineering drawings and specifications as well as all applicable codes and standards. This shall include all activities from startup to commissioning of the project and encompass the work scopes of all the suppliers, contractors and vendors who are involved in the project. If necessary, he shall assist the PIUs in securing the necessary permits to enable the EPC contractors to smoothly carry out the construction works. For the fulfillment of these broad responsibilities, the Consultant shall undertake the following tasks:

Front-end Activities

(i) Prepare a master implementation plan of the project (the term ‘project’ refers to AC facilities) which will be used to guide the EPC contractors in the development of their supply, installation and construction plans. The aim is to ensure that all project activities are integrated such that the project is completed according to the schedule.

(ii) Prepare a project monitoring scheme (which will include technical, physical and financial details) and share with the PIUs for acceptance by the NTCs. Set up an acceptable methodology for the regular and effective monitoring of the project costs and reporting them to the PIUs.

(iii) Develop and have a common agreement on the formats to be used for reporting project progress so that it covers all aspects of the project, viz. design, supply, installation, commissioning, cost, time-line, etc.

(iv) Develop, recommend and reach agreement on procedures for adequate follow-up of production and testing at the manufacturer site, and for the timely supply and delivery of materials and equipment to the project sites.

(v) Develop and execute a plan to provide necessary on-job training to the PIU staff of the various NTCs in the supervision of works as well in the preparation of reports, especially those required by the project financiers.

Ongoing Activities

(vi) Supervise the installation, testing and pre-commissioning activities on the project.

Coordinate all activities wherever AC/DC inter-linkages are involved with the DC section Owner’s Engineer.

(vii) Track the progress of project execution based on the CPM/PERT charts to be submitted by the EPC contractors. Prepare monthly progress reports, capturing progress till date, status with regard to the planned activities, suggested actions to catch up any delay, plan for the next month’s key activities and highlight key areas of contract performance or gaps, with action plans

(viii) Review any modifications in the detailed design proposed by the EPC contractors during project implementation, and recommend to the respective PIUs for their consideration and approval.

(ix) Assist the PIUs/NTCs during the inspection/acceptance tests of material and equipment at the manufactures’ or third parties’ sites.

(x) Assist the PIUs in settling any disputes among the various parties on technical issues.

(xi) Review and recommend for approval to the PIUs the EPC contractors’ supply and installation schedules or their proposed revisions.

(xii) Undertake site supervision to verify project quality, adherence to time schedule and quantity utilization as indicated in the submitted invoices.

(xiii) Assess the adequacy of all inputs such as materials and labor that are deployed by the

EPC contractors and their methods of work in relation to the required progress, and when required, take appropriate action in order to rectify and to expedite progress.

(xiv) Assist the PIUs in initiating action in case of slow progress by contractors and/or violation of the contractors’ obligations, if any, as per conditions of the contract.

(xv) Recommend to the PIUs the payment against contractors’ invoices based on completion of contractual milestones and approve/clear claims and variation orders submitted by the contractors.

(xvi) Examine and make recommendations on all claims from the contractors for time extension, extra compensations, extra work or expenses or other similar matters including determination of new rates when required.

(xvii) Determine the amount to be added to, or deducted from payments to the contractors for any additional work or for work omitted respectively.

(xviii) Inform the PIU on problems or potential problems which may arise in connection with the implementation of the contract and make recommendations to their possible solutions

(xix) Assist PIUs to compile systematic records of the contractor’s site activities, and prepare and maintain inspection/engineering reports and records to adequately document the progress and performance of the work.

(xx) Upon notice of all completion received from the Contractor, inspect the works and inform contractor and client, in writing, items needing rectification for completion (Puch List).

(xxi) Before the issuance of the certificate of substantial completion, specify and supervise any remedial works to be carried out and recommend upon completion. The inspections shall be carried out jointly with representatives of the concerned PIUs.

(xxii) Maintain detailed records of relevant events & activities, drawings & documents, minutes of meetings, etc.

(xxiii) Prepare and submit monthly and quarterly reports describing work progress, the contractor’s performance, quality of work, delays, deficiencies, constraints, and the project’s financial status, forecasts, and give recommendations for action.

