SOW.pdf
PDF 391 KB Posted
- Attached to
- CGC SCIOTO WATER MIST FIRE PROTECTION SYSTEM
- Solicitation number
- 70ZU0227Q0000282
- Issued by
- Not on record
About this file
This is a Statement of Work (SOW) for the retrofit of the USCGC SCIOTO's water mist fire protection system. The contractor must remove all components of the existing Chemetron water mist or CO2 firefighting systems and install a new Marioff Hi-Fog water mist system along with a Kiddie AEGIS-XLT fire alarm control panel (FACP). The government will furnish the major components, including the Hi-Fog MAU Watermist System (P/N: AFP-USCG65-MAU, NSN: 1230-01F24-6865, estimated cost $36,234.00) and the Kiddie Aegis-XLT Control Panel (P/N: AFP-USCG65-FACP, NSN: 1230-01F24-6864, estimated cost $12,049.00); the contractor must furnish minor miscellaneous components and consumables as needed to complete installation.
Work must be performed at USCGC SCIOTO located at 221 Mississippi Drive, Keokuk, Iowa 52632, during the period of November 15, 2026 to November 23, 2026. The contractor must engage a qualified technical representative experienced with Marioff Hi-Fog systems to advise on installation procedures, provide proprietary tools and equipment, and ensure compliance with manufacturer standards. Key requirements include removing and disposing of all existing system components in accordance with federal, state, and local regulations; installing systems per Coast Guard Drawings 65 WD 4803-007 and 65 WD 555-002 and Technical Publication 9163; performing welding, brazing, and electrical work per Surface Forces Logistics Center Standard Specifications; flushing all new and disturbed piping with fresh water and drying with low-pressure air; conducting hydrostatic testing with zero leakage tolerance; certifying system completion with Tech Rep concurrence; applying touch-up preservation coatings to match existing surfaces; and providing on-site familiarization and operational training to the vessel's crew. The contractor must also handle all equipment interferences and relocate or remove conflicting items such as light fixtures, piping, shelves, electrical boxes, and foundations, submitting Change Failure Reports for technical approval as needed.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FAR CLAUSES FOR SERVICES.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement Of Work (SOW)
USCGC SCIOTO Water Mist Fire Protection System
TABLE OF CONTENTS
1. General - SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to remove all components of the existing Chemetron water mist firefighting or CO2 firefighting systems, then install a new Marioff Hi-Fog water mist system and install a new Kiddie AEGIS fire alarm control panel (FACP).
1.1.1 CGC SCIOTO (WLR 65504) - has a Chemetron water mist system that requires removal.
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN
QTY ESTIMATED
COST
($/UNIT)
N **Kit, Hi-Fog MAU Watermist System
P/N: AFP-USCG65-MAU
NSN: 1230-01F24-6865
1 ea. $36,234.00
N **Kit, Kiddie Aegis-XLT Control Panel
P/N: AFP-USCG65-FACP
NSN: 1230-01F24-6864
1 ea. $12,049.00
*Government-loaned property, which must be returned to the vessel upon completion of the availability.
**New equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
Note: The ‘alpha’ characters in the NSN is correct. It is an internal NSN that is specific to the Coast Guard warehouse.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 65 WD 4803-007, Rev -, Retrofit Hi-Fog Watermist Engine Room Fire Protection System, Wiring Diagram
Coast Guard Drawing 65 WD 555-002, Rev A, Retrofit Hi-Fog Watermist Engine Room Fire Protection System, Layout and Arrangement
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 9163, SWBS 555, Mar 2024, Machinery Accumulator Unit (MAU) Water Mist Fire Extinguishing System
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep. The Contractor must utilize the services of a Qualified Technical Representative who is familiar with Marioff Hi-Fog water mist systems to accomplish the following on site:
Advise on manufacturer's proprietary system information.
Assist with the following installation and certification methods.
Provide propriety tools and equipment.
Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, and reassembly as applicable.
3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.
3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
3.2 Removal. The Contractor must remove and dispose of all components on the existing CO2 firefighting or Chemetron water mist firefighting system.
3.2.1 Dispose of all removed components and system fluids in accordance with all applicable Federal, state, and local regulations.
