This is a Specification for Dockside Repairs for the USCGC MUNRO (WMSL-418) during FY2027, developed as Draft-0 on November 5, 2026. The specification outlines 12 work items for maintenance and repairs to be performed at the vessel's homeport in Alameda, California, with an anticipated period of performance from July 27, 2027 through October 27, 2027. Work items include fire detection system inspection and testing, fire prevention planning, miscellaneous system relief valve certification, refrigeration plant hose renewal, compressed air receiver maintenance, stern boat launch and recovery equipment servicing, helicopter hangar door preservation, incinerator inspection, oily water separator maintenance, deck covering repairs and renewal, installation of a new Elex dry air compressor system, and slip-resistant deck covering renewal in hangars. The contractor must supply all necessary labor, materials, services, equipment, supplies, power, and facilities to complete the work in compliance with Coast Guard specifications and applicable industry standards including NFPA 72, SFLC Standard Specifications, and AWS welding codes.

The specification mandates strict compliance with fire prevention and safety protocols, environmental protection requirements, preservation standards per SFLC Std Spec 6310, and welding procedures per SFLC Std Spec 0740. Critical inspection items requiring completion within the first 25 percent of the contract period include work on the fire detection system, refrigeration plant hoses, oily water separator system, and deck covering in hangars. The contractor must appoint qualified technical representatives for specialized systems, submit detailed work plans for approval, and provide comprehensive inspection reports and certifications. Government-furnished property includes air compressors, dryers, receivers, electronic water drain valves, gauges, a heated pilot house window, and sensor kits with estimated costs totaling approximately $29,900. The specification requires contractors to meet stringent quality assurance requirements for preservation work, including surface profile measurements, soluble salt conductivity testing, and coating thickness verification, with detailed QA inspection forms provided for documentation and compliance verification.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC MUNRO (WMSL 755)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2027

Developed By: John Webber

(Draft-0, 5 November 2026)

USCGC MUNRO (WMSL-418) DOCKSIDE AVAILABILITY FY2027

ii (Draft-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. ix Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Fire Detection System, Inspect and Test WORK ITEM 2: Fire Prevention, Provide WORK ITEM 3: Miscellaneous System Relief Valves, 5 Year Certification WORK ITEM 4: Refrigeration Plant Flexible Hoses, Renew WORK ITEM 5: Compressed Air Receivers, Clean, Inspect and Test WORK ITEM 6: Stern Boat Launch and Recovery, Level II WORK ITEM 7: Helo Hangar Door Curtain Assembly, Preserve (100 %) WORK ITEM 8: Incinerator, Inspect and Test WORK ITEM 9: Oily Water Separator (OWS) System, Inspect and Groom WORK ITEM 10: Deck Covering (Polymeric), Repair and Seal WORK ITEM 11: Elex Dry Air Compressor Equipment, Install WORK ITEM 12: Deck Covering (Slip-Resistant) Hangars, Renew iii (Draft-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Draft-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 418A-WMSL 100-001, Rev C, General Arrangements Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-100-006, Rev A, Inboard and Outboard Profiles Coast Guard Drawing 418A-WMSL-185-001, Rev B, Air Compressor and Receiver Foundation

Installation Coast Guard Drawing 418A-WMSL-202-001, Rev D, Elex Dry Air Compressor Control Installation Coast Guard Drawing 418A-WMSL-320-013, Rev C, Elex Dry Air Compressor Power Installation Coast Guard Drawing 418A-WMSL-542-001, Rev B, JP-5 System Diagram Coast Guard Drawing 418A-WMSL-551-001, Rev A, Compressed Air Diagram Coast Guard Drawing 418A-WMSL-551-001, Rev A, Compressed Air Diagram Coast Guard Drawing 418A-WMSL-551-001, Rev B, Compressed Air Diagram Coast Guard Drawing 418A-WMSL-551-003, Rev E, Elex Dry Air Compressor and Equipment

Installation Coast Guard Drawing 418A-WMSL-555-001, Rev A, AFFF System Diagram Coast Guard Drawing 418A-WMSL-588-001, Rev A, Aviation Facilities General Arrangements Coast Guard Drawing 418A-WMSL-593-001, Rev A, Bilge & Oil Pollution Control System Diagram Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 418A-WMSL-801-012, Rev A, Booklet of General Plans NSC 7 Coast Guard Drawing 418A-WMSL-801-1, REV A, Booklet of general plans Coast Guard Drawing 418-WMSL-100-001, Rev C. General Arrangements Coast Guard Drawing 418-WMSL-540-002, Rev A, Diesel Engine and Gas Turbine LO fill, Trans, &

