DEPARTMENT OF HOMELAND SECURITY

UNITED STATES COAST GUARD

SHORE INFRASTRUCTURE LOGISTICS CENTER

SPECIFICATIONS

FOR

Repair ATON Structures

USCGC BOLLARD

New Haven, CT

PSN 7940856

WILLIAM BOGER, PE GERRY GOSSELIN, PE

DESIGN PROJECT MANAGER DESIGN TEAM SUPERVISOR

GERRY GOSSELIN, BY DIRECTION

COMMANDING OFFICER

UNITED STATES COAST GUARD

CIVIL ENGINEERING UNIT PROVIDENCE

475 KILVERT STREET, SUITE 100

WARWICK, RHODE ISLAND 02886

Repair ATON Structures 7940856

USCGC BOLLARD

TABLE OF CONTENTS

SUMMARY OF WORK 01 11 00

WORK RESTRICTIONS 01 14 00

CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES 01 32 00

SUBMITTAL PROCEDURES 01 33 00

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS 01 35 29

TEMPORARY FACILITIES AND CONTROLS 01 50 00

TEMPORARY ENVIRONMENTAL CONTROLS 01 57 19

CLOSEOUT PROCEDURES 01 77 00

OPERATION AND MAINTENANCE DATA 01 78 23

DEMOLITION 02 41 00

RIP RAP, BOULDERS AND BEDDING 31 37 00

EARTHWORK 32 10 02

Appendix A: Black Rock Harbor Entrance LT 2A Existing

Condition Pictures

Appendix B: Housatonic River Breakwater LT 2A Existing

Appendix C: Duck Island North Breakwater LT Existing

Appendix D: Army Corps of Engineers and Connecticut

Department of Energy and Environmental Protection

Permits

SECTION 01 11 00 Page 1 of 6

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes the following and any incidental related work. Coordinate with CGC BOLLARD as required.

a. Black Rock Harbor Entrance LT 2A: Remove and dispose the existing 15’ 5’x5’ skeletal structure IAW local, state and federal regulations. Remove and store the day boards and brackets, remove all other navigational equipment such as the light and batteries, and deliver this equipment to the Officer in Charge of CGC BOLLARD at Sector Long Island Sound in New Haven, CT. Cut any protruding anchor rods flush with the surface and abandon the existing concrete caisson at its existing location.

Provide and evenly place 100 cubic yards (CY) of riprap (similar in composition to the current riprap) under and around the foundation of the structure above MHW with the sides having a 1.5:1 (H:V) slope as indicated in the drawing. The end product shall look similar to a truncated cone. A unit price per cubic yard shall be provided as part of the bid for any additional rip rap if deemed necessary by the contracting officer. Each stone shall weigh at least 2000 lbs.

Build IAW with the provided drawings a new concrete foundation.

Assemble and install a Government Furnished Equipment (GFE) 15’ 5’x5’ skeletal structure, which will be picked up unassembled at the CG facility in New Haven, CT. Install the stored day boards and brackets utilizing new hardware to be provided by the contractor (316 stainless steel (s/s), 304 s/s for U-Bolts).

Contractor shall provide new concrete, sand, grout/epoxy, anchor rods (316 s/s), tower hardware (316 s/s, 304 s/s for U-Bolts), manhole and riprap per the drawings; all costs shall be included in the bid.

Upon completion of work contact the CGC BOLLARD for navigational equipment installation.

SECTION 01 11 00 Page 2 of 6

Figure 1 Black Rock Harbor Entrance LT 2A

b. Housatonic River Breakwater LT 2A: Provide and evenly place 80 cubic yards (CY) of riprap (similar in composition to the current riprap) around the foundation of the structure above MHW with the sides having a 1.5:1 (H:V) slope as indicated in the drawing. The end product shall look similar to a truncated cone. A unit price per cubic yard shall be provided as part of the bid for any additional rip rap if deemed necessary by the contracting officer.

Each stone shall weigh at least 2000 lbs.

Provide a new concrete foundation as detailed in the drawings.

Assemble and install a Government Furnished Equipment (GFE) 15’ 5’x5’ skeletal structure, which will be picked up unassembled at the CG facility in New Haven, CT. Provide new concrete, sand, grout/epoxy, anchor rods (316 s/s), tower hardware (316 s/s, 304 s/s for U-Bolts), manhole and riprap per the drawings; all costs shall be included in the bid. The existing concrete caisson shall remain, abandoned in place. Upon completion of work contact the CGC BOLLARD for navigational equipment installation.

