This amendment modifies a solicitation for repair work at a Coast Guard waterfront facility. The contractor must perform repairs to shore tie facilities in three phases to allow homeported vessels to continuously berth and access utilities. Phase 1 involves work from stations 6+00 to 8+70. Phase 2 covers stations 4+50 to 6+00. Phase 3 includes stations 2+10 to 4+50 and small boat work, maintaining utilities throughout. The contractor must submit a phasing schedule and provide seven-day notices between phases. The bid due date remains August 24, 2021. The document addresses required construction sequencing, project scoping and responsibilities to ensure continuous operations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

PAGE OF PAGES

1 6

2. AMENDMENT/MODIFICATION NO.

3. EFFECTIVE DATE

08/16/2021

4. REQUISITION/PURCHASE REQ. NO.

2121G11PRV156

5. PROJECT NO. (If applicable)

PSN: 15912848

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

Contracting Officer USCG Civil Engineering Unit Providence 475 Kilvert ST STE 100 Warwick, RI 02886

Same as Block 6 Attn: Daniel B. Walker, Contracting Officer

(401) 736-1764

(401) 736-1704 (fax)

8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)

THIS AMENDMENT MUST BE ACKNOWLEDGED

See Block 11 below

9A. AMENDMENT OF SOLICITATION NO.

70Z0G121RPRV15600

9B. DATED (SEE ITEM 11)

07/23/2021

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such Change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET

FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The solicitation referenced in block #9A to REPAIR WATERFRONT AT CG SECTOR SOUTHEASTERN NEW ENGLAND, WOODS HOLE, MA is amended as follows:

1. The open period for receipt of questions is now closed. The following page documents questions received along with the associated responses.

Continued…

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or Print)

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

DANIEL B. WALKER, Contracting Officer

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED

16B UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

08/16/2021

NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA

FAR (48 CFR) 53

RFI’s: Are they emailed direct to you? How will we receive the replies; via Amendment or email?

ANSWER: As stated in note 4 on the cover page of the solicitation: “4. Submit any QUESTIONS to the Contracting Officer via email at daniel.b.walker@uscg.mil no later than the “Questions Due Date” listed above.” When the period for questions closes an amendment will be uploaded posting all questions and answers.

BID: Please confirm that this is to be sent electronically via email to you OR elsewhere.

ANSWER: As stated in note 5 on the cover page of the solicitation: “5. Email, telegraphic, telephonic, or facsimile bids will not be accepted.”

What amount of bulkhead space (LF work area) will be available for this work? We are preparing our pricing with waterborne equipment that will need to traverse the entire work area. Is phasing required / expected.

ANSWER: Phasing is required. See Phasing Plan incorporated via Amendment 0001.

What is the expected time from timber and hardware removed from the fender units to then be able to install new after the cleaning and painting the steel frames are completed and cured?

ANSWER: See Phasing Plan incorporated via Amendment 0001.

There is a note in the plans on sheet S-502 that reads Note 3: “All timber sizes shown as actual dimensions” Is this what is in place now, actual size timbers? Timbers are typically milled to nominal dimensions. i.e., a 12 x 12 measures 11 ½” x 11 ½” in size when we receive them from the mills. Actual size timbers would require a special order and equate to longer lead times and additional costs. Please clarify this requirement or is it mis-noted?

ANSWER: The actual existing timber member sizes are full 12”x12” and 6”x12”.

New timber members must be milled to full 12”x12” and 6”x12”.

Can all the specified fenders be removed of all timbers, hardware and foam filled fenders. Would clean and paint then occur on all fender frames. Then would all fenders be reconstructed with timbers, new and reused hardware and reinstall the reused foam filled fenders? Please clarify sequencing and again if phasing is needed.

ANSWER: See Phasing Plan incorporated via Amendment 0001.

Is the requirement to pre-drill and pre-countersink all new timbers prior to pressure treatment a true requirement that is expected?

ANSWER: Yes pre-drilling and pre-countersinking prior to treatment is required.

No drilling or cutting of timber members is allowed after treatment.

Talking with the GE manufacturer that is pricing up the added 500-amp breakers in the main distribution gear for the power mounds at the docks. We need to get the manufactures job# on the label on the front face of the gear. Can we please have a photo of the tag?

ANSWER: See attached photos.

PAGE OF

PAGES

2 6 mailto:daniel.b.walker@uscg.mil

It is understood that mobilization is supposed to occur 10 days after the project has been awarded. How long after the bid due date will there be an award?

ANSWER: See Block 13 D of the Standard Form 1442. Offerors submitting bids under this Invitation for bids agree to a 90-calendar day acceptance period.

It is understood that we cannot take up the entire dock space during construction. How many phases will there be during construction? How large of a portion of dock space can we work on per phase?

ANSWER: See Phasing Plan incorporated via Amendment 0001.

It is understood that we cannot take up the entire dock space during construction. How many phases will there be during construction? How large of a portion of dock space can we work on per phase?

ANSWER: See Phasing Plan incorporated via Amendment 0001.

Does the contract contain liquidated damages?

ANSWER: It does not include Liquidated Damages.

