AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE PAGE OF PAGES
1 3
2. AMENDMENT/MODIFICATION NO.
3. DATE
21 MAY 2018
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE
7. ADMINISTERED BY (If other than Item 6) CODE
Contracting Officer USCG Civil Engineering Unit 475 Kilvert St. Suite 100 Warwick, RI 02886
Same as block #6
8. NAME AND ADDRESS OF CONTRACTOR (NO., STREET, COUNTY, STATE AND ZIP CODE)
THIS AMENDMENT MUST BE
ACKNOWLEDGED WITH YOUR BID
9A. AMENDMENT OF SOLICITATION NO.
70Z0G118BPFA02200
9B. DATED (SEE ITEM 11)
04/26/2018
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
THE BID OPENING DATE REMAINS 29 MAY 2018 AT 2:00 P.M.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted or
(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE REFERENCED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET
FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (SPECIFY TYPE OF MODIFICATION AND AUTHORITY)
E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
1. The solicitation referenced in Block #9A is hereby amended as follows:
a. Pre-bid inquiries received and responses thereto are provided as shown on page 2.
b. Department of Labor General Decision Number CT180024 modification 5 dated 05/18/2018 (CT24) is hereby incorporated as attached and hereby supersedes all previously incorporated wages.
2. The bid opening date remains 29 May 2018 at 2 p.m. EST as a result of this amendment.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full 15A. NAME AND TITLE OF SIGNER (Type or Print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
TERESA LAMPHERE
15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B UNITED STATES OF AMERICA
BY
16C. DATE SIGNED
05/21/2018
NSN 7540-01-152-8070 STANDARD FORM 30 (Rev. 10-83)
SOLICITATION #70Z0G118BPFA02200
AMENDMENT 0001
21 MAY 2018
PRE-BID INQUIRIES RECEIVED AND RESPONSES THERETO ARE PROVIDED AS FOLLOWS:
Question #1: Please confirm if taxes should be carried in proposals?
Answer #1: Notice to Bidders #8 on the face page of the solicitation states “Bidders shall include all APPLICABLE federal, state and local taxes in their bid price. A tax exempt certificate will not be provided. It is the responsibility of the bidder to determine if any state or local tax exemptions are applicable.”
In addition, FAR 52.229-3 Federal, State, and Local Taxes (FEB 2013) is incorporated by reference on page 11. The full text of the clause can be found at https://www.acquisition.gov and reads as follows:
(a) As used in this clause—
“After-imposed Federal tax” means any new or increased Federal excise tax or duty, or tax that was exempted or excluded on the contract date but whose exemption was later revoked or reduced during the contract period, on the transactions or property covered by this contract that the Contractor is required to pay or bear as the result of legislative, judicial, or administrative action taking effect after the contract date. It does not include social security tax or other employment taxes.
“After-relieved Federal tax” means any amount of Federal excise tax or duty, except social security or other employment taxes, that would otherwise have been payable on the transactions or property covered by this contract, but which the Contractor is not required to pay or bear, or for which the Contractor obtains a refund or drawback, as the result of legislative, judicial, or administrative action taking effect after the contract date.
“All applicable Federal, State, and local taxes and duties” means all taxes and duties, in effect on the contract date, that the taxing authority is imposing and collecting on the transactions or property covered by this contract.
“Contract date” means the date set for bid opening or, if this is a negotiated contract or a modification, the effective date of this contract or modification.
“Local taxes” includes taxes imposed by a possession or territory of the United States, Puerto Rico, or the Northern Mariana Islands, if the contract is performed wholly or partly in any of those areas.
(b)(1) The contract price includes all applicable Federal, State, and local taxes and duties, except as provided in subparagraph (b)(2)(i) of this clause.
(2) Taxes imposed under 26 U.S.C. 5000C may not be—
(i) Included in the contract price; nor
(ii) Reimbursed.
(c) The contract price shall be increased by the amount of any after-imposed Federal tax, provided the Contractor warrants in writing that no amount for such newly imposed Federal excise tax or duty or rate increase was included in the contract price, as a contingency reserve or otherwise.
(d) The contract price shall be decreased by the amount of any after-relieved Federal tax.
(e) The contract price shall be decreased by the amount of any Federal excise tax or duty, except social security or other employment taxes, that the Contractor is required to pay or bear, or does not obtain a refund of, through the Contractor’s fault, negligence, or failure to follow instructions of the Contracting Officer.
(f) No adjustment shall be made in the contract price under this clause unless the amount of the adjustment exceeds $250.
(g) The Contractor shall promptly notify the Contracting Officer of all matters relating to any Federal excise tax or duty that reasonably may be expected to result in either an increase or decrease in the contract price and shall take appropriate action as the Contracting Officer directs.
(h) The Government shall, without liability, furnish evidence appropriate to establish exemption from any Federal, State, or local tax when the Contractor requests such evidence and a reasonable basis exists to sustain the exemption.
SOLICITATION #70Z0G118BPFA02200
AMENDMENT 0001
21 MAY 2018
Question #2: Please confirm if any state, local, or Federal permits will be required on this project?
Answer #2: Contractor is required to provide state, local, or federal permits if necessary to conduct proposed scope of work.
Permits where necessary will be determined by the contractor.
Question #3. Please confirm if there is any known hazardous materials?
Answer #3: Yes. It has been outlined in the contract and scope of the work
Question #4: Will the tunnel be demoed, or will contractor need to climb through and attempt to clean the tunnel?
Answer #4: Lead abatement for the entire exhaust system is required. Means and methods will be determined by the contractor. The scope of work is clearly identified on drawings and specifications. The Contractor is requested to review complete design drawings, specifications and other contract documents.
| 2018-05-21T13:14:53-0400 | |
| LAMPHERE.TERESA.LOUISE.1155638873 |