Figure 2 Housatonic River Breakwater LT 2A

c. Duck Island North Breakwater Light: Replace the concrete foundation and conduct misc repairs to the structure as needed, which includes providing and replacing all hardware. Build IAW with the provided drawings a new concrete foundation. Relocate and re-install the existing 10’ 5’x5’ skeletal structure and all navigational equipment, which includes the light and day boards. Replace all hardware on the existing structure, contractor provided. If the

SECTION 01 11 00 Page 3 of 6 skeletal tower requires new members due to corrosion, etc., contractor shall notify the contracting officer at the preconstruction meeting or if at a later date there will be a 10 workday delivery period, and new members will be delivered to Sector Long Island Sound for the contractor to pick up at no additional cost to the government. Upon completion of the project, no tower part shall show signs of corrosion as deemed by the contracting officer by visual inspection. Provide new concrete, sand, grout/epoxy, anchor rods (316 s/s), tower hardware (316 s/s, 304 s/s for U-Bolts) and manhole per the drawings; all costs shall be included in the bid.

The existing concrete caisson shall remain, abandoned in place.

The contractor shall cut flush with the concrete caisson all anchor rods and remove all debris, specifically metal pieces and concrete stones less than 100lbs, from the worksite.

Figure 3 Duck Island North Breakwater Light

d. Contract time will allow for 90 days for submittals and other administrative tasks followed by the performance period, during which work will be performed. Performance period shall be no longer than 30 consecutive days and temperatures must be consistently (7 days) above 50 degrees Fahrenheit once the concrete work commences.

e. The contractor shall notify CGC BOLLARD (BMC Christopher Connolly,

(203) 468-4465 and the contracting officer 15 days before construction to publish the disestablishment of the aid, and shall notify the proper Coast Guard and civilian authorities as required if a notice to mariners needs to be published about the aid being temporarily extinguished.

1.1.2 Location

The work shall be located at the following locations. Refer to Coast Pilot 2 and local NOAA charts for further details of the area.

a. Black Rock Harbor Entrance LT 2A: Latitude 41-08-13.529N and longitude 073-13-02.045W, approximately as indicated on the

SECTION 01 11 00 Page 4 of 6 drawings. The exact location will be shown by the Contracting Officer.

b. Housatonic River Breakwater LT 2A: Latitude 41-09-38.657N and longitude 073-05-34.939W, approximately as indicated on the

c. Duck Island North Breakwater Light: Latitude 41-15-36.818N and longitude 072-28-29.836W, approximately as indicated on the

1.2 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which is to remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.3 CONTRACT DRAWINGS

The following drawings accompany this specification and are a part thereof.

DRAWING LIST:

Sheet Drawing Site Location Title 1 of 5 G-001 ALL COVER SHEET 2 of 5 C-201 BLACK ROCK HBR ENTR LT 2A RENEW RIPRAP AND TOWER 3 of 5 C-202 HOUSATONIC RIVER BKW LT 2A RENEW RIPRAP AND TOWER 4 of 5 C-203 DUCK ISLAND N. BREAKWATER LT RENEW CONCRETE CAISSON 5 of 5 C-204 CG STD 5BY5 CONSTRUCTION 5’X5’ CONCRETE FOUNDATION 6 of 6 C-205 CG STD 5BY5 CONSTRUCTION 5’X5’ TOWER ASSEMBLY PLAN

One set of full size contract drawings, maps, and specifications will be furnished to the Contractor without charge. Reference publications will not be furnished.

Contractor shall immediately check furnished drawings and notify the Government of any discrepancies.

1.4 SUPERVISION

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

SECTION 01 11 00 Page 5 of 6

1.5 JOB MEETINGS

All conferences or meetings shall be at the contracting officer’s discretion and will either be on-site (vessel transportation will be provided by contractor for all attendees), at Sector Long Island Sound in New Haven, CT or at CEU Providence in Warwick, RI. The contractor shall incur all transportation costs.

1.6 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the contract for construction, safety program, preparation of the schedule of values, shop drawings, and other submittals, scheduling/programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.

1.7 INSPECTION

The Contractor shall keep the COR or duly appointed representative fully informed of contract operations and plans so that a representative may arrange to be present at various times that work is being performed.

1.7.1 Contractor’s Daily Log

The Contractor shall complete the USCG Daily Log form at the end of each working day and deliver it to the Government Inspector. The Government Inspector will attest to its accuracy by initialing the form and forwarding that form to CEU Providence. The form will be provided to the Contractor by the COR.

1.7.2 Transportation to the Work Site

The Contractor shall accommodate requests from the Contracting Officer, or duly appointed representatives, for transportation to and from the work site. These transportation requests may be coordinated with the contractors normal trips back and forth from the work site, provided such coordination doesn’t delay the inspection by more than 4 hours.

1.8 QUALITY ASSURANCE

1.8.1 Manufacturer’s Make and Model Number

Manufacturer’s make and model number, where used, are used for descriptive purposes only, and are intended to indicate the standard of material or articles required. The design is based on the listed manufacturer and model as noted in the plans and/or in the specifications, but is not intended to limit the Contractor to the manufacturer indicated. If an alternate manufacturer or model number is proposed or substituted, it shall be the Contractor’s responsibility to ensure that the substituted equipment meets or exceeds the performance data of the specified equipment, that the equipment can be delivered to the location required without building alteration, that it fits within the designated space, and that access as indicated on the contract documents, and as required by the equipment

SECTION 01 11 00 Page 6 of 6 manufacturer, will be provided. Substitutions will be considered as “or approved equal.”