Service System Coast Guard Drawing 750 WMSL 169-001, Rev F, Helo Hangar Door Installation (ASC169001) Coast Guard Drawing 750 WMSL 588-504, Rev B, Tiedown Installation for Navy H60S/H60R Helo

(Stratton) Coast Guard Drawing 750-WMSL_520_1, Rev H, Seawater Cooling System Diagram Coast Guard Drawing 750-WMSL_520_1, Rev H, Seawater Cooling System Coast Guard Drawing 750-WMSL-085-025, Rev -, Compartment Areas & Volumes NSC 3 & follow

(AS3085012)

Coast Guard Drawing 750-WMSL-100-035, RevRev L v (Draft-0)

ANS : Updated.

L, Unit 2340 Structure Main Deck to 01 Level - Fr 52 to Fr 64 (ASC100234) Coast Guard Drawing 750-WMSL-100-039, Rev M, Unit 3140 Structure Mn Dk to 01 Lvl - Fr 64 to Fr

76 (ASC100314)

Coast Guard Drawing 750-WMSL-300-002, Rev C, Electrical Standard Details Coast Guard Drawing 750-WMSL-300-024, Rev C, Unit 2240 - Main Dk Fr 44 to Fr 52 Arr of Elect Eqpt

(ASC300224)

Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets

(ASC436010)

Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic

(ASC436028)

Coast Guard Drawing 750-WMSL-505-001, Rev C, List of Relief Valves Coast Guard Drawing 750-WMSL-505-006, Rev D, List of Hoses Coast Guard Drawing 750-WMSL-506-001, Rev G, Overflow/Air Escapes Sounding Tubes Diagram Coast Guard Drawing 750-WMSL-506-037, Rev B, OVFL/AE & SNDG Tubes system Unit 4110 Coast Guard Drawing 750-WMSL-506-515, Rev -, Vent Modifications IWO Scuttle 02-29-1 Install Coast Guard Drawing 750-WMSL-508-001, Rev C, Piping And Machinery Insulation And L/M Coast Guard Drawing 750-WMSL-512-536, Rev -, HVAC Mods for POU Compressor Install Coast Guard Drawing 750-WMSL-516-001, Rev E, A/C & Refrigeration Piping Diagram (ASC516001) Coast Guard Drawing 750-WMSL-516-002, Rev K, Chilled Water System Diagram Coast Guard Drawing 750-WMSL-516-035, Rev -, Chilled Water System Diagram WMSL 750 Only Coast Guard Drawing 750-WMSL-516-042, Rev-, Chilled Water System Diagram (SRD)(NSC8) Coast Guard Drawing 750-WMSL-516-045, Rev B, Chilled Water System Diagram WMSL 751 Only Coast Guard Drawing 750-WMSL-516-047, Rev A, Chilled Water System Diagram WMSL 752 Only Coast Guard Drawing 750-WMSL-516-049, Rev B, Chilled Water System DWG NSC 4 Coast Guard Drawing 750-WMSL-516-051, Rev B, Chilled Water System DWG NSC 5 Coast Guard Drawing 750-WMSL-516-052, Rev A, Chilled Water System DWG NSC 6 Coast Guard Drawing 750-WMSL-516-055, Rev-, Chilled Water System (SRD) (NSC 7) Coast Guard Drawing 750-WMSL-516-057, Rev-, Chilled Water System (SRD) (NSC 10) Coast Guard Drawing 750-WMSL-520-020, Rev B, Seawater Cooling System Diagram WMSL 750 Only Coast Guard Drawing 750-WMSL-520-022, Rev B, Seawater Cooling System Diagram WMSL 751 Only Coast Guard Drawing 750-WMSL-520-023, Rev B, Seawater Cooling System Diagram WMSL 752 Only Coast Guard Drawing 750-WMSL-520-024, Rev B, Seawater Cooling System Diagram Selected Record

Drawing NSC 4.