3.3 Install/Retrofit. The Contractor must install the new Marioff Hi-Fog water mist system and the FACP releasing panel as specified below:
3.3.1 Install the Marioff Hi-Fog MAU 150 water mist system in accordance with Coast Guard Drawings 65 WLR 555-002 and Coast Guard Technical Publication 9163.
3.3.1.1 All major components of Marioff Hi-Fog MAU 150 water mist system will be provided as GFP by the USCG. Minor miscellaneous components and consumables may still need to be furnished by the Contractor to successfully install the system.
3.3.2 Install the Kidde AEGIS-XLT FACP in accordance with Coast Guard Drawing 65 WD 4803-007.
3.3.2.1 All major components of the Kidde AEGIS-XLT releasing control panel will be provided as GFP by the USCG. Minor miscellaneous components and consumables may still need to be furnished by the Contractor to successfully install the system.
3.3.3 Perform all welding, brazing and inspections in accordance with SFLC Std Spec 0740.
3.3.4 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041. Utilize the existing wire ways for new cable runs as much as possible.
3.3.5 Consult with the Tech Rep for equipment installation procedures.
3.3.6 Relocate, reorient or remove all equipment, piping or other interferences that prohibit installation of the water mist skid in the specified location. Submit a CFR for technical approval, with a proposed plan of action, for all equipment that is affected. Examples of equipment that may be affected are below:
Light fixtures
Bilge piping
Sewage piping
Shelves
Electrical junction boxes
Bilge alarms
Pump controllers
Foundations
3.4 Pipe flushing. The Contractor must flush all new and disturbed piping with clean fresh water until all debris is removed but no longer than five minutes. Ensure flushing fluid is directed to move scale and foreign debris away from installed machinery to prevent possible damage upon operational testing.
Submit a CFR documenting date and time of flushing process and level of pipe cleanliness.
3.4.1 Dispose of flushing fluid in accordance with all applicable Federal, state, and local regulations.
3.4.2 Ensure all water is removed by blowing dry all flushed piping with dry, low-pressure air.
3.5 Hydrostatic test. After all authorized repairs, the Contractor must hydrostatically test all new and disturbed piping and components of the Firemain system in accordance with SFLC Std Spec 0740, Appendix C, “Hydrostatic Test”. Ensure zero leakage from or permanent deformation of pressure-containing parts by repairing all leaks, deformations, and discrepancies. Submit a CFR.
3.6 System certification. The Contactor must certify the water mist system upon completion of all inspections and testing. Submit a certification letter via CFR, with concurrence from the Tech Rep, that all components have been satisfactorily installed, inspected and tested.
3.7 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, (Touch-ups and minor coating repairs.)
3.8 Crew Training. The Contractor must provide on-site (shipboard) familiarization and operational training to the cutters crew for the newly installed water mist system.
4. NOTES
4.1 Fire Protection System Design. The cutters water mist fire protection system was designed for the USCG by Associated Fire Protection in accordance with NFPA requirements. The contact information for the design activity is shown below:
Associated Fire Protection 4905 South 97th Street, Omaha, NE 68127 402-733-2800 www.associatedfire.net POC: Andy Blaszak
4.2 Tech Rep Contact. The following is provided for information purposes only, regarding a potential technical representative for the water mist system, whose services may be used:
Associated Fire Protection 4905 South 97th Street, Omaha, NE 68127 402-733-2800 www.associatedfire.net POC: James Blaszak
5. PLACE OF PERFORMANCE
5.1 CGC SCIOTO
221 Mississippi Drive, Keokuk IA 52632
5.2 Security Requirements: Provide name of technician to crew prior to arrival and good contact information.
6. PERIOD OF PERFORMANCE
15Nov26-23Nov26
7. POINTS OF CONTACT:
7.1 USCGC SCIOTO MKC Alexander Kull, Alexander.R.Kull@uscg.mil 217-273-1543
7.2 USCG-SFLC-IBCTPL Asset Management: ENS Grant Aki Freeman, grant.a.freeman@uscg.mil,
(510) 239-0042
File details come from the government source that posted it. Updated .