CGC CALHOUN Fire Detection System Inspect Test_SOW.docx

DOCX document 54 KB Posted

Attached to
CALHOUN FIRE SYSTEM INSPECTION AND TEST
Solicitation number
70Z085Q250001087
Issued by

About this file

This is a Statement of Work for inspection and testing of the Fire Detection System aboard the USCGC CALHOUN (WMSL 759) in North Charleston, SC. The work requires a Consilium Marine US authorized technical representative to perform comprehensive testing of the vessel's fire alarm system, including control panels, detectors, manual call points, and bells according to NFPA 72 standards. The period of performance is February 10-28, 2025.

The related solicitation (70Z085Q250001087) from the US Coast Guard Surface Force Logistics Center is a total small business set-aside under NAICS 336611 with a size standard of 1,250 employees. The contract will be awarded as firm-fixed-price using simplified acquisition procedures. Work must be completed within a 2-day period between December 17, 2024 and March 18, 2025. Quotes are due by December 22, 2024 at 0800 Pacific Time and should be submitted to the specified contracting officers via email.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Materials. The Contractor must obtain all of the materials required to complete this job with the exception of the Government-furnished Property shown in Paragraph 1.2 of Work Item 1.

3.3. Period of Performance. The period of performance for this work starts on 10 February 2025 and ends on 28 February 2025.

3.4. Location. The Contractor must perform the work while the USCGC CALHOUN (WMSL 759) alongside Pier Juliet located at 1400 Pierside St, Building 190, North Charleston, SC, 29405

43610_BEC_1124_418

Fire Detection System, Inspect and Test

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to inspect and test Fire Detection System.

TABLE 1 – FIRE ALARM SYSTEM

MODEL NO./ MANUFACTURER
DESCRIPTION
COAST GUARD DRAWING / TECH PUB
F400-101-101103A / Consilium Marine US
Fire Alarm System complete with Main Control and Display Panel, Control/Repeater Panel, Dual Optical Heat and Smoke Detectors, Optical Smoke Detectors, Analog Heat Detectors, Manual Call Points, Pull Stations, Bells, Field Server Profibus DP Gateway Complete in enclosure.
*750-WMSL-436-011 / 9576 / 9556 & 9701

*Applicable sheet are referenced as NF6-AF ONLY.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Add Coast Guard Drawing 750-WMSL-100-088, Rev A, General Arrangements NSC 9 & Follow (AS9100001) Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans Coast Guard Drawing 750-WMSL-100-088, Rev A, General Arrangements NSC 9 & Follow (AS9100001) Coast Guard Drawing 750-WMSL-436-013, Rev C, Fire Detection Sys Cable Running Sheets (ASC436010) Coast Guard Drawing 750-WMSL-436-014, Rev -, Fire Detection and Control System Schematic (ASC436028) Coast Guard Drawing 750-WMSL-436-510, Rev -, Fire Detection System Deck Plan Coast Guard Publications Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Are we incorporating the 2024 specifications now? @SES Comment by Martin, William L IV CPO USCG SFLC (USA): 2022 Std Specs is posted on SFLC website, have not seen 2024 Comment by Martin, William L IV CPO USCG SFLC (USA): Regardless this WI spec is out of date Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Coast Guard Technical Publication (TP) 9919, SWBS 436, Feb 2022, Fire and Smoke Detection System Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Take out all Tech pubs that don’t correspond to Calhoun Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Add the tech pub for Hull 759 Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Can you add the tech pub for Hull 759 Comment by Clark, Benjamin E CIV USCG SFLC (USA): This is the most relevant tech pub for this ship, even though 759 is not listed in the applicability. Please verify the installed system during the shipcheck.

Other References National Fire Protection Association (NFPA) 72, 2022 Edition, National Fire Alarm and Signaling Code

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

3.3 System inspect and test.

3.1.2 Tech Rep. The Contractor must provide the services of an OEM authorized/licensed Technical Representative, who is familiar with marine fire and smoke detection and alarm systems to accomplish the following tasks on-site: Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Change to “The Contractor must provide the services of an OEM authorized/licensed Tech Rep…”

· Provide manufacturer's proprietary information, software, and tools pertinent to the equipment/system.