Coast Guard Drawing 750-WMSL-520-025, Rev B, Seawater Cooling System Diagram Selected Record

Drawing NSC 5.

Coast Guard Drawing 750-WMSL-520-026, Rev B, Seawater Cooling System Diagram Selected Record

Drawing NSC 6.

Coast Guard Drawing 750-WMSL-520-027, Rev B, Seawater Cooling System Diagram (NSC 7).

Coast Guard Drawing 750-WMSL-520-028, Rev B, Seawater Cooling System Diagram (SRD) (NSC 8).

Coast Guard Drawing 750-WMSL-520-029, Rev B, Seawater Cooling System Diagram (SRD) (NSC 10).

Coast Guard Drawing 750-WMSL-530-001, Rev G, Potable Water Systems Diagram vi (Draft-0)

Coast Guard Drawing 750-WMSL-530-044, Rev A, Potable Water Diagram Selected Record Dwg NSC 9 Coast Guard Drawing 750-WMSL-540-001, Rev G, Fuel Oil Diagram Coast Guard Drawing 750-WMSL-540-079, Rev -, Diesel Engine and Gas Turbine LO fill, Trans, &

Service System (SRD) (NSC 7) Coast Guard Drawing 750-WMSL-540-081, Rev A, Diesel Engine and Gas Turbine LO fill, Trans, &

Service System (SRD) (NSC 8) Coast Guard Drawing 750-WMSL-540-081, Rev A, Fuel Oil Diagram (NSC 10) Coast Guard Drawing 750-WMSL-540-083, Rev -, Diesel Engine and Gas Turbine LO fill, Trans, &

Service System (SRD) (NSC 10) Coast Guard Drawing 750-WMSL-551-051, Rev -, Compressed Air Diagram (SRD) (NSC 8) Coast Guard Drawing 750-WMSL-551-052, Rev A, Compressed Air Diagram Selected Record Drawing

NSC 9

Coast Guard Drawing 750-WMSL-551-053, Rev -, Compressed Air Diagram (NSC 10) Coast Guard Drawing 750-WMSL-583-004, Rev K, Stern Launch & Recovery Arrangement & Details

(ASC583004)

Coast Guard Drawing 750-WMSL-588-001, Rev -, Aviation Facilities General Arrangements

(ASC588001)

Coast Guard Drawing 750-WMSL-588-503, Rev E, Tiedown Installation for Navy H60S/H60R Helo

(Waesche Only) Coast Guard Drawing 750-WMSL-593-011, Rev B, Solid Waste System Schematic (ASC593026) Coast Guard Drawing 750-WMSL-625-001, Rev C, Window Arrangement and Details Coast Guard Drawing FL-1204-3, Rev A, Fleet Welded Padeyes and Links Coast Guard Drawing FL-1702-11, Rev -, Inspection Of Sheaves WMSL MH-60R/S Hangar Painting Guidance, 2018, Schlemmer G.W., AIR 4.8.1.5

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual Coast Guard Commandant Instruction (COMDTINST) M10360.3 (Series), Coatings and Color Manual Coast Guard Technical Publication (TP) 7087, Jan 2022, Pressure Relief Valve Coast Guard Technical Publication (TP) 7181, 02-OCT-07, Helo-Hangar Doors Coast Guard Technical Publication (TP) 7346A, SWBS 593, Mar 2022, Bilge Water Separator Ultra-Sep Coast Guard Technical Publication (TP) 7809, SWBS 583, Apr 2021, Boat Retrieval Equipment – Boat

Hoist, Centerline & Carriage Winches Coast Guard Technical Publication (TP) 7946, SWBS 593, May 2021, Incineration Plant - Installation, Operation, Maintenance & Spare Parts Coast Guard Technical Publication (TP) 9556, SWBS 436, Feb 2022, Fire and Smoke Detection System

(For Hull 755) Fire Prevention and Response Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements vii (Draft-0)

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 0850 (SFLC Std Spec 0850), 2022, General Requirements for Drawing Preparation

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response

Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior

Deck Covering Systems

OTHER REFERENCES

Air Capable Ship Aviation Facility Bulletin 1L (2009).