(xxiv) Certify the achievement of the contractual milestones, and the satisfactory quality of the progress, in line with the progress milestones laid down in the contracts.

(xxv) Transfer on a continuous basis the technical know-how to the PIU staff in the fields of project implementation, supervision and construction works through on-the-job training.

Pre-commissioning Activities

(i) Sign the field acceptance test certificates of works and equipment.

(ii) Review, modify (if necessary) and approve the pre-commissioning programs, as and when submitted by the EPC contractors.

(iii) Review, modify (if necessary) and approve the pre-commissioning reports, submitted by the EPC contractors and be present alongside the PIUs at the stage of pre-commissioning.

(iv) Prepare a final acceptance certificate of the pre-commissioning for the PIUs and co-financers of the project.

3. PIU Support

6. The Consultant shall assist the PIUs in preparing their annual reports to be delivered to the

IGC Secretariat, Ministries and the project financiers. The report would cover progress on each project component, implementation key features, key performance indicators, the Annual Work Plan for implementation, annual funds required for implementation with breakdown by each participating financier, update on disbursement profile, planned actions for mitigating negative effects during construction and target indicators for the coming fiscal year.

7. The following PIU staff of the various NTCs will work alongside the consultant for maximum knowledge transfer:

a) Project Director

b) Procurement Specialist

c) Electrical engineers

d) Civil (Structural)Engineer

e) Mechanical Engineer

f) Specialist for relay, protection and automation and communication equipment

g) Financial specialist

The PIUs will provide the following support to the consultant, as detailed below:

In Kyrgyz Republic

Office accommodation in Bishkek with furniture.

In Tajikistan

Office accommodation in Dushanbe with furniture.

The respective offices at the above 2 locations will be maintained by the consultant on all working days (Except Sunday) and any equipment or gadget, other than the one provided by the client stated above, if required for day to day office functioning, will be arranged by the consultant at his / her own cost and expenses.

KEY STAFF

8. The Consultant shall provide at least the key-personnel as detailed below. Qualification &

Experience of the following sub-key personnel only shall be considered for the purpose of evaluation of the consultant’s proposal.

a) Project Manager (Team Leader)

One Project Manager will serve as Team Leader for both Kyrgyz Republic and Tajikistan, respectively, and will be responsible for the overall coordination of the consultant’s services to ensure the satisfactory fulfillment of the requirements of the Terms of Reference and will be stationed in the country throughout the duration of the project. The Team Leader should be a graduate engineer with more than 15 years of experience in managing the construction and operation of HVAC transmission networks involving both transmission lines and substations.

b) Site Managers (Transmission line construction specialist)

Two site managers are to be provided – one based in Kyrgyz Republic and the other in Tajikistan. The position requires at least Bachelor degree in Engineering (civil, mechanical or electrical) with more than 10 years’ experience on metal works of construction features on installation of towers and stringing. The site managers shall assist the respective PIUs in overseeing the EPC contractors’ daily site activities; ensure the accuracy, timing, methodology and quality control of the works. They would be supported by local consultants.

c) HVAC Transmission line design specialist

One specialists (for both Tajikistan and Kyrgyz Republic) having experience of design/management of construction of HVAC transmission lines. These specialists, having minimum of Bachelor of Engineering degrees in Civil (Structural)/Mechanical, etc. with minimum 10 years’ of experience, shall assist the respective PIUs in finalizing and approving the design of transmission towers and materials, test plans etc.

e) Substation design specialist

In addition the consultant would need as and when needed substation design specialist to approve the substation layouts, protection and control philosophy proposed by the EPC contract and equipment design, etc.

f) Contracts specialist

One part time contract specialists having preferably have degrees in Law and shall have more than 10 years’ experience in the preparation, review and administration of complex construction contracts, especially pertaining to HVAC transmission line and substation projects.

g) Other experts

As and when needed other needed specialists are to be mobilized at the site by the Consultant.

These will include, but not be limited to, Civil Engineer (substations), Relays/Protection specialist, Controls Engineer, QA Expert, etc.

