SPECIFICATIONS FOR IFB 70Z0G120BPRV00400 DREDGE CHANNEL AT USCG STA JONES BEACH FREEPORT NY PSN 9829696.pdf

PDF 9 MB Posted

Attached to
DREDGE CHANNEL AT U. S. COAST GUARD STATION JONES BEACH, FREEPORT, NEW YORK (NASSAU COUNTY) PSN 9829696
Solicitation number
70Z0G120BPRV00400
Issued by

About this file

This solicitation is for maintenance dredging of the entrance channel at USCG Station Jones Beach in Freeport, New York. Hydraulic dredging is permitted to remove an estimated 6,875 cubic yards of coarse sand, silt, clay, and gravel. Dredge spoils will be dewatered onsite and disposed of at 110 Sand Company in Melville, New York. All in-water work must be completed between October 1 and December 31, 2020, though NYSDEC may extend this window. The period of performance is 110 days from notice to proceed. Bids are due on May 28, 2020. The contractor will be compensated per cubic yard removed based on the actual quantity within dredging limits. Performance and payment bonds are required. The solicitation packages will be available on April 22, 2020 from the Federal Business Opportunities website. The NAICS code is 237990 and it is reserved for small businesses with less than $27.5 million in annual revenue.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

SHORE INFRASTRUCTURE LOGISTICS CENTER

SPECIFICATIONS FOR

DREDGE CHANNEL

PSN 9829696

AT

U.S. COAST GUARD STATION JONES BEACH

FREEPORT, NEW YORK

(Nassau County)

Mike Black, PE Design Project Manager Design Team 1 Supervisor

TECHNICAL DIRECTOR

UNITED STATES COAST GUARD

CIVIL ENGINEERING UNIT PROVIDENCE

475 KILVERT STREET, SUITE 100.

WARWICK, RHODE ISLAND 02886

Dredge Channel USCG Station Jones Beach, Freeport, NY PSN 9829696

DREDGE CHANNEL

USCG STATION JONES BEACH, FREEPORT, NY

PSN 9829696

TABLE OF CONTENTS

SPECIFICATIONS

DIVISION 01

01 11 00 Summary of Work 01 14 00 Work Restrictions 01 32 00 Construction Schedule 01 33 00 Submittal Procedures 01 35 29 Safety & Occupational Health 01 57 19 Temporary Environmental Controls 01 77 00 Closeout Procedures

DIVISION 32

32 92 19 Seeding

DIVISION 35

35 20 23 Dredging

APPENDICES

Appendix A – Permits, including NYSDEC and USACE Appendix B – Sampling and Testing Report, Aqua Survey, August 6, 2019

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work to be performed under this project consists of providing all labor, equipment, and materials to perform maintenance dredging of the channel at U.S. Coast Guard Station Jones Beach, NY. Dredging by hydraulic means is allowable. Immediate placement of the dredge material will be in the temporary, purpose built Confined Dewatering Facility (CDF), located west, adjacent to the Jones Beach Station parking lot, as shown on the Contract Documents prepared by US Army Corps of Engineers, New York District. Contractor shall be responsible for all construction of and final removal of the CDF. After the dredge spoil material is dewatered, according to the standards in the New York State Department of Environmental Conservation (NYSDEC) Water Quality Certificate (WQC), it will be trucked for final disposal to the 110 Sand Company, 136 Spagnoli Road, Melville, NY 11747 - as specified in the WQC and permits.

Contractor must comply with all the requirements of the NYSDEC permit and the Army Corps permit. These permits are included in Appendix A.

The maintenance dredging consists of an estimated approximately 6,875 cubic yards (CY) of dredge material to the required dredging depth of -8 feet below Mean Lower Low Water (MLLW) plus 1 foot of allowable overdredge.

Upon removal of all dewatered dredge material, the Confined Dewatering Facility will be dismantled and the site returned to its former condition.

1.1.2 Location

The work is located at Coast Guard Station Jones Beach, 1 West End Boat Basin, Freeport, NY 11520

1.1.3 Drawings

1.1.3.1 The work is shown on drawing number P9829696, Sheets 01 to 05.

1.2 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which are to remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

SECTION 01 11 00 Page 2

1.3 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours.

1.4 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of values (prices), shop drawings, and other submittals, scheduling, programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.

1.5 INSPECTION

The Contractor shall keep the Contracting Officer or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.

1.5.1 Contractor’s Daily Log

The Contractor shall complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector, or email it to CEU Providence. The Government Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the Contracting Officer or Contracting Officer’s Representative.