The project scope indicates a requirement to paint the exiting Steel Piles to the lower limit of elevation 0.00 MLLW. However, there is not sufficed time within a tide cycle to perform the specified substrate preparation, application of the specified paint product(s), and allow for the required cure time (temperature dependent) within the tidal zone.

These factors (tide cycle time and temperature) combined with work hour restrictions makes the possibility of compliance with the painting specifications unattainable. Please provide a specification for painting that allows for proper application of coatings within the tidal zone.

ANSWER: This specification has been used successfully on numerous waterfront re-coating projects that have extended to MLLW. Understanding there is some difficultly and concern on compliance at the MLLW elevation, blasting between MLLW and elevation +2 ft. may be relaxed to WJ-3.

The representative cross sections of the Existing and New Fender Panels indicate the Concrete Cap to be at elevation 6.00. The corresponding existing conditions and site utility plans indicate the top of pavement in the vicinity of the concrete cap to be approximately 3.3. Site visit observations do not appear to align with a difference in elevation between the concrete cap and existing pavement of over 2.5 ft. Please confirm the existing condition elevations of the pavement and concrete cap.

ANSWER: Clarification- All Fender work follows MLLW vertical datum. All Site/Utility work follows NAVD88 vertical datum...

Please provide geotechnical information relative to existing soil classifications, ground water elevation, and soil permeability within the sheeted bulkhead area where Utility excavation work is designated to occur.

ANSWER: See Phasing Plan incorporated via Amendment 0001.

Specification Section 01 14 00 Work Restrictions per 1.1c states that slip closures must be coordinated 30 day in advance of the work. The ability, or inability, to close multiple slips at the same time is not addresses. Please advise if more than one slip can be closed at the same time.

ANSWER: See Phasing Plan incorporated via Amendment 0001.

3 6

Specification Section 01 35 26 Gov’t Safety Requirements par 1.7.1.1.1 States, The SSHO may also may not serve as the Quality Control Manager. Please clarify id the SSHO CAN or CAN NOT also serve as the QCM.

ANSWER: Clarification- The SSHO CAN also serve as the QCM.

Is this project exempt from sales tax?

ANSWER: The following is an excerpt from page 1 of the SF 1442 in the solicitation: “BIDDER SHALL INCLUDE ALL APPLICABLE FEDERAL, STATE, AND LOCAL TAXES IN THEIR BID PRICE. A tax exempt number will not be provided.”

Is there a limit to the amount of existing shore ties that can be taken out of service at the same time?

ANSWER: See Phasing Plan incorporated via Amendment 0001.

Please verify that the Contractor is not responsible for providing temporary power, water, and sanitary services for boats that may be berthed while the shore ties are out of service.

ANSWER: See Phasing Plan incorporated via Amendment 0001.

End Item 1, Questions & Answers.

Continued

4 6

2. In reference to Specification Section 01 14 00; Add the following sub-Section:

1.4 PHASING

1.4.1 Contractor shall perform construction services in three phases to allow for the homeported CG vessels to berth at the pier and have access to shore-side utilities (electric, telecommunications, sewer, water).

1.4.1 Phase 1: Shore-Tie #3

(a) Contractor shall demolish and perform new work associated with Shore-Tie #3.

This shall include all work between stations 6+00 and 8+70.

(b) Contractor shall maintain all utilities to Shore-Tie #1 & #2 during Phase 1 construction.

(c) Perform preliminary inspection and testing of all new utilities at Shore-Tie #3.

This shall include connecting a WPB CG Cutter to test the new utilities for acceptance.

(d) Provide the Contracting Officer a seven (7) calendar day notice of when Phase 2 will commence.

1.4.2 Phase 2: Shore-Tie #2

(a) Contractor shall demolish and perform new work associated with Shore-Tie #2.

This shall include all remaining work between stations 4+50 and 6+00.

(b) Contractor shall maintain all utilities to Shore-Tie #1 & #3 during Phase 2 construction.

(c) Perform preliminary inspection and testing of all new utilities at Shore-Tie #2.

This shall include connecting a WPB CG Cutter to test the new utilities for acceptance.

(d) Provide the Contracting Officer a seven (7) calendar day notice of when Phase 3 will commence.

1.4.3 Phase 3: Shore-Tie #1 & Small Boat Distribution

(a) Contractor may demolish and perform new work associated with Shore-Tie #1.

This shall include all remaining work between stations 2+10 and 4+50 and the small boat basin.

(b) Contractor shall maintain all utilities to Shore-Tie #2 & #3 during Phase 3 construction.

(c) Coordinate Small Boat Distribution work to minimize power outages. All Small Boat 120VAC/100A shore-tie receptacles shall be energized by the close of business each working day. Maintain two (2) of the 120VAC/100A receptacles for use at all times with the exception of minimal cut-over times not to exceed 4 hrs.

(d) Perform final inspections and testing per contract documents.

1.4.4 Phasing Schedule

(a) Submit to the Contracting Officer a Phasing Schedule to show for each phase the work to be performed, date, and duration until completion.

5 6

3. The sign in sheet for the Pre-Bid meeting held on Thursday, August 5, 2021 is hereby provided

(attached).

4. The due date for receipt of bids is unchanged and remains AUGUST 24, 2021, 02:00 PM LOCAL

TIME, WARWICK, RI

All other terms and conditions remain unchanged.