SUB-KEY STAFF

The Consultant shall provide at least the sub-key-personnel as detailed below in accordance with the provisions of this contract. Qualification & Experience of the following sub-key personnel shall not be considered for the purpose of evaluation of the consultant’s proposal, but this will not relieve the consultant from appointing well qualified and experienced personnel:

a) Logistics Specialist

b) Financial Accountant

c) Drawing Draftsman with knowledge of AutoCad.

1 1 1 9 1 9 2 1 0 12 0 12 3 1 0 10 0 10 4 1 1 21 1 21 5 1 0 10 0 10 6 Contracts Specialist 1 1 12 1 12 3 74

* Local Site Managers will assist

Owner's Engineer (AC Section) - International Staff

S.No Position/Title Number of Persons

Home Office Months

Total Person-Months

Pre- Construct ion & Pre-

Award

Construct ion

Pre-Construction & Pre-Award

(Home Office)

Construction (Field)

Project Manager Site Manager (KYG)*

Transmission Line Specialist Substations Design Specialist

TOTAL ESTIMATED EFFORT

Site Manager (TAJ)*

Figure 1: Project Schematic & Transmission Line Route

Figure 2: Institutional Arrangements Diagram

Terms of Reference – Owner’s Engineer (DC Facilities)

These Terms of Reference (TOR) consist of two parts. The first part gives broad information about CASA-1000 project which includes history, description and the institutional arrangements for its construction and operation. It also provides details of the various components of the CASA-1000 project and a separate sub-section which covers the detailed description of DC Facilities of the CASA-1000 project. The second part contains the objective and scope of services of the Owner’s Engineer which are limited to the DC facilities of the CASA-1000 project. For ease of understanding, the responsibilities have been divided into pre-construction phase (which is expected to last up to 6 months) and construction phase (expected to be of 42 months’ duration). At the end, details of the reporting relationships and other physical arrangements have been addressed. It may be noted that information about AC network, wherever provided in this document, is to provide an overall picture of the project while the scope of services under this TOR is limited only to the DC facilities.

I. Project information

Background:

Project Rationale and History

1. The Central Asia-South Asia Electricity Transmission and Trade Project (CASA-1000) aims to facilitate electricity trade between hydropower surplus countries in Central Asia and electricity deficient countries in South Asia by putting in place the commercial and institutional arrangements and the transmission infrastructure required for this trade. Sustained efforts to promote institutional development and socio-economic prosperity in the CASA-1000 countries are a high priority for the World Bank Group. The CASA-1000 countries vary significantly in terms of population numbers, economic size and development trajectories but they have complementary development needs and goals, especially in the energy sector.

2. The project envisages a transmission interconnection between the Central Asia and

South Asia Regions that would be used to export surplus electricity in the summer from existing generation capacity in Kyrgyz Republic and Tajikistan to energy-deficient Afghanistan and Pakistan. The feasibility study confirmed the soundness of the considerations that: (i) sufficient quantities of surplus electricity are available in the Central Asian countries (the Kyrgyz Republic and Tajikistan), even under conservative estimates of no new generation project; (ii) a significant need for electricity imports exists in South Asia (particularly Pakistan) to meet existing and projected demand; and (iii) the differences in the cost of electricity between the importing and exporting countries potentially provide a justifiable rationale to make transmission investments to support the electricity trade.

Project Description

3. The project will build a cross-border power trade facility, comprising about 475 km of 500kV HVAC transmission lines to carry power from Kyrgyz Republic to Tajikistan at Khoudjand; a 1300 MW HVDC converter in Tajikistan (at Sangtuda) and thereafter a 800km long ±500kV HVDC transmission link to a 1,300 MW terminal with HVDC converter facilities in Pakistan. The AC to DC convertor station would be designed to help power trade in any direction and would offer significant emergency system support to the national grids of the countries connected through HVDC system. The 300 MW Converter station at Kabul has been shelved and instead ,Tajikistan would supply 300 MW of power to Afghanistan through the existing 220 kV AC transmission line from Sangtuda to Pul-e-Khumri. A 500 MW BTB Converter station (not in the present OE scope) at Pul-e-Khumri will receive power from Tajikistan and transmit it further to Kabul and other provinces of Afghanistan.

