Wireless_Survey.pdf
PDF 205 KB Posted
- Attached to
- Wireless Survey
- Solicitation number
- 71311119Q0006
- Issued by
-
Overseas Private Investment Corporation
About this file
Performance Work Statement
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_4-_OPIC_Terms_and_Conditions.pdf | ||
| Wireless_Survey_Worksheet.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Overseas Private Investment Corporation
Wireless Site Survey RFQ
Performance Work Statement
June 5, 2019
Overseas Private Investment Corporation 1100 New York Avenue NW, Washington, DC 20005
1. Overview
The OPIC Office Chief Information Officer (OCIO) leverages information technology, management, and consulting resources to support OPIC’s goals to grow the OPIC portfolio and development impact, increase environmental benefit, foster productivity and efficiency and build long-term support for OPIC to advance U.S. foreign policy objectives. The current WiFi environment no longer provides the security, and protocols demanded by the enterprise.
Technologies have greatly improved over the years and OPIC desires a Wireless study to ensure full coverage on floors 10, 11, and 12 and half the 4th floor.
2. Scope
This PWS describes the objectives that need to be met in order to prepare OPIC to successfully architect and deploy new Wi-Fi technology within the OPIC corporate offices.
A wireless survey will be performed on floors 10, 11, 12 and one-half of the 4th floor. The vendor will evaluate the current Wi-Fi placement and attempt to realize the current cabling and mounting infrastructure, and supplement with additional locations as required by the survey.
OPIC will utilize 802.11ac, 802.11n, 802.1ax, 802.11g, 802.11a, and 802.11b
3. Period of Performance
The period of performance is forty-five days from contract award.
4. Assumptions
OPIC will provide the vendor with current building blueprints and access to each floor. OPIC will provide vendor with appropriate Access Point.
5. Place of Performance
Primary place of performance is at the OPIC Headquarters in Washington, DC. Documentation may be performed remotely as directed or with the approval of the Government Contracting Officer Representative (COR).
6. Constraints
Work performed under this task order may experience the following constraints:
• Regulatory and policy requirements are subject to change over the course of this task order and may impact current policies and operations.
• Compliance with all Federal IT- related policies and standards is required.
• All contractors performing work under this contract must be approved via Federal
Government regulations and/or processing.
• The contractor must establish and document configuration settings using Center for
Internet Security (CIS) or comparable federal and OPIC approved entity for information products employed within the information system(s) using organization defined or to-be defined security configuration checklists that reflect the most restrictive mode consistent with operational requirements; implement the configuration settings;
identifies, documents and approves any deviations from the established configuration settings for organization-defined information system components based on organization-defined operational requirements and monitor and control changes to the configuration settings in accordance with organizational policies and procedures.
7. Vendor Organizational Capabilities Vendor must provide a brief description of its entity (including business locations, size, areas of specialization and expertise, client base and the Vendor organization’s experience and history with Wireless services, including, but not limited to:
1. Years of experience performing wireless site surveys,
2. Number of wireless site surveys performed in the last 24 months,
3. Types of wireless site surveys performed in the last 24 months (i.e., data, voice, outdoor mesh, location, etc.), and
4. Number of and availability of personnel to perform wireless site surveys.
5. Vendor personnel certified, by certification (i.e., Cisco Unified wireless site survey (CUWSS), Ekahau Certified Survey Engineer (ECSE), Airmagnet Certified Training, etc.), in providing wireless site surveys.
8. Warranty
The Vendor shall provide a 90 day warranty on work performed to assure the Vendor AP placement is effective and provides adequate coverage. If the AP placement does not work and at OPIC’s sole discretion, the Vendor shall correct placement at no additional cost until the AP provides adequate coverage. For the avoidance of doubt, adequate coverage means a correctly implemented WiFi network with 99.9% availability.
Samples Provided
In its Response, the Vendor shall provide the following documents:
1. A sample predictive site survey;
2. A sample pre-deployment on-site survey;
3. A post implementation verification survey; and
4. Any questionnaires or other documentation that must be completed prior to the site survey.
All samples must be for new wireless network installations conducted in the last 24 months.