1.6 UTILITIES

A search of the regulatory files within New York District, Corps of Engineers disclosed that there were no submerged utilities within the footprint of dredging under this solicitation. All permits issued in the vicinity between 1913 and 1969 are for abandoned communications cables. The 2005 permit for the Neptune Power Cable states it makes landfall south of the Jones Beach clock tower on the ocean-ward side.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

--End of Section--

SECTION 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

1.1 SPECIAL SCHEDULING REQUIREMENTS AND WORK RESTRICTIONS

a. The work is subject to time restrictions specified herein and in the permits issued for the work included in Appendix A.

b. Have all equipment, personnel, and materials necessary to perform the work on site before beginning the work.

c. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing Coast Guard operations. Identify on the construction schedule each factor which constitutes a potential disruption to operations. Contractor shall perform all work to minimize disruptions to USCG STA Jones Beach operations.

d. Conduct dredging operations so that navigation through the channel is possible at all times. Relocate and secure dredging equipment at the end of each work day away from the channel and areas of the mooring basin in use. Contractor shall have radio equipment capable of monitoring a frequency specified by Station personnel, to be able to communicate between contractor vessels and Station personnel.

e. Dredging equipment shall have no less than the production capacity specified, as stated in Section 35 20 23.

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

1.2.2 Regular Working Hours

Given the timing of this project, working hours shall be allowable up to a 10 1/2 hour period from 0700 to 1730, seven days a week, excluding Government holidays, as established by the Contractor, and as approved by the Contracting Officer.

1.2.3 Work Outside Regular Hours

Work outside regular working hours established in 1.2.2 requires Contracting Officer approval. Make application 5 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification

SECTION 01 14 00 Page 2 provided, the Contracting Officer may approve work outside regular hours.

During periods of darkness, the different parts of the work shall be lighted in a manner approved by the Contracting Officer.

1.3 SECURITY REQUIREMENTS

1.3.1 Areas Not Covered by Contract

The Contractor will not be permitted to enter buildings or areas not covered by the work included in this contract, except by prior approval of the Officer-in-Charge of the facility.

1.3.2 Parking

Parking is prohibited on any piers and waterfront areas. An exception may be made for vehicles which are part of the equipment needed to do the required work. Do not park on or block the marked fire lanes at any time.

A limited parking area and staging area will be made available at STA Jones Beach for contractor personnel and equipment. This exact staging area will be determined by working with the USCG Contracting Officer’s Representative, once the project is awarded.

SECTION 01 32 00 Page 1

SECTION 01 32 00

CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES

1.1 SUBMITTALS

Submit the following in accordance with Section 01 33 00, "Submittal Procedures."

SD-01 Preconstruction Submittals

Construction Schedule/Schedule of Values

1.2 CONSTRUCTION SCHEDULE

a. At the Pre-Construction Conference, submit a Construction Schedule and

Schedule of Values in accordance with FAR Clause 52.236.15 - Schedules for Construction Contracts. The Schedule of Values shall be based on the actual breakdown of the bid price. The cost of insurance shall not be listed as a separate item but included as part of each item of work.

The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the Contracting Officer. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.

b. Construction Schedule and Schedule of Values shall be incorporated into one form which clearly indicates the start and completion dates and unit value of all major work components. The sample form provided in this section may be used. Optional forms may be used provided they include at a minimum all information conveyed on the sample form.

c. Construction Schedule/Schedule of Values form shall incorporate at a minimum the following activities:

1. Bonds

2. Mobilization

3. Demobilization

4. Pre-Construction Submittals

5. Work Activities

6. In-Progress Submittals

7. Final Government Inspection

8. Close-Out Submittals

9. Pre/Post dredge survey and quantity computations

SECTION 01 32 00 Page 2

d. Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related site work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods. These activity periods shall not be exclusive of the contract performance period. No site work shall commence until the respective submittals have been approved.

e. The value of all major work components within the project shall be identified on the Construction Schedule/Schedule of Values on a unit quantity and unit cost basis, e.g. number of square feet and cost per square foot of roofing, number of lineal feet and cost per lineal foot of conduit, number of panels and cost per panel etc. Lump sum items shall only be paid for when 100% complete.

f. The Construction Schedule/Schedule of Values as approved by the

Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job.

Omissions and errors on the Construction Schedule/Schedule of Values are the responsibility of the Contractor.

g. Payments will not be made until the schedule of prices has been submitted to and approved by the Contracting Officer.

