CGC NEAH BAY ANCHOR WINDLASS REPAIR.pdf

PDF 976 KB Posted

Attached to
CGC NEAH BAY ANCHOR WINDLASS REPAIRS
Solicitation number
70ZU0227Q0001147
Issued by
Not on record

About this file

This is a Statement of Work (SOW) for anchor windlass repair services on the USCGC NEAH BAY (WTGB 105), a U.S. Coast Guard vessel located in Cleveland, Ohio.

The contract consists of two contract line items (CLINs): CLIN 0001 covers the Open, Inspect, and Report phase, requiring the contractor to remove the anchor windlass and gearbox assembly, transport it to an off-site repair facility, disassemble and inspect the components, fabricate one replacement key from 4140 heat-treated steel, and submit a Condition Found Report (CFR) detailing inspection findings and recommended repairs; CLIN 0002 covers repair and reinstallation work, which is authorized only upon written approval by the Contracting Officer following review of the CFR and includes machining, restorative repair, final fitting, transport back to the vessel, reinstallation, alignment, and operational testing. The work is divided into five sequential phases: removal and transport with crane services, open and inspect, CFR submission, repair and fabrication, and reinstallation and operational testing. The period of performance is any five-day work period within November 30, 2026 to December 15, 2026, with on-site work conducted Monday through Friday, 7:00 AM to 5:00 PM during 10-hour workdays. The contractor must furnish all labor, tools, specialized rigging, crane services, transportation, raw materials, and machine shop equipment, while the Government provides electrical isolation prior to removal and operates the system during post-repair testing. All contractor employees onboard Coast Guard facilities must present valid government-issued photo identification, and an on-site lead technician or supervisor must be designated in writing prior to work commencement.

View the file

Other files

File Type Posted
Wage and Determinations Ohio.pdf PDF
FAR CLAUSES FOR SERVICES.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

USCGC NEAH BAY (WTGB 105) ANCHOR

WINDLASS REPAIRS

SECTION 1 – GENERAL INFORMATION AND

REQUIREMENTS

1.1 Scope of Services (Open, Inspect, Report, and Repair

[OIR/R])

The Contractor shall provide all personnel, equipment, tools, materials, crane services, transportation, supervision, and other items and services necessary to perform the Open, Inspect, Report, and Repair (OIR/R) of the anchor windlass and gearbox assembly onboard USCGC NEAH BAY in accordance with the requirements defined in this Statement of Work (SOW).

1.1.1 Contract Line Item Structure

CLIN 0001 – Open, Inspect, and Report: The Contractor shall perform the removal, crane service, rigging, transport to repair facility, disassembly, inspection, fabrication of one (1) new replacement key constructed of 4140 Heat Treated (HT) steel, and Condition Found Report (CFR) work necessary to determine the full extent of damage and recommended repair actions. No restorative machining, permanent repair, or reinstallation work beyond the base effort described in CLIN 0001 is authorized under CLIN 0001.

CLIN 0002 – Repair and Reinstallation: If authorized in writing by the Contracting Officer after review of the CFR, the Contractor shall perform the approved machining, restorative repair, final fitting and installation of the replacement key as required, transport back to the vessel, crane service, rigging, reinstallation, alignment, and support for operational testing necessary to return the anchor windlass gearbox shafting and keyway to serviceable condition.

1.1.2 Detailed OIR/R Requirements

The core requirement is divided into five sequential operational phases:

1.1.2.1 Removal, Crane Service, and Transport: The Contractor shall disconnect and remove the anchor windlass and/or gearbox assembly from the vessel. The Contractor shall arrange, coordinate, and provide all necessary crane services and rigging required for safe removal and reinstallation. The Contractor shall transport the removed assembly and any damaged components to a suitable repair and machine shop facility, and return them to the vessel upon completion of repairs.

1.1.2.2 Open and Inspect: Upon arrival at the repair facility, the Contractor shall disassemble (open) and conduct a thorough mechanical and dimensional inspection of the anchor windlass gearbox shafting, coupling, and associated keyway to determine the full extent of wear, distortion, or damage.

