This is a Statement of Work (SOW) for anchor windlass repairs aboard USCGC KATMAI BAY (WTGB 101), a U.S. Coast Guard vessel. The contractor must perform Open, Inspect, Report, and Repair (OIR/R) services on the anchor windlass and gearbox assembly during a compressed five-day period from November 16-20, 2026, at the vessel's location in Sault Sainte Marie, Michigan (337 E Water St, Sault Sainte Marie, MI 49783).
The work consists of five sequential phases: (1) removal and transportation of the anchor windlass/gearbox assembly, including coordination of crane services and rigging for safe removal and reinstallation; (2) disassembly and thorough mechanical and dimensional inspection at a contractor-operated repair facility to determine wear, distortion, or damage; (3) submission of a written Condition Found Report (CFR) detailing inspection findings, required tolerances, and recommended machine work before proceeding; (4) fabrication of one new key constructed of 4140 Heat Treated steel and performance of authorized machining and repair services on the gearbox shafting and keyway; and (5) transportation of the assembly back to the vessel, crane-assisted reinstallation, and alignment followed by operational testing in the presence of the contractor and Coast Guard Representative. The contractor shall furnish all labor, tools, specialized rigging gear, crane services, transportation, raw materials including 4140 HT steel stock, machine shop equipment, and supervision. The Government will provide electrical system isolation prior to removal and operate the system during post-repair testing. Work hours are 10-hour days, Monday through Friday, 0700-1700. All contractor personnel onboard the Coast Guard facility must possess valid government-issued photo identification. The Coast Guard Representative is CWO2 Patrick T. Holom (907-351-0794; Patrick.T.Holom@uscg.mil). Invoices must reference the contract requisition number/order number, company name and address, UEI/DUNS number, invoice number, and invoice date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAR CLAUSES FOR SERVICES.pdf | ||
| Wage and Determinations Michigan.pdf |
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
USCGC KATMAI BAY (WTGB 101) ANCHOR
WINDLASS REPAIRS
SECTION 1 – GENERAL INFORMATION AND
REQUIREMENTS
1.1 Scope of Services (Open, Inspect, Report, and Repair
[OIR/R])
The Contractor shall provide all personnel, equipment, tools, materials, crane services, transportation, supervision, and other items and services necessary to perform the Open, Inspect, Report, and Repair (OIR/R) of the anchor windlass and gearbox assembly onboard USCGC KATMAI BAY in accordance with the requirements defined in this Statement of Work (SOW).
1.1.1 Detailed OIR/R Requirements
The core requirement is divided into five sequential operational phases:
1.1.1.1 Removal, Crane Service, and Transport: The Contractor shall disconnect and remove the anchor windlass and/or gearbox assembly from the vessel. The Contractor shall arrange, coordinate, and provide all necessary crane services and rigging required for safe removal and reinstallation. The Contractor shall transport the removed assembly and any damaged components to a suitable repair and machine shop facility, and return them to the vessel upon completion of repairs.
1.1.1.2 Open and Inspect: Upon arrival at the repair facility, the Contractor shall disassemble (open) and conduct a thorough mechanical and dimensional inspection of the anchor windlass gearbox shafting, coupling, and associated keyway to determine the full extent of wear, distortion, or damage.
1.1.1.3 Condition Found Report (CFR): Prior to commencing any machine work or permanent repairs beyond the baseline key fabrication, the Contractor shall submit a written Condition Found Report (CFR) to the Coast Guard Representative and the Contracting Officer. The CFR shall detail all inspection findings, required tolerances, recommended machine work, and restorative actions needed to return the gearbox shafting and keyway to serviceable specification.
1.1.1.4 Repair and Fabrication: The Contractor shall fabricate one (1) new key constructed of 4140 Heat Treated (HT) steel fitted to the restored shaft and coupling keyway dimensions. Following Contracting Officer authorization of any required restorative machine work identified in the CFR, the Contractor shall coordinate and perform all machining and repair services on the anchor windlass gearbox shafting and associated keyway.