1.3 UPDATED SCHEDULES

Update the construction schedule and equipment delivery schedule at monthly intervals or when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.

3.1 PROGRESS UPDATES

3.1.1 General

A revised Construction Schedule/Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule/Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule/Schedule of Values.

3.1.2 Modifications

When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule/Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.

Station Jones Beach xxxxxxx

0 ###. ##

DURATION OF WORK ITEM

(Indicates Friday date of each contract week in row below)

1 -$

2 -$

3 -$

4 -$

5 -$

6 -$

7 -$

8 -$

9 -$

10 -$

11 -$

12 -$

13 -$

-$ 0%

Construct Confined De-Watering Facility

Seeding

Task Order Number:

TOTAL COST:

Bonds

Pre-Construction Submittals

Pre-Dredge Survey

Mobilization

Work Activities (Dredge 4,745, cy)

Work Activities (Dispose 4,745 cy)

In-Progress Submittals

Final Inspection

Post-Dredge Survey

Demobilization

Close-Out Submittals

Limit to Complete Date:

Contractor's Schedule / Schedule of Values

Contract Number:

Project Title:

Project PSN:

Notice to Proceed Date:

Limit to Commence Date:

Contractor Name & Address:

Percentage of Total

Contract

Cost

Estimated CostContract Work Item

Project Location:

MJBlack1 Text Box 6,875

MJBlack1 Text Box 6,875

SECTION 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 DEFINITIONS

1.1.1 Submittal

Shop drawings, product data, samples, and administrative submittals shall be presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."

1.1.2 Types of Submittals

Submittals shall be classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals may also be grouped as follows:

a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data submitted by Contractor prepared specifically for this contract by Contractor, subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion(s) of work.

b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.

c. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.

1.1.3 Submittal Descriptions (SD)

Construction Progress Schedule

Submittal Register

Schedule of Values

Work Plan

Environmental Protection Plan

Pre-dredge Survey and Quantity Computations

SD-02 Shop Drawings

SECTION 01 33 00 Page 2

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

Daily checklists

Final acceptance test and operational test procedure

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Post-dredge survey and computation

1.1.4 Approving Authority

Person authorized to approve submittal.

1.1.5 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.2 SUBMITTALS

Submit the following in accordance with the requirements of this section.

Submittal register

SECTION 01 33 00 Page 3

1.3 USE OF SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses.

1.3.1 Submittal Register

Submit submittal register. Do not change data in columns (a), (b), and (c) as delivered by the Government. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:

Column (d) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

1.4 PROCEDURES FOR SUBMITTALS

1.4.1 Reviewing, Certifying, Approving Authority

Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Project Manager unless otherwise specified for specific submittal.

1.4.2 Constraints

a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.

b. Submittals shall be complete for each definable feature of work;

components of definable feature interrelated as a system shall be submitted at same time.

c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.

d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.

1.4.3 Scheduling

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.

b. Except as specified otherwise, allow review period, beginning with receipt by approving authority, that includes at least 10 working days.

Period of review for each re-submittal is the same as for initial submittal.

1.4.4 Variations

Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to Government.

SECTION 01 33 00 Page 4

1.4.4.1 Considering Variations

Discussion with Contracting Officer prior to submission, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal

(VECP).

1.4.4.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. If lower cost is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

1.4.4.3 Warranting That Variation Are Compatible

When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.4.4.4 Review Schedule Is Modified

In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.

1.4.5 Contractor's Responsibilities

a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.

b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to Government, or delays to separate contractors.

c. Advise Contracting Officer of variation, as required by paragraph entitled "Variations."

d. Correct and resubmit submittal as directed by approving authority.

When resubmitting disapproved transmittals or transmittals noted for re-submittal, the Contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.

e. Furnish additional copies of submittal when requested by Contracting Officer.

f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.

SECTION 01 33 00 Page 5

g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.

1.4.6 Government Responsibilities

a. Note date on which submittal was received from Contractor on each Contract Item Approval Request Form.

b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.

c. Review submittals for conformance with project design concepts and compliance with contract documents.

d. Ensure that material is clearly legible.

e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.

1.4.7 Actions Possible

Submittals will be returned with one of the following notations:

a. Submittals marked "approved" "approved as submitted" authorize

Contractor to proceed with work covered.

b. Submittals marked "approved" "see below" authorize Contractor to proceed with work as noted provided Contractor takes no exception to the notations.

c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until re-submittal is approved.