1.8.2 Buy American Act Compliance

All equipment purchased by U.S. Government agencies must comply with the “Buy American Act” (BAA). In summary, this means that the equipment or systems installed must be made in the USA.

1.9 SALVAGE MATERIAL AND EQUIPMENT

Items designated on the drawings for reuse, shall be carefully removed and stored in safe location on site for reinstallation as directed by the COR.

Contractor shall maintain property control records for material or equipment designated as salvage. Contractor’s system of property control may be used if approved by the COR. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the COR.

1.10 ABBREVIATIONS AND DEFINITIONS

CC - Communications Center.

COR - The CG Contracting Officer Representative with specific responsibilities, including enforcement of Contract Document requirements.

FED – Facilities Engineering Department at USCG Sec New York, Fort Wadsworth, Staten Island.

Refer to Drawing G-001 for additional Abbreviations and Definitions.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

--End of Section--

Section 01 14 00 Page 1 of 3

SECTION 01 14 00

WORK RESTRICTIONS

1.1 CONTRACTOR ACCESS AND USE OF PREMISES

1.1.1 USCG Regulations

Ensure that Contractor personnel employed become familiar with and obey USCG regulations including safety, fire, traffic, environmental and security regulations. Keep within the limits of the work and avenues of ingress and egress. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.

Coordinate access to each facility and the project work areas with the COR.

Submit a typewritten list on company letterhead of all Contractor employees who will be on site to the COR. The list shall contain name and date of birth. Each person on site shall carry valid photo identification.

Submit a typewritten list on company letterhead of all Contractor related vehicles (work and personal) that will be left unattended within the facility to the COR.

Do not enter private rooms/areas (including Offices and Berthing Rooms) without a Government escort.

The installation of any unauthorized electric, electronic, or any other type of monitoring device is strictly forbidden. Any violation of this directive will result in immediate removal of the person(s) responsible, and their employer, from the project for an indefinite period of time, and legal action against the parties involved.

1.1.1.1 Spud

All barges, tugs and other contractor vessels shall not anchor in or near the vicinities of the work site. Spuds are the only approved method to secure any vessel at the work site. Follow all local, state and federal regulations for navigational rules, anchorages, etc.

1.1.2 Working Hours

Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer (COR) Monday through Friday, excluding Government holidays.

Normal working hours shall be between 0730 and 1800, to be finalized at the pre-construction conference. If work outside these hours is required, a request stating the hours proposed shall be submitted to the COR in writing.

Section 01 14 00 Page 2 of 3

1.1.3 Work Outside Regular Hours

Work outside regular working hours requires COR approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, and type of work to be performed. Based on the justification provided, the COR may approve work outside regular hours.

Note: Based on the anticipated Construction Phasing Schedule, it is expected that there will be certain periods when work will take place outside regular hours. Work identified on an approved Construction Phasing Schedule, and discussed one week in advance, will not need formal approval.

During periods of darkness, the different parts of the work shall be lighted in a manner approved by the COR.

1.1.4 Existing Structures

The Contractor shall be working on or around existing structure(s), which is not occupied, however, still operational, such as fog and light signals.

1.1.5 Utility Cutovers and Interruptions

The contractor is responsible for any utility requirements to complete the work, which includes, but not limited to: water, sewage and electrical.

1.1.6 Transportation to the Work Site

The Contractor shall accommodate requests from the Contracting Officer, or duly appointed representatives, for transportation to and from the work site. These transportation requests may be coordinated with the contractors normal trips back and forth from the work site, provided such coordination doesn’t delay the inspection by more than 4 hours.

1.2 SECURITY REQUIREMENTS

1.2.1 Areas Not Covered by Contract

The Contractor will not be permitted to enter Buildings or areas not covered by this contract, except by prior approval of the COR.

1.2.2 Staging Area

The contractor is responsible for following any federal, state and local regulations at their determined staging area. The contractor shall not utilize any CG facility as a staging area. The contractor is responsible for finding such an area for a staging area.

1.2.3 Parking

The contractor is responsible for following any federal and local parking regulations at their determined staging area.

1.3 CONSTRUCTION SCHEDULE

Section 01 14 00 Page 3 of 3

In addition to the information and the requirements of this specification section, refer to contract drawings, and specification Section 01 32 01 PROJECT SCHEDULE, which are provided to generally indicate the complexity and requirements for the manner in which work shall proceed. The Contractor shall provide a submittal for review and approval to the Government which details the Construction Schedule.