American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A, 2024, Personnel Qualification and Certification in Nondestructive Testing American Society for Nondestructive Testing (ASNT), Standard No. ANSI/ASNT CP-189-2024, 2024, ASNT Standard for Qualification and Certification of Nondestructive Testing Personnel American Welding Society (AWS) B1.10M/ B1.10, 2016, Guide for Nondestructive Examination of

Welds American Welding Society (AWS) B1.11M/B1.11, 2015, Guide for the Visual Examination of Welds American Welding Society (AWS) D1.1/D1.1M, 2025, Structural Welding Code – Steel ASTM International (ASTM) D3359-23, 2023, Standard Test Methods for Measuring Adhesion by Tape

Test ASTM International (ASTM) F1836M, Reapproved 2007, Standard Specification for Stuffing Tubes, Nylon and Packing Assemblies (Metric) ASTM Internationals (ASTM) G46-21, 2021, Standard Guide for Examination and Evaluation of Pitting

Corrosion Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment Code of Federal Regulations (CFR) Title 29, Part 1915, Subpart E, Sep 2015, Scaffolds, Ladders and

Other Working Surfaces MIL-C-24757, Nov 1990, Cloth, Fiberglass, Coated viii (Draft-0)

MIL-D-16791, Jan 1993, Detergents, General Purpose (Liquid, Nonionic) MIL-DTL-24643, Oct 2009, Cables, Electric, Low Smoke Halogen-Free, For Shipboard Use, General

Specification for MIL-PRF-24176C, 2020, Cement, Epoxy, Metal Repair and Hull Smoothing MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric MIL-PRF-24667C, May 2008, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-PRF-24667D, 2021, Coating System, Non-Skid, for Roll, Spray, or Self-Adhering Application MIL-STD-1310, Sep 2009, Shipboard Bonding, Grounding, and Other Techniques for Electromagnetic

Compatibility and Safety MIL-STD-1689A, 1990, Fabrication, Welding, and Inspection of Ships Structure MIL-STD-2003-2, Sep 2009, Electric Plant Installation, Standard Methods for Surface Ships &

Submarines (Equipment) MIL-STD-2003-3, Sep 2009, Electric Plant Installation, Standard Methods for Surface Ships &

Submarines (Penetrations) National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and Signaling Code NAVAIR ENGCEN Bulletin 1, Rev J; Air Capable Ship Aviation Facilities Resume NAVAIR SI-ACS-AFB-1P, 2020, Air Capable Ship Aviation Facility Certification No. 1P Naval Sea System Command (NAVSEA) Technical Manual (TM) S6435-TP-MMI-010, Rev 5, Angle

Relief Valves BCS Series for Air/Gas Service Naval Sea Systems Command (NAVSEA) Technical Manual (TM) S6435-TL-MMI-010, Rev 9, Angle

Relief Valve – Type D50 Naval Sea Systems Command (NAVSEA) Technical Manual (TM) S6435-UU-MMO-010, Rev 5, Angle

Relief Valve – Model D50FF NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2016, Solvent Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 11 (SSPC-SP 11), 2016, Bare Metal Power Tool Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2020, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.2 (SSPC-SP 2), 2004, Hand Tool Cleaning The Society for Protective Coatings (SSPC) Surface Preparation Specification No.3 (SSPC-SP 3), 2024, Power Tool Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 10 (WAB)/NACE WAB-2, 2015, Near-White Metal Wet Abrasive Blast Cleaning

US Environmental Protection Agency Method 1664, Feb 1999, N-Hexane Extractable Material and Silica Gel Treated N-Hexane Extractable Material by Extraction and Gravimetry.

ix (Draft-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

6 N Spring, Sheave NSN: 5360-01-672-

8829 PN: P2-965-

8 ea. 185.00

6 N Pins, Spring NSN: 5315-01-672-

8220 PN: B2-066-

8 ea. 400.00

6 N Pins, Cotter NSN: 5315-01-672-

8187 PN: 81-E-

8 ea. 1.50

6 N Flat Washer, 2 ½� Nominal, TY A 5�OD x 2 5/8� ID x 0.238� THK

NSN: 5310-01-672-

8737 PN: 61-E-16

8 ea. 1.50

6 N Jacking Bolt, Sheave NSN: 5306-01-672-

9033 PN: B2-033-

8 ea. 275.00

6 Y *CB-OTH Mark IV N/A 1 ea. N/A 6 Y *Long Range Interceptor II N/A 1 ea. N/A 9 Y Monitor, Smart Bilge NSN: 2040-01-600-

0112 1 ea. 4,700.00Â

11 N Atlas Copco SF6 + P 7.5 HP, Oil Free Scroll Air Compressor, 30 Inch X 26 Inch X 33 Inch, Approximate Weight 350 Lbs.