1.5 FORMAT OF SUBMITTALS

1.5.1 Transmittal Form

Transmit electronically each submittal, unless otherwise noted in the submittal register and/or where electronic submission is not feasible (i.e.

samples), to office of approving authority. The maximum file size that may be emailed is 10 MB; anything larger must be submitted via hard copy or on a CD. Transmit submittals with transmittal form prescribed by Contracting Officer and standard for project. The transmittal form shall identify Contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations. Note: Submittals requiring hard copy submission shall be provided with carbon copy transmittal form provided by the Government.

SECTION 01 33 00 Page 6

1.5.2 Identifying Submittals

Identify submittals, except sample panel and sample installation, with the following information on each separate component of each submittal and transmittal form. The maximum file size for electronic email submittals shall be no larger than 10 MB. Identify each copy of each submittal identically, with the following:

a. Project title and location.

b. Construction contract number.

c. Section number of the specification section by which submittal is required.

d. Submittal description (SD) number of each component of submittal.

e. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.

f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.

g. Product identification and location in project.

1.5.3 Format for Product Data

a. Present product data submittals for each section. Include table of contents, listing page and catalog item numbers for product data.

b. Indicate, by prominent notation, each product which is being submitted;

indicate specification section number and paragraph number to which it pertains.

c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project.

1.5.4 Format for Shop Drawings

a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.

b. Present 8 1/2 by 11 inches sized shop drawings as part of the submittals required by section. Present larger drawings in sets.

c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."

d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.

SECTION 01 33 00 Page 7

1.5.5 Format of Administrative Submittals

a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply Contractor's approval stamp to document, but to a separate sheet accompanying document.

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Copies of Product Data

When hard copy submission is required, submit four copies of submittals of product data.

1.6.2 Number of Copies of Shop Drawings

Submit shop drawings in compliance with quantity requirements specified for product data.

1.6.3 Number of Copies of Administrative Submittals

Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.

Dredge Channel, CG Station Jones Beach; Project 9829696 SUBMITTAL REGISTER

Specification Section Number or Item Number

SD No., and Type of Submittal Material or Product

Specification Paragraph Number.

Planned Submittal Date

Date Fwd to Appr Auth /Date Recd From Contr

Date Fwd to Other Reviewer

Date Recd From Other Reviewer

Action Code

Date of Action

Mailed to Contr / Recd From Appr Auth

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j)

Section

01 32 00

SD-01, Preconstruction Submittals

1 Construction Schedule/Schedule of Values

1.1

Section

01 33 00

2 Submittal Register 1.2

Section

01 35 29

3 Accident Prevention Plan (APP)

1.2

4 Activity Hazard Analysis

(AHA)

1.2

Section

01 35 29

SD-11, Closeout

5 Reports, Certificate(s) of Compliance

1.2

Section

01 57 19

SD-01 Preconstruction

6 Environmental Protection Plan

1.3

Section

01 57 19

7 Laboratory Analysis 1.3

Section

01 57 19

8 Preconstruction Survey 1.3

9 Solid Waste Disposal Permit

1.3

10 Waste Determination Documentation

1.3

11 Disposal documentation for hazardous and regulated waste

1.3

12 Solid waste disposal report

1.3

13 Contractor Hazardous Material Inventory Log

1.3

Section

01 77 00

14 Post-dredge survey and quantity calculations

1.1

Section 32 92 19 SD-02 Shop Drawings

15 Site Restoration and Seeding Plan

1.4

Section 32 92 19 SD-03 Product Data

16 Fertilizer 1.4

Section 32 92 19 SD-06 Test Reports

17 Topsoil Composition Tests

1.4

Section 32 92 19 SD-07 Certificates

18 State certification and approval for seed

1.4

Section 32 92 19 SD-08 Manufacturer’s Instructions

19 Erosion Control Measures

1.4

Section

35 20 23

SD-02 Shop Drawings

20 Dredge Plan 1.2

21 Daily quantity calculations

1.2

22 Pre-dredge survey, cross sections, and quantity calculations

1.2

23 Post-dredge survey, cross sections, and quantity calculations

1.2

24 Delivery Tickets 1.2

SECTION 01 35 29 Page 1

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

Dredging operations have an offshore workplace with hazardous conditions.