Business and Technical Requirements
OPIC’s Technical Environment
The Vendor must be able to operate within and provide wireless site survey services that align with OPIC’s technical wireless environment, which includes:
1. Aruba Meridian BlueTooth Wayfinding
2. Aruba AP-515 802.11ax 5.4 GBs TAA compliant
3. Cisco 9000 series switches
4. HPE Aruba ClearPass
Wireless Predictive Site Survey Requirements
The Vendor must perform wireless predictive site surveys that at a minimum achieve the following requirements:
1. Achieve the best possible Wireless Local Area Network (WLAN) performance for the customers intended use.
2. Minimize co-channel interference.
3. Determine the quantity and best locations for access points.
4. Document installation characteristics.
5. Ensure redundant coverage to support seamless roaming.
6. Provide all wireless predictive site survey deliverables.
Wireless Pre-deployment On-Site Survey Requirements
The Vendor must perform wireless pre-deployment on-site surveys that at a minimum achieve the following requirements:
1. Achieve the best possible Wireless Local Area Network (WLAN) performance for the customers intended use.
2. Minimize co-channel interference.
3. Determine the quantity and best locations for access points.
4. Locate unauthorized “rogue” access points and neighbor networks.
5. Document installation characteristics.
6. Ensure redundant coverage to support seamless roaming.
7. Provide all wireless site survey deliverables.
Post Implementation Verification Requirements
The Vendor must perform post implementation verifications that wireless implementations have achieved the designed and documented wireless site surveys requirements.
Service Timelines
The Vendor must perform requested wireless site surveys and post implementation verifications services within 30 business days from request, unless approved in writing by OPIC for a different timeline.
Predictive Wireless Site Survey List of Deliverables
At a minimum, the Vendor shall provide to OPIC the following Deliverables upon completion of a predictive wireless site survey:
1. Executive Summary – Overview of the study;
2. Study Methodology – How the study was performed;
3. Customer Expected Use Cases;
4. Existing Deployments – A review of currently deployed wireless networks;
5. Structural Material Analysis – Installation considerations;
6. Analysis of Existing Infrastructure – Physical and logical interface design considerations;
7. Map of site with coverage area, all access point placements and antenna types; and
8. Suggested bill of materials needed for implementation (i.e., cables, mounting brackets, etc.) The Bill of materials (BOM) should list the recommended wireless hardware, pictures of mounting locations, configurations, channel plans, integration plans, security requirements, and data cabling necessary for implementation for products available on current state contracts.
Wireless Pre-deployment On-Site Survey List of Deliverables
At a minimum, the Vendor shall provide to OPIC the following Deliverables upon completion of a pre-deployment on-site wireless site survey:
1. Executive Summary – Overview of the study;
2. Study Methodology – How the study was performed;
3. Customer Expected Use Cases;
4. Spectrum Analysis – Results of frequency scan/spectrum analysis of the site;
5. Existing Deployments – A review of currently deployed wireless networks;
6. Structural Material Analysis – Installation considerations;
7. Analysis of Existing Infrastructure – Physical and logical interface design considerations;
8. Map of site with coverage area, all access point placements and antenna types; and
9. Suggested bill of materials needed for implementation (i.e., cables, mounting brackets, etc.)
Vendor Wireless Site Survey Audits
The Vendor must allow OPIC designated staff to escort and audit wireless site survey services as requested. This includes reviewing the process documentation, tools used, analysis done, and deliverables developed.
Service Area
The Vendor must be able and willing to travel OPIC headquarters.
Qualified Personnel
The Vendor must be responsible to provide qualified personnel who are trained and experienced in wireless site survey services. Vendor will ensure that the employees assigned to assist OPIC are a certified wireless site survey engineers. Vendor is responsible for providing the qualified persons to perform the work required under any subsequently awarded contract.
Vendor personnel must be professional in appearance, have a proven background in conducting wireless site surveys and include all equipment and supplies to ensure the survey is done completely and accurately. OPIC may request that Vendor remove and replace any Vendor employee for any reason, and Vendor shall remove any such employee and provide appropriate replacements with OPIC’s approval. Vendor agrees to maintain a consistent skill level among all replacement personnel.
| 1. Overview |
| 2. Scope |
| 3. Period of Performance |
| 4. Assumptions |
| OPIC will provide the vendor with current building blueprints and access to each floor. OPIC will provide vendor with appropriate Access Point. |
| 5. Place of Performance |
| 6. Constraints |
| 7. Vendor Organizational Capabilities |
| 8. Warranty |
| Samples Provided |
| Business and Technical Requirements |
| OPIC’s Technical Environment |
| Wireless Predictive Site Survey Requirements |
| Wireless Pre-deployment On-Site Survey Requirements |
| Post Implementation Verification Requirements |
| Service Timelines |
| Predictive Wireless Site Survey List of Deliverables |
| Wireless Pre-deployment On-Site Survey List of Deliverables |
| Vendor Wireless Site Survey Audits |
| Service Area |
| Qualified Personnel |
File details come from the government source that posted it.