4. The CASA-1000 feasibility study proposes a route for the line that takes into consideration cost effectiveness, security (especially in Afghanistan and Pakistan to avoid areas that would require significant demining), terrain to facilitate easier operations and maintenance and minimizing social and environmental impacts. For the most part the line traverses a manageable topography with the exception of a narrow and high mountain range in Afghanistan known as the Salang Pass. In the possible scenario of space constraint in that area, alternative options to bypass the Salang pass will be adopted. However, due to restructuring of HVDC terminal stations & based on preliminary survey, new route via Kunduz-Pul-e-Khumri-Kabul has been agreed upon. The final route of transmission line will be designed by the transmission line contractor within the first year of the contractor’s scope of work.

Figure 1 gives the project schematic and shows the route of the HVAC and HVDC transmission lines.

Project Implementation and Commercial Framework

5. The four project countries will be implementing CASA-1000 as a public sector project through their respective NTCs (national transmission companies) with support from IFIs (international financial institutions) and other donors. All the Project assets will be owned by the respective NTCs within the boundaries of their own country which are the following:

a. In Afghanistan - Da Afghanistan Breshna Sherkat (DABS)

b. In the Kyrgyz Republic - Joint Stock Company (JSC) National Electric Grid of

Kyrgyzstan (NEGK)

c. In Pakistan - National Transmission and Despatch Company (NTDC)

d. In Tajikistan - Open Joint Stock Holding Company Barki Tojik (BT)

6. One of the key characteristics of project design is the provision of open access by third-parties to the CASA-1000 transmission system for power trading during the non-supply period (or the period when the countries have committed to fully utilize the HVDC line). The CASA-1000 countries all agree to this principle and as such are defining and developing appropriate ‘open access’ rules and procedures to manage and facilitate these future transactions. This includes defining the participants in the transaction(s), access charges, main characteristics of the allocation mechanism of capacity to third parties, contracting arrangements, operational planning and congestions management including responsibility for dispatch and management of the transactions. Given the limited experience in the region on third party access, it is important to develop this in a phased manner.

Procurement Arrangements

7. The project procurement is complex and the nature of major procurement packages requires close coordination among the four implementing countries not only to ensure smooth procurement, but also to synchronize project implementation activities keeping in mind overall project sequencing. Market conditions and security concerns along the route of the proposed transmission line add to the complexity of the procurement plan and structure. Hence the project’s implementation arrangements include an intergovernmental mechanism for the procurement and contract management decision-making process for the joint procurement packages for the countries. The IGC has established through a resolution a Procurement Sub- Committee (PSC), comprising senior technical and procurement staff designated by each country. The PSC will carry out all the work needed on behalf of the parties to oversee and bring to successful closure the entire procurement process leading to award of the contracts by the NTCs. The NTCs will follow their respective corporate procedures for internal clearances of procurement and contract awards and assist the PSC in its work. This arrangement has helped in streamlining the joint procurement process and is expected to lead to timely award of all the major DS&I (design, supply and installation) contracts on the project.

8. The major procurements under the project include the HVDC stations in two countries, HVDC and HVAC transmission lines and O&M contracts. Though all the implementing agencies have some experience in managing such large and complex contracts, they do not have sufficient resources to help with drafting of the Pre- Qualification / bidding documents and the evaluation reports, hence, these functions are being facilitated by an international engineering consultancy company.

Procurement of all contracts , except for the O&M contract has been under way.

Progress of Procurements as below

• HVDC Converter Stations at Pakistan and Tajikistan – First stage /Technical bid expected to be opened in May’17.

• HVDC Transmission Line In Afghanistan – Under Finalization of Contract award

• HVDC (including AC part) Transmission Line in Pakistan – Bidding process for invitation of bids from pre-qualified bidders launched.

• HVDC Transmission Line and AC Transmission Line (Part) in Tajikistan –

Bidding process for invitation of bids from pre-qualified bidders launched.

• AC Transmission Line (Part) in Kyrgyzstan – Bidding process for invitation of bids from pre-qualified bidders launched.

• AC Transmission Line (Part) and Sub-station Extension in Tajikistan and Kyrgyzstan – Bidding process for invitation of bids being launched.