Close attention must be paid to risk management and workplace safety. All contractor personnel that work over or near the water, must wear proper personal floatation devices.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A10.32 (2012) Personal Fall Protection Used in

Construction and Demolition Operations

ANSI A10.34 (2001; R 2012) Protection of the Public On or

Adjacent to Construction Sites

ANSI Z359.1 (2016) Safety Requirements for Personal Fall

Arrest Systems, Subsystems and Components

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.22 (2016) Articulating Boom Cranes

ASME B30.3 (2016) Construction Tower Cranes

ASME B30.5 (2011) Mobile and Locomotive Cranes

ASME B30.8 (2015) Floating Cranes and Floating Derricks

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-Required Confined Spaces

29 CFR 1919 Gear Certification

29 CFR 1926 Safety and Health Regulations for

Construction

29 CFR 1926.500 Fall Protection

CORPS OF ENGINEERS (COE)

EM 385-1-1 (2014) Safety -- Safety and Health

Requirements and Published Changes and Errata

SECTION 01 35 29 Page 2

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2018) Standard for Portable Fire

Extinguishers

NFPA 241 (2013) Safeguarding Construction, Alteration, and Demolition Operations

NFPA 51B (2014) Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2017) National Electrical Code

NFPA 70E (2018) Electrical Safety in the Workplace

Accident Prevention Plan (APP)

Activity Hazard Analysis (AHA)

Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."

Certificate of Compliance

1.3 QUALITY ASSURANCE

1.3.1 Meetings

The Safety Officer shall attend the pre-construction conference.

1.3.1.1 Weekly Safety Meetings

Hold weekly at the project site. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the QC Contractor Quality Control daily report.

1.3.1.2 Work Phase Meetings

The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.

SECTION 01 35 29 Page 3

1.3.1.3 New Employee Indoctrination

New employees will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.

1.3.2 Certifications

1.3.2.1 Accident Prevention Plan (APP)

Submit the APP at least 15 calendar days prior to start of work at the job site, following Appendix A of EM-385-1-1. Make the APP site specific.

Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHA as amendments to the APP. In accordance with contract quality control requirements each AHA will be reviewed during an on-site preparatory inspection.

1.4 ACCIDENT PREVENTION PLAN (APP)

Prepare the APP in accordance with EM-385-1-1 Table 1-1. Include the associated AHA and other specific plans, programs and procedures detailed in Paragraphs 01.A.09 and 01.A.10 of EM-385-1-1, some of which are listed below.

1.4.1 Contents of the Accident Prevention Plan

a. Name and safety related qualifications of safety officer (including training and any certifications).

b. Qualifications of competent and of qualified persons.

c. Identity of the individual who will complete exposure data (hours worked); accident investigations, reports and logs; and immediate notification of accidents to include subcontractors.

d. Emergency Response Plan. Conform to EM-385-1-1, paragraph 01.E and include a map denoting the route to the nearest emergency care facility with emergency phone numbers. Contractor may be required to demonstrate emergency response.

e. Critical Lift Plan. Weight handling critical lift plans shall be prepared and signed in accordance with EM-385-1-1, paragraph 16.c.18.

f. Fall Protection and Prevention (FP&P) Plan. The plan shall be site specific and address all fall hazards in the work place. It shall address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person shall prepare the plan. The plan shall include fall protection and prevention systems, equipment and methods employed, responsibilities, rescue and escape equipment and operations, training requirements, and monitoring methods. FP&P Plan shall be revised [once every six months] for lengthy projects, to reflect any new changes during the course of construction, due to changes of personnel, equipment, systems or work habits.

SECTION 01 35 29 Page 4

g. Silica Exposure Reduction. The plan shall include specific procedures to prevent employee silica inhalation exposures.

h. Training Records and Requirements. List of mandatory training and certifications which are applicable to this project (e.g. explosive actuated tools, confined space entry, fall protection, crane operation, vehicle operator, forklift operators, personal protective equipment);

list of requirements for periodic retraining/certification; outline requirements for supervisory and employee safety meetings.

i. Severe Weather Plan. Procedures of ceasing on-site operations during lightning or upon reaching maximum allowed wind velocities.

j. Emergency Lighting and Power Systems Plan (e.g. periodic testing of batteries for emergency lighting.)

1.5 ACTIVITY HAZARD ANALYSIS (AHA)

Prepare for each phase of the work. As a minimum, define activity being performed, sequence of work, specific hazards anticipated, control measures to eliminate or reduce each hazard to acceptable levels, training requirements for all involved, and the competent person in charge of that phase of work. For work with fall hazards, including fall hazards associated with scaffold erection and removal, identify the appropriate fall arrest systems. For work with materials handling equipment, address safeguarding measures related to materials handling equipment. For work requiring excavations, include excavation safeguarding requirements. The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.