8153611358 2 ea. 14,000

11 N AtlasCopco,CD+10,21.SCFM@100psi,160 psi(g) Heatless Regenerative Desiccant Air

Dryer,-40 Deg. F Dew Point, 115/1/60, 1/2" Connection Size (NPT), 16 inch L x

14 inch W x 43 inch H, 82 lbs

8102368843 2.ea. 4,500

11 N Atlas Copco LH120-200,120 Gallon, Receiver 25 Inch D X 67 Inch L, Approximate Weight 316 Lbs.

A10033 1 ea. 1,300

11 N Atlas Copco Electronic Water Drain Valve (IWD), 230 PSI, 138 CFM, 6.7 Inch X 2.8

Inch X 4.5 Inch, 115V

810204812 2 ea. 500

11 N Atlas Copco Gauge Kit for receiver, Kit:

SRV-GAG

1280585377 1 ea. 200.00

11 N Window, Heated, Fixed, Pilot House with Wiper Assembly Wynn type C by Cornell-

Car*

CC-10082-1 1 ea. 2,500.00

11 N Kit PDP Sensor CD5-30+ 8092266823 1 ea 1,900 *Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Draft-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

1 Fire Detection System, Inspect and Test

4 Refrigeration Plant Flexible Hoses, Renew

9 Oily Water Separator (OWS) System, Inspect and Groom

12 Deck Covering (Slip-Resistant) Hangars, Renew xi (Draft-0)

PRINCIPAL CHARACTERISTICS

418' WMSL

PHYSICAL

Length overall 418' 0" Length between perpendiculars 390' 0" Maximum beam 54' 0" Beam @ 01 level 47' 9-1/8" Depth (01 level @ side to baseline) 39' 2-3/4" 01 deck camber foredeck 1/4" in 1'-0" Minimum berth depth 20' 0" Height of highest projection Approximately 119' Draft, design 14.40' Design displacement 3925 long tons

MACHINERY

Two diesel engines MTU 20V, 20-cylinder 9,730 SHP each One gas turbine General Electric LM2500; 29,500 SHP Type of propulsion CODAG Electrical system 24 Volt DC Two controllable pitch propellers Rolls-Royce 5 blade, 14' 0" diameter; 229 RPM max Two reduction gears RENK One cross connect gear RENK

HULL

Hull material 5086 Aluminum HSLA-80 Steel ABS EH 36 Steel

ABS AH 36

Frame spacing FWD of FR 9 2' 3" FR 9 to FR 10 6' 9" FR 10 to FR 98 4' 1" FR 98 to FR 99 3'-8"

ELECTRICAL

Power Three 1360 kW, 450 V, 60 Hz, 3 Phase, 1800 RPM Caterpillar 3512B diesel engines with Baylor ship service generators Shore tie cable Seven MIL-C-24368/2 (NATO) shore power receptacles, 400 A each

TANK CAPACITIES

Diesel oil 220,359 gal Fresh water 12,454 gal JP-5 Fuel 35,182 gal

1 (Draft-0)

00000_0226_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for

Fabrication, Welding, and Inspection of Submarine Structure

2 (Draft-0)

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

APM: Select the delivery option for the Fire Plan from the options below:

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

Or

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

A-Team: Determine whether the Contractor or the Coast Guard will provide fire watches; then select the applicable paragraph 3.2 (fire watch, fire extinguishers, or the combination of both requirements), and delete the others. Under normal circumstances, for all cutters, fire watch personnel for contract work will be provided by ship's force with the contractor providing fire extinguishers. For situations involving a small cutter crew (such as WLIC and WLR tenders) and large amounts of hot work or multiple shift work, the A-team may consider the requirement for contractor provided fire watch personnel or a combination of both fire watch and fire extinguishers.