Not Used

Section 01 32 00 Page 1 of 3

SECTION 01 32 00

CONSTRUCTION SCHEDULE/SCHEDULE OF VALUES

1.1 SUMMARY

The requirements of this Section apply to, and are a component part of each Section of the Specifications.

1.2 SUBMITTALS

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Construction Progress Schedule

Schedule of Values

1.3 CONSTRUCTION SCHEDULE AND SCHEDULE OF VALUES

At the Pre-Construction Conference, submit a Construction Schedule and Schedule of Values in accordance with FAR Clause 52.236.15.

The Construction Schedule and Schedule of Values as approved by the Government is not a substitute for quantities conveyed by the specification and drawings and those required for a complete job. Omissions and errors on the Construction Schedule and Schedule of Values are the responsibility of the Contractor.

Payments will not be made until the Schedule of Values has been submitted to and approved by the COR.

The Construction Schedule shall clearly indicate the start and completion dates of major work components. The Schedule of Values shall clearly indicate unit value of all major work components.

1.3.1 Construction Schedule

Once approved by the Government, the Construction Schedule shall be maintained by the Contractor as a fluid document, used during job meetings to review upcoming work. At a minimum, a two week “look ahead” will be discussed at each job meeting once the period of on-site construction approaches (i.e. within one month of start of On-Site Construction).

The Coast Guard views the Construction Schedule, and management of it, to be a critical component for the success of the project. It is in the best interest of the Government and the Contractor to complete the work in a thoughtful, efficient manner in order to maximize resources, and minimize the period of construction.

The Construction Schedule shall incorporate at a minimum the following

Section 01 32 00 Page 2 of 3

Activities:

a. Mobilization

b. Demobilization

c. Pre-construction Submittals

d. Work Activities

e. In-Progress Submittals

f. Final Government Inspection

g. Close-Out Submittals; i.e. Testing Balancing Reports, Warranties, Operation and Maintenance Manuals, Posted Instructions

h. Record Drawings

i. Factors which Constitute Potential Interruptions to

Facility Operations

Pre-Construction Submittals are those activities which encompass the obtaining, submission, review and approval of submittals necessary prior to the start of the related work. Contractor shall annotate all such activities into the progress schedule with their forecasted time periods.

These activity periods shall not be exclusive of the contract performance period. No work shall commence until the respective submittals have been approved.

1.3.2 Schedule of Values

The value of all major work components within the project shall be identified on the Schedule of Values, using quantities and values that are appropriate to the contract structure of the project, and tasks involved.

The Schedule of Values shall be based on the actual breakdown of the Bid Price, and shall clearly indicate unit value of all major work components.

Line items shall be established to support not only the work of each trade and associated sub-contractor, but the progress of phased work, in order to facilitate review and approval of Contractor requisitions for payment. The cost of Insurance shall not be listed as a separate item but included as part of each item of work. The actual cost of bonds may be paid as the first progress payment when a receipt from the bonding company is presented to the COR. In addition, keep the Government Inspector informed daily of the expected delivery dates for major pieces of equipment and materials.

1.4 CONSTRUCTION SCHEDULE UPDATES

Update the Construction Schedule as required, and in any event in advance of each Job Meeting, and distribute to Job Meeting participants at (or in advance of) each Job Meeting, and when schedule has been revised. Reflect any changes occurring since the last update. Submit copies of the purchase orders and confirmation of the delivery dates as directed.

Section 01 32 00 Page 3 of 3

Not Used

3.1 PROGRESS UPDATES

3.1.1 General

A revised Construction Schedule and Schedule of Values shall be issued by the Contractor on a monthly basis. In addition, any revisions to the Construction Schedule and Schedule of Values such as modifications or delays shall be reflected by Contractor submission of an updated Construction Schedule and Schedule of Values.

3.1.2 Modifications

When a modification is issued by the Government, record the modification as the last activity of the Construction Schedule and Schedule of Values and include the value of the modification. Adjust the Schedule of Values to reflect the inclusion of the modification. Revise the Construction Schedule portion of the form to annotate the progress change. Enter all modifications in this manner in sequential order.

-- End of Section --

SECTION 01 33 00 Page 1 of 10

SECTION 01 33 00

SUBMITTAL PROCEDURES

1.1 DEFINITIONS

1.1.1 Submittal

Shop drawings, product data, samples, and administrative submittals presented for review and approval. Contract Clauses "FAR 52.236-5, Material and Workmanship," paragraph (b) and "FAR 52.236-21, Specifications and Drawings for Construction," paragraphs (d), (e), and (f) apply to all "submittals."