Project Components

9. The Project has been divided into three broad components: Component A - High Voltage Transmission Infrastructure, Component B – Project Management and Capacity Building, and Component C- Community Support Program. For the purposes of this assignment, which pertains to the responsibilities of Owner’s Engineer, the details of the High Voltage Transmission Infrastructure (Component A) are given hereunder:

(i) Sub-component A1 – High Voltage Direct Current (HVDC) Transmission Line which involves the construction of approximately 800 km of 500 kV HVDC overhead transmission line to interconnect the electricity network of Tajikistan, at the Sangtuda substation (s/s), with the Pakistan network, at the Nowshera substation.

The line will have a transmission capacity of 1,300 MW in either direction, using a bipolar and earth-return configuration and will consist mainly of self-supported lattice tower structures, conductors, and insulators.

(ii) Sub-Component A2 – HVDC Converter Stations which involve the engineering design, construction, and commissioning of two High Voltage Alternating Current (HVAC) to Direct Current (DC) converter stations at Sangtuda s/s (1,300 MW) in Tajikistan and Nowshera s/s (1,300 MW) in Pakistan. These convert AC power into DC, and vice versa, as needed. The s/s main equipment package includes specialized converter transformers, breakers, filtering equipment, inverters, controls, ground electrodes, and static and dynamic compensation equipment.

(iii) Sub-component A3 – Kyrgyz-Tajik HVAC Transmission Interconnection which includes the construction of about 475 km of 500 kV HVAC overhead transmission line to interconnect the electricity network of the Kyrgyz Republic, at Datka s/s, with the Tajikistan network, at the Khudjand s/s. About 450 km of the line will be in the Kyrgyz Republic and 25 km in Tajikistan. (Note: This section is not included in the scope of the DC Owner Engineer).

(iv) Sub-component A4– Tajikistan grid reinforcement which includes reinforcements in

Tajikistan including construction of 500 kV line from Regar s/s to Sangtuda s/s and other parts of the network necessary to ensure transfer of Tajikistan and Kyrgyz export power to Sangtuda HVDC station. (Note: This section is not included in the scope of the DC Owner Engineer).

10. Two consultancy firms (one for the HVDC network and another for the HVAC system) will be selected through a competitive process to act as Owner’s Engineers. These consultants will be responsible for assisting the CASA-1000 countries in supervising the EPC contracts until handing over and commercial operation of the facilities, certifying contractors’ payments, and assisting the IGC Secretariat with coordination among all relevant institutions. There will be a single EPC contract for the DC stations while it’s anticipated that the DC and AC transmission lines will be divided among a number of EPC contractors depending on the procurement rules of the financiers who will be funding these facilities. Figure 2 shows the institutional arrangements for the implementation of the project and indicates the lines of responsibility of the Owner’s Engineers.

The above is the detailed background and scope of the overall project and from this point onward details relating to the DC Network and the roles and responsibilities of the Owner’s Engineer (The Consultant) for the DC Network are being provided.

Details of the DC Network

DC Transmission Line Description of Scope

11. The scope of work of the +500 KV DC transmission line includes the engineering, design, manufacturing, testing, supply, installation and commissioning of the following:

a. 120 kms in Tajikistan;

b. 570 kms in Afghanistan; and

c. 110 kms in Pakistan.

d. Electrode Stations in the vicinity of Sangtuda and Nowshera.

e. Repeater Stations at required locations for communication link through

OPGW.

Transmission Line Routing

The proposed CASA 1000 Project Transmission Line routing is depicted in Figures A to D.

AC/DC Converter Stations Description of Scope

12. The HVDC Converter stations, which are an integral part of the CASA-1000 transmission system, rectify the power (from AC to DC) in order to transfer the Kyrgyz and Tajik power supplies through the HVDC line Nowshera where the converter stations would then invert the power from DC to AC in order to be absorbed into the Afghan and Pakistan grids, respectively. The scope of works of this package shall consist of engineering, design, manufacturing, testing, supply, installation and commissioning of the following:

a. Two DC Converter Stations

(i) 1,300 MW Converter Station at Sangtuda in Tajikistan with Ground

Electrode and Electrode line;

(ii) 1300 MW Convertor Station at Nowshera in Pakistan with Ground Electrode and Electrode line;

13. In addition, the following is included in the scope of work relating to the Line/Substation bay:

o In Pakistan Two nos 500 kV line bays complete with terminal equipment, protection coupler, HF cable, HF Coupler in NTDC 500 kV Nowshera SS.