Not Used.

3.1 CONSTRUCTION

Comply with EM-385-1-1, NFPA 241, the accident prevention plan, the activity hazard analysis and other related submittals and activity fire and safety regulations.

3.1.1 Hazardous Material Exclusions

Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited.

Exceptions to the use of any of the above excluded materials may be considered by Contracting Officer upon written request by Contractor.

3.1.2 Unforeseen Hazardous Material

The design should have identified materials such as PCB, lead paint, and friable and nonfriable asbestos. If additional material, not indicated, which may be hazardous to human health upon disturbance during construction

SECTION 01 35 29 Page 5 operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2 PERSONNEL PROTECTION

3.2.1 Hazardous Noise

Provide hazardous noise signs, and hearing protection, wherever equipment and work procedures produce sound-pressure levels greater than 85 dBA steady state or 140 dBA impulse, regardless of the duration of the exposure.

3.2.2 Fall Protection

Enforce use of the fall protection device designated for each specific work activity in the FP&P plan and/or AHA all times when an employee is on a surface 6 feet or more above lower levels. Personal fall arrest systems are required when working from an articulating or extendible boom, scissor lifts, swing stages, or suspended platform. Fall protection must comply with ANSI A10.32.

3.3 SCAFFOLDING

Employees shall be provided with a safe means of access to the work area on the scaffold. Climbing of any scaffold braces or supports not specifically designed for access is prohibited. Stair towers or ladders built into scaffold systems in accordance with EM 385-1-1 Appendix J are required for work platforms greater than 20 feet in height. Contractor shall ensure that employees that are qualified perform scaffold erection. Do not use scaffold without the capability of supporting at least four times the maximum intended load or without appropriate fall protection as delineated in the accepted fall protection plan. Minimum platform size shall be based on the platform not being greater in height than three times the dimension of the smallest width dimension for rolling scaffold. Some Baker type scaffolding has been found not to meet these requirements. Stationary scaffolds must be attached to structural building components to safeguard against tipping forward or backward. Special care shall be given to ensure scaffold systems are not overloaded. Outrigger brackets used to extend scaffold platforms on self supported scaffold systems for the storage of material is prohibited.

The first tie-in shall be at the height equal to 4 times the width of the smallest dimension of the scaffold base.

3.4 ELECTRICAL

3.4.1 Portable Extension Cords

Portable extension cords shall be sized in accordance with manufacturer ratings for the tool to be powered.

SECTION 01 35 29 Page 6

3.5 CRYSTALLINE SILICA

Grinding, abrasive blasting, and foundry operations of construction materials containing crystalline silica, shall comply with OSHA regulations, such as 29 CFR 1910.94, and EM-385-1-1, (Appendix C). The Contractor shall develop and implement effective exposure control and elimination procedures to include dust control systems, engineering controls, and establishment of work area boundaries, as well as medical surveillance, training, air monitoring, and personal protective equipment.

3.6 HOUSEKEEPING

3.6.1 Clean-up

All debris in work areas shall be cleaned up daily or more frequently as necessary. Construction debris may be temporarily located in an approved location, however garbage accumulation must be removed each day.

3.6.2 Dust Control

In addition to the dust control measures required elsewhere in the contract documents dry cutting of brick or masonry shall be prohibited. Wet cutting must address control of water run off.

Maintenance Dredging, CG Station Shinnecock PSN 12249163

SECTION 01 57 19 Page 1

SECTION 01 57 19

TEMPORARY ENVIRONMENTAL CONTROLS

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.1200 Hazard Communication

40 CFR 112 Oil Pollution Prevention

40 CFR 122.26 EPA National Pollutant Discharge Elimination

System Permit Regulations

40 CFR 241 Guidelines for Disposal of Solid Waste

40 CFR 243 Guidelines for the Storage and Collection of

Residential, Commercial, and Institutional Solid Waste

40 CFR 258 Subtitle D Landfill Requirements

40 CFR 260 Hazardous Waste Management Systems: General

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Generators of Hazardous Waste