1.1.2 Types of Submittals

All submittals are classified as indicated in paragraph "Submittal Descriptions (SD)". Submittals also are grouped as follows:

a. Shop drawings: As used in this section, drawings, schedules, diagrams, and other data prepared specifically for this contract, by contractor or through contractor by way of subcontractor, manufacturer, supplier, distributor, or other lower tier contractor, to illustrate portion of work.

b. Product data: Preprinted material such as illustrations, standard schedules, performance charts, instructions, brochures, diagrams, manufacturer's descriptive literature, catalog data, and other data to illustrate portion of work, but not prepared exclusively for this contract.

c. Samples: Physical examples of products, materials, equipment, assemblies, or workmanship that are physically identical to portion of work, illustrating portion of work or establishing standards for evaluating appearance of finished work or both.

d. Administrative submittals: Data presented for reviews and approval to ensure that administrative requirements of project are adequately met but not to ensure directly that work is in accordance with design concept and in compliance with contract documents.

1.1.3 Submittal Descriptions (SD)

Submittal register

Construction Progress Schedule

Schedule of values

Health and safety plan

SECTION 01 33 00 Page 2 of 10

Accident Prevention Plan (APP)

Activity Hazard Analysis (AHA)

Work plan

Quality control plan

Traffic control plan

Construction site plan

Storage inventory form

Dirt and dust control plan

Environmental protection plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the contractor for integrating the product or system into the project.

Drawings prepared by or for the contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-05 Design Data

SECTION 01 33 00 Page 3 of 10

Calculations, mix designs, analyses or other data pertaining to a part of work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. (Testing must have been within three years of date of contract award for the project.)

Report which includes findings of a test required to be performed by the contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports

Daily checklists

Final acceptance test and operational test procedure

SD-07 Certificates

Statements signed by responsible officials of manufacturer of product, system or material attesting that product, system or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a supplier, installer or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

Confined space entry permits.

SD-08 Manufacturer's Instructions

Preprinted material describing installation of a product, system or material, including special notices and Material Safety Data sheets concerning impedances, hazards and safety precautions.

SD-09 Manufacturer's Field Reports

Documentation of the testing and verification actions taken by manufacturer's representative to confirm compliance with manufacturer's standards or instructions.

Factory test reports.

SD-10 Operation and Maintenance Data

SECTION 01 33 00 Page 4 of 10

Data intended to be incorporated in operations and maintenance manuals.

Equipment/product warranty list

SD-11 Closeout Submittals

Reports

Certificate of Compliance

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

As-built drawings

Special warranties

Solid waste disposal permit

Waste determination documentation

Regulatory notification

Solid waste disposal report

Contractor hazardous material inventory log

Posted operating instructions

Training plan

1.1.4 Approving Authority

Person authorized to approve submittal.

1.1.5 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce construction and materials, products, equipment, and systems incorporated or to be incorporated in such construction.

Submit the following in accordance with the requirements of this section:

Submittal register

1.3 USE OF SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data in columns (a), (b), (c), and (d) as delivered by government.

SECTION 01 33 00 Page 5 of 10

1.3.1 Submittal Register

Submit submittal register. Verify that all submittals required for project are listed and add missing submittals. Complete the following on the register:

Column (e) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

1.4 PROCEDURES FOR SUBMITTALS

1.4.1 Reviewing, Certifying, Approving Authority

Government organization shall be responsible for reviewing and certifying that submittals are in compliance with contract requirements. Approving authority on submittals is the Project Manager unless otherwise specified for specific submittal.

1.4.2 Constraints

a. Submittals listed or specified in this contract shall conform to provisions of this section, unless explicitly stated otherwise.

b. Submittals shall be complete for each definable feature of work;

components of definable feature interrelated as a system shall be submitted at same time.

c. When acceptability of a submittal is dependent on conditions, items, or materials included in separate subsequent submittals, submittal will be returned without review.

d. Approval of a separate material, product, or component does not imply approval of assembly in which item functions.

1.4.3 Scheduling

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential requirements to resubmit.

b. Except as specified otherwise, allow review period, beginning with receipt by approving authority that includes at least 10 working days. Period of review for each resubmittal is the same as for initial submittal.

1.4.4 Variations

Variations from contract requirements require Government approval pursuant to contract Clause entitled "FAR 52.236-21, Specifications and Drawings for Construction" and will be considered where advantageous to government.

1.4.4.1 Proposing Variations

When proposing variation, deliver written request to the contracting officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost

SECTION 01 33 00 Page 6 of 10 is a benefit, also include an estimate of the cost saving. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.

1.4.4.2 Warranting That Variation Is Compatible

When delivering a variation for approval, contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work, and deliver the same service life and performance.

1.4.4.3 Review Schedule Is Modified

In addition to normal submittal review period, a period of 5 working days will be allowed for consideration by the Government of submittals with variations.

1.4.5 Contractor's Responsibilities

a. Determine and verify field measurements, materials, field construction criteria; review each submittal; and check and coordinate each submittal with requirements of the work and contract documents.

b. Transmit submittals to Contracting Officer in accordance with schedule on approved Submittal Register, and to prevent delays in the work, delays to government, or delays to separate contractors.

c. Advise contracting officer of variation, as required by paragraph entitled "Variations."

d. Correct and resubmit submittal as directed by approving authority.