.500 kV Bus extension interconnecting the Nowshera Converter Station to adjacent 500 kV NTDC station.

500 kV AC provision for interconnection to 500 kV Switchyard of NTDC. All protection and control equipment (along with cabling) for the interconnection bus will be in the scope of HVDC Converter station.

o In Tajikistan One number 500 kV Line bay complete with terminal equipment One number ICT bay for terminating 3*167 MVA, 500/220 kV ICT and one

167 MVA spare ICT 220 kV Switchyard Two number 220 kV line bay complete with terminal equipment (One at

Sangtuda Converter Station and other at Existing 220 kV Sangtuda Station).

For the bays (two nos 500 kV and two nos of 220 kV) Coupling device, carrier terminal equipment, protection coupler, HF cable and HF Coupler for local and remote end to be supplied by contractor, Sangtuda 220 kV and existing 220 kV Sangtuda Station will have DPLC in place of conventional PLCC with Digital protection coupler and Fibre optic terminal equipment.

Operations and Maintenance Contract

14. The scope of this component includes the following facilities :

a. Complete HVDC Converter Stations ( +/- 500 kV , 1300 MW Bi-Pole) at Tajikistan & Pakistan including AC & DC Switch yard and Station Auxiliaries

b. Sangtuda ( Tajikistan) – Nowshera ( Pakistan ) +/– 500 kV HVDC Transmission line

c. Electrode lines and Electrode Stations at Tajikistan and Pakistan

II. Consulting Services Objective and Scope

Objective

1. The services of an Owner’s Engineer (the Consultant) are required for the implementation phase of the CASA-1000 Project for the 2 (two) DC Converter Stations and the 800 km DC Transmission Line traversing the territories in Tajikistan, Afghanistan and Pakistan. The Consultant will assume the duties of the Project Manager as defined in the Design, Supply and Installation contract (also called EPC contract) for the HVDC converter station, three EPC contracts for the HVDC Transmission Lines in Afghanistan, one EPC contract each for the HVDC line Pakistan and Tajikistan respectively. This includes support in supervising implementation of the environment safeguards and social safeguards plans by the EPC contractors as specified in the EPC contracts and will make all necessary inputs and advice to project team and prepare relevant reports related to environment and social safeguard.

2. In addition, the Project Consultant will assist implementing agencies of the project in construction supervision reporting, other support for project implementation, audit and capacity building. Specifically, the Consultant’s support would be needed in the construction supervision of HVDC convertor stations and HVDC line.

3. The Consultant (OE) would also assist the NTCs and the Procurement Sub-Committee of CASA-1000 in procurement of the contract for the O&M services on the DC Facilities of the Project. The support for procurement of HVDC O&M Contract will be extended through Project Manager and his team of Site Managers (Converter and transmission line) and contract specialist.

4. The Employer(s) shall appoint Project Director for all its Facilities under CASA 1000

Project. Project Manager (Representative of Owner’s Engineer) along with Project Director(s) shall represent and act for and on behalf of the Employer(s) at all times during the performance of the EPC Contract for Coordinated decisions to ensure timely and integrated execution of the project. The Project Manager shall be the single point of contact for all communications between the Employer(s) and the Contractor(s).

Personnel requirements

5. The estimated time of this assignment is 6 months pre-construction and a 42-month construction period. The minimum effort of Key Expert is 220 man-months (18.5 man-months in Home-Office and 201.5 man-months on site). These services will be needed over a period of approximately 48 calendar months (6 calendar months for Pre- Construction activities and 42 calendar months for construction supervision). In addition, Minimum 72 man-months of Non-Key Experts are needed for local and professional support.

Scope of Work:

Pre-Construction Phase

6. During this period the Consultant will advise and assist the 3 NTCs in the finalization of detailed design of the project by undertaking the following tasks:

Review the design of DC facilities to be submitted by the EPC contractors to ensure its technical adequacy for the project. Harmonize the various design parameters of the facilities to be built by the various EPC contractors.