· Assist with proper repair methods, and ensure compliance with manufacturer's procedures and standards during disassembly, inspection, repair, modification, calibration, and reassembly of the equipment/system.

3.1.2.1 The Tech Rep must be qualified and experienced in accordance with the requirements of NFPA 72, paragraph 10.5.3, and provide evidence of qualification according to the means of qualification in NFPA 72 paragraph 10.5.3.4. Licensure by the state licensing board (from the state in which the work is performed) as a contractor specialized in fire protection systems is an acceptable form of evidence for the purposes of this WI. Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Add: 3.1.2.1 Ensure that the Tech Rep is an OEM authorized/licensed representative of Consilium-Marine Fire Detection System. Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Why all of this additional verbiage? Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Comment by Clark, Benjamin E CIV USCG SFLC (USA): OEM authorized/licensed is not needed here. @Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA) Read NFPA 72, and you will understand why the verbiage is there.

3.1.2.2 Submit the Tech Rep’s name and résumé to the COR NLT 07 days following the award.

3.1.2.3 Point of Contact:

Mr. Magnus Edelius Service Manager Mobile: +1 954 257 1358 Consilium Marine US e-Mail: Magnus.Edelius@consiliumsafety.com

OR

· Herbert S. Hiller

· A division of The Hiller Companies, Inc.

· 401 Commerce Point

· Harahan, LA 70123

· (504) 736-0008

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

1. Sheathing

1. Bulkhead insulation

1. Piping

1. Electrical Cables

3.1.5 Electrical work. The Contractor must accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041, except where manufacturer-specific guidance is provided for the fire detection system. Utilize the existing wire ways for new cable runs as much as possible.

3.1.5.1 Fire detection system continuity and insulation resistance testing must, as a matter of priority, be tested in accordance with the manufacturer’s instructions as provided in the system tech manual.

3.1.6. Fire Readiness. While the Fire Alarm system is down, the Contractor must provide personnel in that space who can communicate with Ship’s Force in the event of a fire. The Contractor must submit a Fire Plan addressing the duration of the fire alarm system losses and their methods of communication with the crew to communicate in an emergency, and any other applicable issues from paragraphs 3.1.2 and 3.1.3 of SFLC Std Spec 5550. Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Do we need to do a fire prevention conference then? Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Recommend removing this entire paragraph. The job takes 3 days, the contractor does a third of the ship each day and brings the detectors that are tested back online same day. The FDS will not be down for the entire POP Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Do you agree? Comment by Clark, Benjamin E CIV USCG SFLC (USA): The level of communication and monitoring in those spaces while the testing is going on is up to the ship’s crew and QA to agree with the contractor, but there should be some written plan in place.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.1.7 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.2 Required Testing Tools. The Contractor must provide and be capable of operating recommended test equipment in accordance with the OEM Service and Maintenance Manual. These tools include, but are not limited to: Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Why are we listing tools? Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Recommend removing this entire paragraph Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Do you agree? Comment by Clark, Benjamin E CIV USCG SFLC (USA): Disagree, will not remove. Contractor must provide tools used specifically for testing this system to ensure detectors are tested properly.

Testfire: multi-stimulus detector tester.

Salwico Solo 330: smoke detector tester.

Salwico Solo 461: heat detector tester.

Salwico VD T-1: heat detector tester.

Salwico IR Test Lamp: flame detector tester.

Salwico UV Test Lamp: UV flame detector tester.

W8066: UV test lamp.

3.2.1 Password protection. Fire alarm panel is password protected for software. Prior to start work on this item (i.e. Maximum 5 days prior to Tech Rep arrival) Tech Rep must request Password through Herbert S. Hiller a division of The Hiller Companies and Coast Guard Inspector.

3.2.2 Test Plan. The Contractor must, in consultation with the Tech Rep, develop a test plan to clearly define the scope of the fire detection system testing, and submit to the COR for approval. The test plan must include, at a minimum, the annually required tests of NFPA 72 table 14.4.3.2, as applicable to the system defined by OEM tech manuals and the system drawings. Submit a CFR.