1.1.2.3 Condition Found Report (CFR): Prior to commencing any restorative machining or permanent repair work beyond the base effort included under CLIN 0001, the Contractor shall submit a written Condition Found Report (CFR) to the Coast Guard Representative and the Contracting Officer. The CFR shall detail all inspection findings, required tolerances, recommended machine work, and restorative actions needed to return the gearbox shafting and keyway to serviceable specification. The Government will review the complete CFR and provide a response within two (2) business days of receipt. If the CFR is received outside normal business hours, the review period begins on the next business day. The Contractor shall not proceed with any restorative machining or permanent repair work beyond the base effort included under CLIN 0001 until authorized in writing by the Contracting Officer.

1.1.2.4 Repair and Fabrication: Following Contracting Officer authorization of any required restorative machine work identified in the CFR, the Contractor shall coordinate and perform all approved machining and repair services on the anchor windlass gearbox shafting and associated keyway, and complete the final fitting and installation of the replacement key to the restored shaft and coupling keyway dimensions.

1.1.2.5 Reinstallation and Operational Testing: Upon completion of repairs and fabrication, the Contractor shall transport the assembly back to USCGC NEAH BAY, provide crane service to rig the equipment back aboard, and reinstall and align the anchor windlass and gearbox assembly. Following installation, Ship's Force will operate the anchor system to conduct operational testing in the presence of the Contractor and the Coast Guard Representative to verify proper alignment, key seating, and satisfactory mechanical operation under load.

1.1.3 Period of Performance

The Period of Performance (POP) for this requirement is any five-day work period within the window 30 November 2026 to 15 December 2026.

1.1.4 Place of Performance

Unit: USCGC NEAH BAY (WTGB 105) Address: 1055 East 9th Street, Cleveland, OH 44114 (and Contractor's off-site repair facility as required for machining and shop inspection).

1.1.5 Coast Guard Representative

Name: CWO2 Dominic M. Potter Unit: USCGC NEAH BAY Phone: 517-474-4888 E-mail: dominic.m.potter@uscg.mil

1.1.6 Contact for Questions and Site Visits

1.1.6.1 Any questions regarding the scope of work or contractual changes must be directed to the Contracting Officer.

1.1.6.2 All requests for site visits must be scheduled through the Coast Guard Representative. Requests may be submitted via phone call or e-mail using the contact information in Section 1.1.5.

1.2 Contractor Personnel and Security

1.2.1 On-Site Supervision

The Contractor shall designate an on-site lead technician or project supervisor responsible for coordinating daily removal, crane rigging, reinstallation, and testing evolutions with the Coast Guard Representative. The designated lead shall be provided in writing to the Contracting Officer and the Coast Guard Representative prior to the start of work, must have authority to manage daily on-site operations, and must be able to read, write, speak, and understand the English language.

1.2.2 Security Requirements

Due to heightened security at U.S. Coast Guard (USCG) facilities, all Contractor employees performing tasks related to this SOW while onboard a Coast Guard facility or vessel shall possess and present proper, valid government-issued photo identification. Time spent undergoing security screening and entrance procedures at USCG facilities will not be considered a Government delay of work or a differing site condition.

1.3 Hours of Operation

1.3.1 Standard Workday

To accommodate the compressed five-day Period of Performance, the Contractor shall perform on-site tasks required by this SOW during 10-hour workdays:

Monday through Friday between 07:00 AM and 05:00 PM (0700–1700).

SECTION 2 – GOVERNMENT AND CONTRACTOR

FURNISHED ITEMS AND SERVICES

2.1 Government Furnished Support

The Government (Ship's Force) will provide electrical tag-out/isolation of the anchor windlass system prior to removal and will operate the anchor windlass system during post-repair operational testing.

2.2 Contractor Furnished Items and Services

Except for the operational system isolation and testing operation performed by Ship's Force as specified in Section 2.1, the Contractor shall furnish all labor, tools, specialized rigging gear, crane services, transportation, raw materials (including 4140 HT steel stock), machine shop equipment, and supervision necessary to perform this contract in accordance with all of its terms.

SECTION 3 – REFERENCE PHOTOGRAPHS

The following reference photographs illustrate the current configuration and damaged condition of the USCGC NEAH BAY anchor windlass gearbox shafting, coupling, key, and keyway:

1. Figure 1: Gearbox Assembly Staged in Forward Compartment

2. Figure 2: Gearbox output shaft, coupling interface, and damaged key/keyway

(angled view).

3. Figure 3: Wildcat Shaft and Coupling Gear Interface

File details come from the government source that posted it. Updated .