Construction phase

7. The Consultant shall assume the responsibility of the Project Manager and act as the prime liaison between the EPC contractors and the NTCs for all matters relating to their contracts. He shall manage and provide oversight during manufacturing and installation according to the approved engineering drawings and specifications as well as all applicable codes and standards. This shall include all activities from startup to commissioning of the project and encompass the work scopes of all the suppliers, contractors and vendors who are involved in the project. He shall also assist the NTCs in securing the necessary permits to enable the EPC contractors to smoothly carry out the construction services on the various sites of the project. For the fulfillment of these broad responsibilities, the Consultant shall be carrying out the following tasks:

Front-end Activities

(i) Prepare a master implementation plan of the project which will be used to guide the

EPC contractors in the development of their supply, installation and construction plans. The aim is to ensure that all project activities are integrated such that the project is completed according to the schedule.

(ii) Participate in pre-construction meetings with the EPC contractors and PIUs to discuss and finalize work programs for the implementation of various components of the project and to agree on lines of reporting, administrative arrangements, etc.

(iii) Prepare a project monitoring scheme (which will include technical, physical and financial details) and share with the PIUs for acceptance by the NTCs. Set up an acceptable methodology for the regular and effective monitoring of the project costs and reporting them to the PIUs.

(iv) Develop and have a common agreement on the formats to be used for reporting project progress so that it covers all aspects of the project, viz. design, supply, installation, commissioning, cost, time-line, etc.

(v) Develop, recommend and reach agreement on procedures for adequate follow-up of production and testing at the manufacturer site, and for the timely supply and delivery of materials and equipment to the project sites.

(vi) Develop and execute a plan to provide necessary training to the PIU staff of the various NTCs in the preparation of reports required by the project financiers through on-the-job training.

Ongoing Activities

(vii) Supervise the installation, testing and pre-commissioning activities on the project.

(viii) Assist the PIUs and/or the procurement sub-committee of the IGC (depending on the importance e.g. for converter stations) during the inspection/acceptance tests that will take place at the manufactures’ sites.

(ix) Assist the PIUs in settling any disputes among the various parties arising during the implementation of the project.

(x) Review and recommend for approval to the PIUs the EPC contractors’ supply and installation schedules or their proposed revisions.

(xi) Assist the authorized representatives of the concerned employer in carrying out inspection of material and equipment at the manufacturers’ works as per approved drawings and technical specifications as given in their respective contracts.

(xii) Undertake site supervision to verify project quality, adherence to time schedule and quantity utilization as indicated in the submitted invoices.

(xiii) Assess the adequacy of all inputs such as materials and labor that are deployed by the EPC contractors and their methods of work in relation to the required progress, and when required, take appropriate action in order to rectify and to expedite progress. For this purpose use as benchmarks the contractors’ commitments as given in their submitted bids and in the signed EPC contracts.

(xiv) Track the progress of project execution based on the CPM/PERT charts to be submitted by the EPC contractors.

(xv) Assist the PIUs in initiating action in case of slow progress by contractors and/or violation of the contractors’ obligations, if any, as per conditions of the contract.

(xvi) Assist the PIUs in exercising strict financial control vis-a-vis physical progress on the various project activities.

(xvii) Recommend to the PIUs the payment against contractors’ invoices based on completion of contractual milestones and approve/clear claims and variation orders submitted by the contractors.

(xviii) Examine and make recommendations on all claims from the contractors for time extension, extra compensations, extra work or expenses or other similar matters including determination of new rates when required.

(xix) Determine the amount to be added to, or deducted from payments to the contractor for any additional work or for work omitted respectively.

(xx) Inform the PIU on problems or potential problems which may arise in connection with the implementation of the contract and make recommendations to their possible solutions

(xxi) Assist PIUs to compile systematic records of the contractor’s site activities, and prepare and maintain inspection/engineering reports and records to adequately document the progress and performance of the work.

(xxii) Upon notice of all completion received from the Contractor, inspect the works and inform contractor and client, in writing,…