SF30_Amendment_0001.pdf
PDF 398 KB Posted
- Solicitation number
- 70Z0G119BPRV10300
About this file
Amendment 00001 to solicitation 70Z0G119BPRV10300
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO.
00001
3. EFFECTIVE DATE
04/15/2019
4. REQUISITION/PURCHASE REQ.
2119G19PRV10300
5. PROJECT NO. (If applicable)
12249163
6. ISSUED BY CODE 51283 7. ADMINISTERED BY (If other than Item 6) CODE 51283
Contracting Officer USCG Civil Engineering Unit Providence
475 Kilvert St., Suite 100 Warwick, RI 02886
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
TO ALL POTENTIAL OFFERORS
AMENDMENT MUST BE ACKNOWLEDGED
9A. AMENDMENT OF SOLICITATION NO.
70Z0G119BPRV10300
9B. DATED (SEE ITEM 11)
3/21/2019
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE 834953036 FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[ x ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return __ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The solicitation referenced in block 9 for the Station Shinnecock dredging, is amended as follows. This amendment provides clarifications and answers bidders concerns.
The due date for receipt of bids remains unchanged. Bids will be opened on 4/23/2019 at 2:00 pm., at the address in block 6.
-continued-
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
Jean Bretz
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
4/15/19
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83) PREVIOUS EDITION UNUSABLE Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 00001
Q1: The solicitation states that work must be completed by June 30th, 2019. However the bid due date is April 23, 2019 and that leaves 68 days from dates bids are due until June 30th. Assuming the notice to proceed is issued sometime after April 23rd, that leaves even less days. Will the completion date be adjusted based on the NTP date?
A1: The completion date is set in accordance with environmental permits. It is the intent of USCG to issue Notice of Award and NTP as soon as feasible following bid opening.
Q2: What is the allowable load rating for the south corner of the steel sheet pile bulkhead with concrete cap/wale?
Can we utilize off-loading equipment on crane mats close to the wall to allow for off-loading of the scows?
A2: Offloading equipment on mats may be used south of the main building and a minimum of 10-feet horizontal setback from the bulkhead/sheetpile. Any existing landscaping disturbed during construction activities will be restored by the contractor to the pre-construction conditions.
Q3: Will access be allowed to the parking lot to stage a crane between the boat ramp and T-dock for temporary offloading of trucks and launching of marine equipment directly into the water? This would be the preferred approach to mobilization rather than backing trucks across the temporary road/spoils area and around the communication tower to a crane set on mats in the south corner.
A3: No. The parking lot is for use by MMB personnel.
Q4: Is access dredging allowed in the south corner of the boat basin to create draft for the marine equipment to operate?
A4: No. Additional dredging in the boat basin is not permitted.
Q5: Can a larger gate be installed at the construction entrance for construction equipment? The current gate is very narrow.
A5: The existing gate at the main entrance may not be modified. Either of the existing gates to the south of the communications tower may be used or expanded, with proper submittal and approval by the Coast Guard.
Q6: Can a second construction gate be added and temporary haul road to create a better traffic flow pattern?
A6: With proper submittal of proposed location and gate and approval by Coast Guard, additional gates and temporary access roads may be included.
Q7: Could you please clarify the dredging area shown in Sheet C-102? The dotted area depicted as the dredge area is only 20'x60'. This, with a calculated cut face of 2.5' (going from -5.5' to -8' with overdredge), is only ~100 CY of material.
I also see elevation cross sections for areas of the channel, with no corresponding areas marked in the plan view.
Please clarify where the 2500 CY requiring removal is located.
A7: The hatch pattern indicating the area to dredge may not have come through clearly in the printing process. The area to be dredged is delineated with coordinates (e.g. N 252,490 E 1,398,707) and dimensions all around (i.e. 145’, 96’, 204’, 100’, 265’ & 50’).
Q8 There were no permits provided in appendix A. Please provide if able for review.
A8: Draft conditions received. "As of now, the permit-specific conditions are:
(A) The permittee understands and agrees that, if future operations by the United States require the removal, relocation, or other alteration, of the structure or work herein authorized, or if, in the opinion of the Secretary of the Army or his authorized representative, said structure or work shall cause unreasonable obstruction to the free navigation of the navigable waters, the permittee will be required, upon due notice from the Corps of Engineers, to remove, relocate, or alter the structural work or obstructions caused thereby, without expense to the United States. No claim shall be made against the United States on account of any such removal or alteration.
Amendment 00001
(B) The permittee shall sign and submit the attached compliance certification form to this office within 30 days of COMPLETION of the regulated activity authorized by this permit and any mitigation work required by Special Condition.
(C) The permittee, and their agents, shall take actions to prevent construction materials, including debris, from entering any waterway to become drift or pollution hazards.
Note, these Special Conditions are typical for any project verified under the Nationwide Permit program. To my knowledge and according to the correspondence between USCG and NMFS(EFH) this office does not have any other Special Conditions to add to the permit."
Q9: The specification limits operations to 10.5 hours per day, 7 days per week. Are there time of day restrictions as well?
As this is a shallow water project, the work will have to be closely coordinated with tidal events. Having operations restricted to specific hours will greatly affect scheduling of work.
A9: The specifications allow for written request for work outside the hours listed. It is recognized that this project will follow tidal events and the proposed schedule should reflect such. Coast Guard personnel are housed at the main building and therefore, work will be prohibited between 2200 and 0630 (10 pm and 6:30 am).
Q10: What type of survey will be required for pre and post dredge measurements? Single trace or multi beam?
A10: Survey shall be of sufficient quality and accuracy as required to comply with Specification Section 35 20 23 paragraph 1.11.
Q11: Will there be a site visit scheduled prior to bidding?
A11: Not a scheduled site visit. See Section L of the solicitation for site visit instructions.
Q12: Will an area of the bulkhead be made available for offloading dredge spoils from barges into the upland dewatering area?
A12: Offloading equipment on mats may be used south of the main building and a minimum of 10-feet horizontal setback from the bulkhead/sheetpile. Any existing landscaping disturbed during construction activities will be restored by the contractor to the pre-construction conditions.
Q13: Will the contractor be allowed to dewater material on barges?
A13: No.
Q14: As the upland disposal site is mandated by contract, who will be responsible for any tipping fees, if applicable?
A14: Contractor shall be responsible for tipping/disposal fees, if any.
Q15: Will there be a silt curtain required on the project? Where would it be located on the project so dimensions can be taken?
A15: Turbidity curtains are not expected to be required, at this time. Turbidity curtain will be the responsibility of the Contractor, if needed, to minimize turbidity during dredge activities; however, at no time shall the Contractor or his/her equipment impede or block Coast Guard access to or from the boat basin. Dredge equipment will not be stored or anchored in the entrance channel when not in use.
-End-