1.1.1.5 Reinstallation and Operational Testing: Upon completion of repairs and fabrication, the Contractor shall transport the assembly back to USCGC KATMAI BAY, provide crane service to rig the equipment back aboard, and reinstall and align the anchor windlass and gearbox assembly. Following installation, Ship's Force will operate the anchor system to conduct operational testing in the presence of the Contractor and the Coast Guard Representative to verify proper alignment, key seating, and satisfactory mechanical operation under load.
1.1.2 Period of Performance
The Period of Performance (POP) for this requirement is 16 November 2026 to 20 November 2026.
1.1.3 Place of Performance
Unit: USCGC KATMAI BAY (WTGB 101) Address: 337 E Water St, Sault Sainte Marie, MI 49783 (and Contractor's off-site repair facility as required for machining and shop inspection).
1.1.4 Coast Guard Representative
Name: CWO2 Patrick T. Holom Unit: USCGC KATMAI BAY Phone: 907-351-0794 E-mail:Patrick.T.Holom@uscg.mil
1.1.5 Contact for Questions and Site Visits
1.1.5.1 Any questions regarding the scope of work or contractual changes must be directed to the Contracting Officer.
1.1.5.2 All requests for site visits must be scheduled through the Coast Guard Representative. Requests may be submitted via phone call or e-mail using the contact information in Section 1.1.4.
1.2 Contractor Personnel and Security
1.2.1 On-Site Supervision
The Contractor shall designate an on-site lead technician or project supervisor responsible for coordinating daily removal, crane rigging, reinstallation, and testing evolutions with the Coast Guard Representative. The designated lead shall be provided in writing to the Contracting Officer and the Coast Guard Representative prior to the start of work, must have authority to manage daily on-site operations, and must be able to read, write, speak, and understand the English language.
1.2.2 Security Requirements
Due to heightened security at U.S. Coast Guard (USCG) facilities, all Contractor employees performing tasks related to this SOW while onboard a Coast Guard facility or vessel shall possess and present proper, valid government-issued photo identification. Time spent undergoing security screening and entrance procedures at USCG facilities will not be considered a Government delay of work or a differing site condition.
1.3 Hours of Operation
1.3.1 Standard Workday
To accommodate the compressed five-day Period of Performance, the Contractor shall perform on-site tasks required by this SOW during 10-hour workdays:
Monday through Friday between 07:00 AM and 05:00 PM (0700–1700).
1.4 Invoicing
Invoices shall be submitted to the designated billing address specified in the contract. To ensure timely and proper payment, all invoices shall clearly indicate the requisition number/order number, company name and address, Unique Entity ID (UEI) / DUNS number, invoice number, and invoice date. It is recommended that the Contractor attach a copy of the Purchase Order / Contract to their invoice(s).
SECTION 2 – GOVERNMENT AND CONTRACTOR
FURNISHED ITEMS AND SERVICES
2.1 Government Furnished Support
The Government (Ship's Force) will provide electrical tag-out/isolation of the anchor windlass system prior to removal and will operate the anchor windlass system during post-repair operational testing.
2.2 Contractor Furnished Items and Services
Except for the operational system isolation and testing operation performed by Ship's Force as specified in Section 2.1, the Contractor shall furnish all labor, tools, specialized rigging gear, crane services, transportation, raw materials (including 4140 HT steel stock), machine shop equipment, and supervision necessary to perform this contract in accordance with all of its terms.
SECTION 3 – REFERENCE PHOTOGRAPHS
The following reference photographs illustrate the current configuration and damaged condition of the USCGC KATMAI BAY anchor windlass gearbox shafting, coupling, key, and keyway:
1. Figure 1: Anchor windlass assembly and gearbox shaft-to-coupling arrangement onboard USCGC KATMAI BAY. (Insert Photo 1: Overview of electric motor, blue gearbox assembly, handwheel, and upper shaft coupling)
2. Figure 2: Gearbox output shaft, coupling interface, and damaged key/keyway (angled view). (Insert Photo 2: Close-up view of coupling flange and displaced/sheared shaft key)
3. Figure 3: Detailed close-up of damaged gearbox shaft key and keyway deformation. (Insert Photo 3: Macro view showing keyway wall deformation and damaged key seating)
File details come from the government source that posted it. Updated .