When resubmitting disapproved transmittals or transmittals noted for resubmittal, the contractor shall provide copy of that previously submitted transmittal including all reviewer comments for use by approving authority. Direct specific attention in writing or on resubmitted submittal, to revisions not requested by approving authority on previous submissions.

e. Furnish additional copies of submittal when requested by contracting officer, to a limit of 4 copies per submittal.

f. Complete work which must be accomplished as basis of a submittal in time to allow submittal to occur as scheduled.

g. Ensure no work has begun until submittals for that work have been returned as "approved," except to the extent that a portion of work must be accomplished as basis of submittal.

1.4.6 Government Responsibilities

a. Note date on which submittal was received from contractor on each Contract Item Approval Request Form.

b. Review each submittal; and check and coordinate each submittal with requirements of work and contract documents.

SECTION 01 33 00 Page 7 of 10

c. Review submittals for conformance with project design concepts and compliance with contract documents.

d. Ensure that material is clearly legible.

e. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

f. Identify returned submittals with one of the actions defined in paragraph entitled "Actions Possible" and with markings appropriate for action indicated.

1.4.7 Actions Possible

Submittals will be returned with one of the following notations:

a. Submittals marked "approved" "approved as submitted" authorize contractor to proceed with work covered.

b. Submittals marked "approved" "see below" authorize contractor to proceed with work as noted provided contractor takes no exception to the notations.

c. Submittals marked "disapproved" indicate submittal is incomplete or does not comply with design concept or requirements of the contract documents and shall be resubmitted with appropriate changes. No work shall proceed for this item until resubmittal is approved.

1.5 FORMAT OF SUBMITTALS

1.5.1 Transmittal Form

Transmit each submittal electronically, unless otherwise noted in the submittal register and/or where electronic submission is not feasible (i.e.

samples), to the office of approving authority. The maximum file size that may be emailed is 10 MB; anything larger must be submitted hard copy or on a CD. Transmit submittals with transmittal form prescribed by contracting officer and standard for project. The transmittal form shall identify contractor, indicate date of submittal, and include information prescribed by transmittal form and required in paragraph entitled "Identifying Submittals." Process transmittal forms to record actions regarding sample panels and sample installations. Note: Submittals requiring hard copy submission shall be provided with carbon copy transmittal form provided by the government.

1.5.2 Identifying Submittals

Identify submittals, except sample panel and sample installation, with the following information on each separate component of each submittal and transmittal form. The maximum file size for electronic submittals shall be no larger than 10 MB. Identify each copy of each submittal identically, with the following:

a. Project title and location.

b. Construction contract number.

SECTION 01 33 00 Page 8 of 10

c. Section number of the specification section by which submittal is required.

d. Submittal description (SD) number of each component of submittal.

e. When a resubmission, alphabetic suffix on submittal description, for example, SD-10A, to indicate resubmission.

f. Name, address, and telephone number of subcontractor, supplier, manufacturer and any other second tier contractor associated with submittal.

g. Product identification and location in project.

1.5.3 Format for Product Data

a. Present product data submittals for each section. Include table of contents, listing page and catalog item numbers for product data.

b. Indicate, by prominent notation, each product which is being submitted; indicate specification section number and paragraph number to which it pertains.

c. Supplement product data with material prepared for project to satisfy submittal requirements for which product data does not exist. Identify this material as developed specifically for project.

1.5.4 Format for Shop Drawings

a. Shop drawings shall not be less than 8 1/2 by 11 inches nor more than 30 by 42 inches.

b. Present 8 1/2 by 11 inches sized shop drawings as part of the submittals required by section. Present larger drawings in sets.

c. Include on each drawing the drawing title, number, date, and revision numbers and dates, in addition to information required in paragraph entitled "Identifying Submittals."

d. Dimension drawings, except diagrams and schematic drawings; prepare drawings demonstrating interface with other trades to scale. Shop drawing dimensions shall be the same unit of measure as indicated on the contract drawings. Identify materials and products for work shown.

1.5.5 Format of Samples

a. Furnish samples in sizes below, unless otherwise specified or unless the manufacturer has prepackaged samples of approximately same size as specified:

(1) Sample of Equipment or Device: Full size.

(2) Sample of Materials Less Than 2 by 3 inches: Built up to 8

1/2 by 11 inches.

SECTION 01 33 00 Page 9 of 10

(3) Sample of Materials Exceeding 8 1/2 by 11 inches: Cut down to

8 1/2 by 11 inches and adequate to indicate color, texture, and material variations.

(4) Sample of Linear Devices or Materials: 10 inch length or length to be supplied, if less than 10 inches. Examples of linear devices or materials are conduit and handrails.