40 CFR 263 Transporters of Hazardous Waste

40 CFR 264 Owners and Operators of Hazardous Waste

Treatment, Storage, and Disposal Facilities

40 CFR 265 Interim Status Standard for Owners and

Operators of Hazardous Waste Treatment, Storage, and Disposal Facilities

40 CFR 266 Management of Specific Hazardous Wastes and

Specific Types of Hazardous Waste Management Facilities

40 CFR 268 Land Disposal Restrictions

40 CFR 270 EPA Administrated Permit Programs: The

Hazardous Waste Permit Program

SECTION 01 57 19 Page 2

40 CFR 271 Requirements for Authorization of State Hazardous Waste Programs

40 CFR 272 Approved State Hazardous Waste Management

Programs

40 CFR 273 Universal Waste Management

40 CFR 279 Used Oil Regulations

40 CFR 280 Owners and Operators of Underground Storage

Tanks

40 CFR 300 National Oil and Hazardous Substances

Pollution Contingency Plan

40 CFR 355 Emergency Planning and Notification

40 CFR 372-SUBPART D EPA Toxic Chemical Release Reporting

Regulations

40 CFR 716 Health and Safety Data Reporting

40 CFR 761 Polychlorinated Biphenyls (PCBs)

Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions

49 CFR 173 Shipments and Packagings

49 CFR 178 Packagings

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA SW-846 (1996) Evaluating Solid Waste

(Physical/Chemical Methods)

EPA 832-R-92-005 Storm Water Management for Construction

Activities

1.2 DEFINITIONS

1.2.1 Sediment

Soil and other debris that have eroded and have been transported by runoff water or wind.

1.2.2 Solid Waste

Garbage, refuse, debris, sludge, or other discharged material (except hazardous waste as defined in paragraph entitled "Hazardous Waste" or hazardous debris as defined in paragraph entitled "Hazardous Debris"), including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.

Material not regulated as solid waste are: nuclear source or byproduct materials regulated under the Federal Atomic Energy Act of 1954 as amended;

suspended or dissolved materials in domestic sewage effluent or irrigation return flows, or other regulated point source discharges; regulated air

SECTION 01 57 19 Page 3 emissions; and fluids or wastes associated with natural gas or crude oil exploration or production.

a. Green waste: The vegetative matter from landscaping, land clearing and grubbing, including, but not limited to, grass, bushes, scrubs, small trees and saplings, tree stumps and plant roots. Marketable trees, grasses and plants that are indicated to remain, be re-located, or be re-used are not included.

b. Surplus soil: Existing soil that is in excess of what is required for this work, including aggregates intended, but not used, for on-site mixing of concrete, mortars and paving. Contaminated soil meeting the definition of hazardous material or hazardous waste is not included.

c. Inert construction and demolition debris: Broken or removed concrete, masonry, and rock asphalt paving; ceramics; roofing paper and shingles. Inert materials may be re-enforced with or contain ferrous wire, rods, accessories and weldments.

d. Wood: Dimension and non-dimension lumber, plywood, chipboard, hardboard. Treated and/or painted wood that meets the definition of lead contaminated or lead based contaminated paint is not included.

e. Scrap metal: Scrap and excess ferrous and non-ferrous metals such as re-inforcing steel, structural shapes, pipe and wire that are recovered or collected and disposed of as scrap. Scrap metal meeting the definition of hazardous material or hazardous waste is not included.

f. Paint cans: Metal cans that are empty of paints, solvents, thinners and adhesives. If permitted by the paint can label, a thin dry film may remain in the can.

g. Recyclables: Materials, equipment and assemblies such as doors, windows, door and window frames, plumbing fixtures, glazing and mirrors that are recovered and sold as recyclable.

1.2.3 Debris

Non-hazardous solid material generated during the construction, demolition, or renovation of a structure which exceeds 2.5 inch particle size that is: a manufactured object; plant or animal matter; or natural geologic material (e.g. cobbles and boulders). A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.

1.2.4 Hazardous Debris

As defined in paragraph entitled "Debris" of this section, debris that contains listed hazardous waste (either on the debris surface, or in its interstices, such as pore structure) per 40 CFR 261; or debris that exhibits a characteristic of hazardous waste per 40 CFR 261.

SECTION 01 57 19 Page 4

1.2.5 Chemical Wastes

This includes salts, acids, alkalies, herbicides, pesticides, and organic chemicals.

1.2.6 Garbage

Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.

1.2.7 Hazardous Waste

Hazardous waste as defined in 40 CFR 261 or as defined by applicable State and local regulations.

1.2.8 Oily Waste

Petroleum products and bituminous materials.

1.2.9 Regulated Waste

Those solid waste that have specific additional Federal, state, or local controls for handling, storage, or disposal.