TABLE 1 – NFPA-72 ANNUAL FIRE ALARM TEST

DESCRIPTION

Test and Visual Inspection of Panel Functionality

Test Panel Battery Charger

Battery Discharge Test

Test and Visual Inspection Horns, Strobes, Chimes and Bells

Test and Visual Inspection of Smoke Detectors

Test and Visual Inspection of Heat Detectors

Replace Sealed Lead Acid Battery every Five Years (Verify Expiration Date on the Battery and Submit a CFR)

Smoke and Heat Detectors: Replacement is recommended every 10 Years

3.3 Fire detection system inspect and test. The Contractor must perform inspection and test of the Fire Alarm System in the presence of a Coast Guard inspector or Coast Guard personnel. Testing must be performed in accordance with NFPA-72 (i.e. National Fire Alarm and Signaling Code) and OEM tech manuals. The Contractor must perform 100 % test on all field devices (i.e., ALARM-INITIATING DEVICES AND CIRCUITS) listed in the system drawing. Submit CIR.

3.3.1 The Contractor must supply and install sealed lead acid batteries (i.e. Battery 12 Volt, 2.3 Ah, Quantity 2) mounted inside Fire Alarm Control Panel in accordance with the OEM tech manual. Submit a CFR. Comment by Martin, William L IV CPO USCG SFLC (USA): The above table notes “every 5 years”, will these batteries not be replaced if they are within expiration period or will be if they will expired before next servicing? Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Recommend we remove “every Five Years (Verify Expiration Date on the Battery and Submit a CFR)” Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): The CFR in 3.3.1 should provide the cutter with the battery install date and recommended replacement date Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Comment by Clark, Benjamin E CIV USCG SFLC (USA): Verification of expiration is good, doesn’t need to be changed every time.

NOTE

The Contractor must perform only applicable test on the Fire Alarm System. Some of the test identified on the attached Data Sheet may not be required on installed Fire Alarm System on the Cutter.

3.3.2 The Contractor must perform applicable tests on the Consilium Fire Detection System with assistance from Tech Rep in accordance with the OEM tech manual. These tests must include fault detection tests, control unit and repeater panel tests, cable tests, firmware verification and the testing of horns, strobes, chimes and bells for proper operation. Submit a CFR. Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Take out Central, it will only confuse the KTR Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Replace Central with Consilium

3.3.2.1 Perform applicable test as identified in NFPA Standard 72 Table 14.4.3.2, record on a suitable checklist created for the purpose of this test. Submit a CFR.

3.3.2.2 With assistance from ship’s crew, verify signals from Fire Alarm Control Panel to CGMCS display console.

3.3.2.3 The Contractor must verify operation of the repeater panel on the bridge (pilothouse).

3.3.2.4 Certify that Fire Alarm System on the Cutter is operating properly by signing the end of the test document with identification, company, and licensing/credentialing information. This step must only be completed once repairs are completed to the satisfaction of the Coast Guard inspector.

3.4 Repair system discrepancies according to CIR. The Contractor must make repairs and conduct calibration as needed to restore operability to malfunctioning components within the system. Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): This will make it difficult for the contractor to bid accurately. They won’t know the extent of any repairs until the condition is found. A contract vehicle needs to be put in place to create the ability for growth. Such as “Submit CFR” which will allow us to create a CR and issue a modification change Comment by Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA): Recommend changing to Submit CFR for any calibration or repairs of equipment needed Comment by Hyacinth, Melissa N ENS USCG SFLC (USA): @Clark, Benjamin E CIV USCG SFLC (USA) Comment by Clark, Benjamin E CIV USCG SFLC (USA): @Rodriguez-Lupica, Jacob J LTJG USCG SFLC (USA) There’s already a CIR after the testing is complete, the CR can come from that. Numbering of the WI will be changed to make this more clear.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5 Operational test – post repairs. After completion of work, the Contractor must witness an operational test (by Coast Guard personnel) of all items or shipboard devices that have been disturbed, used, repaired, altered, or installed, to prove that they are in satisfactory operating condition. Submit a CFR.

3.6 Touch-up preservation. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable. Abide by all touch-up requirements outlined in SFLC Std Spec 0000, Appendix A (Requirements for Preservation of Ship Structures).

4. NOTES

This section is not applicable to this work item.