(5) Sample of Non-Solid Materials: Pint. Examples of non-solid materials are sand and paint.

(6) Color Selection Samples: 2 by 4 inches.

(7) Sample Panel: 4 by 4 feet.

(8) Sample Installation: 100 square feet.

b. Samples Showing Range of Variation: Where variations are unavoidable due to nature of the materials, submit sets of samples of not less than three units showing extremes and middle of range.

c. Reusable Samples: Incorporate returned samples into work only if so specified or indicated. Incorporated samples shall be in undamaged condition at time of use.

d. Recording of Sample Installation: Note and preserve the notation of area constituting sample installation but remove notation at final clean-up of project.

e. When color, texture or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.

1.5.6 Format of Administrative Submittals

a. When submittal includes a document which is to be used in project or become part of project record, other than as a submittal, do not apply contractor's approval stamp to document, but to a separate sheet accompanying document.

1.6 QUANTITY OF SUBMITTALS

1.6.1 Number of Copies of Product Data

a. When hard copy submission is required, submit four copies of submittals of product data.

1.6.2 Number of Copies of Shop Drawings

Submit shop drawings in compliance with quantity requirements specified for product data.

1.6.3 Number of Samples

a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of

SECTION 01 33 00 Page 10 of 10 samples will be retained by approving authority and one will be returned to contractor.

b. Submit one sample panel. Include components listed in technical section or as directed.

c. Submit one sample installation, where directed.

d. Submit one sample of non-solid materials.

1.6.4 Number of Copies of Administrative Submittals

a. Unless otherwise specified, submit administrative submittals compliance with quantity requirements specified for product data.

Not used.

SECTION 01 35 29 Page 1 of 6

SECTION 01 35 29

SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS

This project consists of an offshore workplace with hazardous conditions.

Close attention must be paid to risk management and workplace safety.

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI A10.32 (2012) Personal Fall Protection Used in

Construction and Demolition Operations

ANSI A10.34 (2001; R 2012) Protection of the Public On or

Adjacent to Construction Sites

ANSI Z359.1 (2016) Safety Requirements for Personal Fall

Arrest Systems, Subsystems and Components

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.22 (2016) Articulating Boom Cranes

ASME B30.3 (2016) Construction Tower Cranes

ASME B30.5 (2011) Mobile and Locomotive Cranes

ASME B30.8 (2015) Floating Cranes and Floating Derricks

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-Required Confined Spaces

29 CFR 1919 Gear Certification

29 CFR 1926 Safety and Health Regulations for

Construction

29 CFR 1926.500 Fall Protection

CORPS OF ENGINEERS (COE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements and Published Changes and Errata

SECTION 01 35 29 Page 2 of 6

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2018) Standard for Portable Fire Extinguishers

NFPA 241 (2013) Safeguarding Construction, Alteration, and Demolition Operations

NFPA 51B (2014) Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2017) National Electrical Code

NFPA 70E (2018) Electrical Safety in the Workplace

Submit the following in accordance with Section 01 33 00, "Submittal Procedures."

Accident Prevention Plan (APP)

Activity Hazard Analysis (AHA)

Reports

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."

Certificate of Compliance

1.3 QUALITY ASSURANCE

1.3.1 Meetings

The Safety Officer shall attend the pre-construction conference.

1.3.1.1 Weekly Safety Meetings

Hold weekly at the project site. Attach minutes showing contract title, signatures of attendees and a list of topics discussed to the QC Contractor Quality Control daily report.

1.3.1.2 Work Phase Meetings

The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.

SECTION 01 35 29 Page 3 of 6

1.3.1.3 New Employee Indoctrination

New employees will be informed of specific site hazards before they begin work. Documentation of this orientation shall be kept on file at the project site.

1.3.2 Certifications

1.3.2.1 Accident Prevention Plan (APP)

Submit the APP at least 15 calendar days prior to start of work at the job site, following Appendix A of EM-385-1-1. Make the APP site specific.

Submit the AHA for review at least 15 calendar days prior to the start of each phase. Format subsequent AHA as amendments to the APP. In accordance with contract quality control requirements each AHA will be reviewed during an on-site preparatory inspection.

1.4 ACCIDENT PREVENTION PLAN (APP)

Prepare the APP in accordance with EM-385-1-1 Table 1-1. Include the associated AHA and other specific plans, programs and procedures detailed in Paragraphs 01.A.09 and 01.A.10 of EM-385-1-1, some of which are listed below.