1.2.10 Class I Ozone Depleting Substance (ODS)

Class I ODS is defined in Section 602(a) of The Clean Air Act and includes the following chemicals:

chlorofluorocarbon-11 (CFC-11) chlorofluorocarbon-213 (CFC-213) chlorofluorocarbon-12 (CFC-12) chlorofluorocarbon-214 (CFC-214) chlorofluorocarbon-13 (CFC-13) chlorofluorocarbon-215 (CFC-215) chlorofluorocarbon-111 (CFC-111) chlorofluorocarbon-216 (CFC-216) chlorofluorocarbon-112 (CFC-112) chlorofluorocarbon-217 (CFC-217) chlorofluorocarbon-113 (CFC-113) halon-1211 chlorofluorocarbon-114 (CFC-114) halon-1301 chlorofluorocarbon-115 (CFC-115) halon-2402 chlorofluorocarbon-211 (CFC-211) carbon tetrachloride chlorofluorocarbon-212 (CFC-212) methyl chloroform

1.2.11 Hazardous Materials

Any material that is regulated as a hazardous material in accordance with 49 CFR 173, requires a Material Safety Data Sheet (MSDS) in accordance with 29 CFR 1910.1200, or which during end use, treatment, handling, storage, transportation or disposal meets or has components which meet or have the potential to meet the definition of a Hazardous Waste in accordance with 40 CFR 261. Throughout this specification, hazardous material includes hazardous chemicals.

1.3 SUBMITTALS

SECTION 01 57 19 Page 5

Environmental protection plan;

Laboratory analysis

Some of the records listed below are also required as part of other submittals.

Preconstruction survey

Solid waste disposal permit

Waste determination documentation

Disposal documentation for hazardous and regulated waste

Solid waste disposal report

Contractor Hazardous Material Inventory Log

1.4 REPORTS

1.4.1 Preconstruction Survey

Perform a preconstruction survey of the project site with the Contracting Officer, and take photographs showing existing environmental conditions in and adjacent to the site. Submit a report for the record.

1.4.2 Solid Waste Disposal Permit

Submit one copy of a State and local permit or license showing such agencies’ approval of the disposal plan before transporting wastes off Government property.

1.4.3 Waste Determination Documentation

The Contractor shall submit all Waste Determination Documentation for all Contractor-derived wastes to be generated. The waste determination must be based upon either a constituent listing from the manufacturer used in conjunction with consideration of the process by which the waste was generated, EPA approved analytical data, or laboratory analysis (Material Safety Data Sheets (MSDS) by themselves are not adequate). All support documentation must be attached to the Waste Determination form.

1.4.4 Disposal Documentation for Hazardous and Regulated Waste

Submit a copy of the applicable EPA and State permit(s), manifest(s), or license(s) for transportation, treatment, storage, and disposal of hazardous and regulated waste by permitted facilities.

SECTION 01 57 19 Page 6

1.4.5 Solid Waste Disposal Report

Monthly, the Contractor shall submit a solid waste disposal report to the Contracting Officer. For each waste, the report shall state the classification (using the definitions provided in this section), amount, location, and name of the business receiving the solid waste. The Contractor shall include copies of the waste handling facilities' weight tickets, receipts, bills of sale, and other sales documentation. In lieu of sales documentation, the Contractor may submit a statement indicating the disposal location for the solid waste which is signed by an officer of the Contractor firm authorized to legally obligate or bind the firm. The sales documentation or Contractor certification shall include the receiver's tax identification number and business, EPA or State registration number, along with the receiver's delivery and business addresses and telephone numbers.

For each solid waste retained by the Contractor for his own use, the Contractor shall submit on the solid waste disposal report the information previously described in this paragraph. Prices paid or received shall not be reported to the Contracting Officer unless required by other provisions or specifications of this Contract or public law.

1.5 ENVIRONMENTAL PROTECTION REQUIREMENTS

Provide and maintain, during the life of the contract, environmental protection as defined. Plan for and provide environmental protective measures to control pollution that develops during normal construction practice. Plan for and provide environmental protective measures required to correct conditions that develop during the construction of permanent or temporary environmental features associated with the project. Comply with Federal, State, and local regulations pertaining to the environment, including water, air, solid waste, hazardous waste and substances, oily substances, and noise pollution.

1.5.1 Contractor Liabilities for Environmental Protection

The Contractor is advised that this project and the station are subject to Federal, State, and local regulatory agency inspections to review compliance with environmental laws and regulations.