3.2 Contractor-provided fire watch personnel. The Contractor must provide fire watch personnel and equipment.

Or

3.2 Contractor-provided fire extinguishers. The Contractor must provide portable fire extinguishers.

Or

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in

3 (Draft-0) lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

The following subparagraphs (3.4.1-3.4.3) are applicable to 270B class cutters only. If this availability is not for a 270B class cutter, than paragraphs 3.4.1, 3.4.2, and 3.4.3 must be removed along with the NAVSEA reference TP 1688 from the list of references and the NOTE immediately following these paragraphs.

4 (Draft-0)

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Strenx 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Strenx 900, all welding procedures and welder qualifications for welding Strenx 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Strenx 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

APM: Select the appropriate 3.5.1 paragraph(s) for the location of the planned availability. Delete the other 3.5.1 paragraph(s).

3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

Or

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

5 (Draft-0)

APM: For availabilities to be conducted at Coast Guard facilities, the Contractor must be provided the USCG Activity Generator Status for the Coast Guard Facility.

Provide the Generator Status code in paragraph 3.5.1.1, and other applicable environmental permits in paragraph 3.5.1.2 below.

Ensure the CG Base or Sector Environmental POC for this is actively engaged in the early planning for this availability to ensure the Facility can accommodate the planned work.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is _________.

APM: If applicable, provide the list of unit-specific plans and permits required, and provide description of the specifics of these plans in paragraph 3.5.1.2. Otherwise delete paragraph 3.5.1.2.

CG Base or Sector Environmental POC must provide these details.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

APM: Retain 3.6.2 and beyond paragraphs for all availabilities.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral

6 (Draft-0) position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

A-Team: For availabilities at Navy facilities, be aware that Navy facilities have local base instructions (for example, NAVFAC P-307 for Weight Handling Program Management) that may pertain to Work Items in this specification package. It is highly recommended that local Navy NAVFAC personnel and the Coast Guard support element closest to the cutter participate in the 1st A-Team meeting to develop a list of local instructions that the Contractor should be aware of and include in the bid to meet those requirements.

As applicable, copy the following under paragraph 3.6, “3.6.1 This availability is to be conducted at an US Navy facility. The Contractor must comply with all US Naval facility instructions (e.g. NAVFAC P-307 for Weight Handling Program Management, etc.)”

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

7 (Draft-0)

ATeam Note: For MECPL Avails discuss need to include the following paragraph for freeze protection.

3.8 Freeze protection. After the Arrival Conference, the Contractor must conduct a walkthrough with the COR and Ships Force (EO and/or MPA), to perform a joint inspection to identify compartments and systems that will require freeze protection.

Within 7 days of completing this joint inspection, the Contractor must submit a CFR documenting their plan for freeze protection when temperatures are expected to drop below freezing. Freeze protection must include securing systems/components and auxiliary equipment and its piping exposed to freezing temperatures or if not protected must be completely drained. If necessary, drain connections may be broken to prevent damage due to freezing.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

8 (Draft-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK

ITEM #

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

9 (Draft-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL # WORK

ITEM # WORK ITEM TITLE

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER

COAT, BARRIER COAT, TOP

COAT, ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFAC

E

AMBIEN

T

ΔT

| DP -

SURFACE |

10 (Draft-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

11 (Draft-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT

QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

12 (Draft-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK

ITEM #

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

13 (Draft-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL # WORK ITEM

# WORK ITEM TITLE

COATING MFG PRODUCT NAME BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

14 (Draft-0)

4.2 Tank and Void Assessment form.

15 (Draft-0)

43610_BEC_0826_418

WORK ITEM 1: Fire Detection System, Inspect and Test

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect and test Fire Detection System.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL-436-011, Rev E, Fire Detection Sys Deck Plan (ASC436009) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets

(ASC436010)

Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic

(ASC436028)

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response Coast Guard Technical Publication (TP) 9556, SWBS 436, Feb 2022, Fire and Smoke Detection

System (For Hull 755)

OTHER REFERENCES

National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and

Signaling Code

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

• 3.3 System inspect and test.

3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Technical Representative, who must demonstrate familiarity with marine fire and smoke detection and alarm systems, and fulfill the requirements of this section.

3.1.2.1 The Tech Rep must advise on repair methods when needed to restore the system to its operational capability according to the design documents included in Section 2, and the requirements of NFPA 72.

3.1.2.2 The Tech Rep must inspect the system for compliance with the standards governing the condition of the fire detection system…