1.4.1 Contents of the Accident Prevention Plan

a. Name and safety related qualifications of safety officer (including training and any certifications).

b. Qualifications of competent and of qualified persons.

c. Identity of the individual who will complete exposure data (hours worked); accident investigations, reports and logs; and immediate notification of accidents to include subcontractors.

d. Emergency Response Plan. Conform to EM-385-1-1, paragraph 01.E and include a map denoting the route to the nearest emergency care facility with emergency phone numbers. Contractor may be required to demonstrate emergency response.

e. Critical Lift Plan. Weight handling critical lift plans shall be prepared and signed in accordance with EM-385-1-1, paragraph 16.c.18.

f. Fall Protection and Prevention (FP&P) Plan. The plan shall be site specific and address all fall hazards in the work place. It shall address how to protect and prevent workers from falling to lower levels when they are exposed to fall hazards above 6 feet. A qualified person shall prepare the plan. The plan shall include fall protection and prevention systems, equipment and methods employed, responsibilities, rescue and escape equipment and operations, training requirements, and monitoring methods. FP&P Plan shall be revised once every six months for lengthy projects, to reflect any new changes during the course of construction, due to changes of personnel, equipment, systems or work habits.

SECTION 01 35 29 Page 4 of 6

g. Silica Exposure Reduction. The plan shall include specific procedures to prevent employee silica inhalation exposures.

h. Training Records and Requirements. List of mandatory training and certifications which are applicable to this project (e.g. explosive actuated tools, confined space entry, fall protection, crane operation, vehicle operator, forklift operators, personal protective equipment); list of requirements for periodic retraining/certification; outline requirements for supervisory and employee safety meetings.

i. Severe Weather Plan. Procedures of ceasing on-site operations during lightning or upon reaching maximum allowed wind velocities.

j. Emergency Lighting and Power Systems Plan (e.g. periodic testing of batteries for emergency lighting.)

1.5 ACTIVITY HAZARD ANALYSIS (AHA)

Prepare for each phase of the work. As a minimum, define activity being performed, sequence of work, specific hazards anticipated, control measures to eliminate or reduce each hazard to acceptable levels, training requirements for all involved, and the competent person in charge of that phase of work. For work with fall hazards, including fall hazards associated with scaffold erection and removal, identify the appropriate fall arrest systems. For work with materials handling equipment, address safeguarding measures related to materials handling equipment. For work requiring excavations, include excavation safeguarding requirements. The appropriate AHA shall be reviewed and attendance documented by the Contractor at the preparatory, initial, and follow-up phases of quality control inspection.

3.1 CONSTRUCTION

Comply with EM-385-1-1, NFPA 241, the accident prevention plan, the activity hazard analysis and other related submittals and activity fire and safety regulations.

3.1.1 Hazardous Material Exclusions

Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited.

Exceptions to the use of any of the above excluded materials may be considered by Contracting Officer upon written request by Contractor.

3.1.2 Unforeseen Hazardous Material

The design should have identified materials such as PCB, lead paint, and friable and nonfriable asbestos. If additional material, not indicated, SECTION 01 35 29 Page 5 of 6 which may be hazardous to human health upon disturbance during construction operations is encountered, stop that portion of work and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous. If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification pursuant to "FAR 52.243-4, Changes" and "FAR 52.236-2, Differing Site Conditions."

3.2 PERSONNEL PROTECTION

3.2.1 Hazardous Noise

Provide hazardous noise signs, and hearing protection, wherever equipment and work procedures produce sound-pressure levels greater than 85 dBA steady state or 140 dBA impulse, regardless of the duration of the exposure.

3.2.2 Fall Protection

Enforce use of the fall protection device designated for each specific work activity in the FP&P plan and/or AHA all times when an employee is on a surface 6 feet or more above lower levels. Personal fall arrest systems are required when working from an articulating or extendible boom, scissor lifts, swing stages, or suspended platform. Fall protection must comply with ANSI A10.32.

3.3 SCAFFOLDING

Employees shall be provided with a safe means of access to the work area on the scaffold. Climbing of any scaffold braces or supports not specifically designed for access is prohibited. Stair towers or ladders built into scaffold systems in accordance with EM 385-1-1 Appendix J are required for work platforms greater than 20 feet in height. Contractor shall ensure that employees that are qualified perform scaffold erection. Do not use scaffold without the capability of supporting at least four times the maximum intended load or without appropriate fall protection as delineated in the accepted fall protection plan. Minimum platform size shall be based on the platform not being greater in height than three times the dimension of the smallest width dimension for rolling scaffold. Some Baker type scaffolding has been found not to meet these requirements. Stationary scaffolds must be attached to structural building components to safeguard against tipping forward or backward. Special care shall be given to ensure scaffold systems are not overloaded. Outrigger brackets used to extend scaffold platforms on self-supported scaffold systems for the storage of material is prohibited. The first tie-in shall be at the height equal to 4 times the width of the smallest dimension of the scaffold base.

3.4 ELECTRICAL

3.4.1 Portable Extension Cords

Portable extension cords shall be sized in accordance with manufacturer ratings for the tool to be powered.

SECTION 01 35 29 Page 6 of 6

3.5 CRYSTALLINE SILICA

Grinding, abrasive blasting, and foundry operations of construction materials containing crystalline silica,…