Attachment 2 - USCGC MARIA BRAY DS FY27 - SPECIFICATION.pdf

PDF 2 MB Posted

Attached to
USCGC MARIA BRAY (WLM 562) DOCKSIDE REPAIR FY27
Solicitation number
70Z08527QIBCT0003
Issued by
Not on record

About this file

This is a Specification for Dockside Repairs for the USCGC MARIA BRAY (WLM-175), a 175-foot Coast Guard buoy tender, covering fiscal year 2027 maintenance and repair work. The specification outlines 31 work items addressing fire prevention, tank cleaning and inspection, hydraulic systems maintenance, ventilation duct cleaning, potable water filter installation, and various machinery inspections and services. Work includes cleaning and inspecting hydraulic oil tanks, lube oil tanks, cargo hatches, main diesel engine exhaust piping, ship service diesel generator exhaust piping, and multiple ventilation systems (engine room, galley, laundry, and other spaces). Critical inspection items include the hydraulic cargo hatch, compressed air receivers, hydraulic chain stoppers, hydraulic crossdeck winches, hydraulic inhaul winch, mechanical chain stoppers, warping capstan, single point davit, buoy crane, and bilge preservation—all requiring Critical Inspection reports within the first 25 percent of the contract period.

The solicitation is a fixed firm price definitive contract designated as a 100 percent Small Business Set-Aside, with place of performance at the vessel's homeport in Atlantic Beach, Florida. The deadline for requesting drawings is December 1, 2026 at 8 AM PST; site visit coordination must occur by December 2, 2026; and all questions must be submitted by December 3, 2026. Government-furnished property includes water filter assemblies, hydraulic components, winch assemblies, valves, pumps, and various repair kits for cargo hatches, chain stoppers, davits, and cranes. All work must comply with Surface Forces Logistics Center Standard Specifications (SFLC Std Specs) for general requirements, welding, auxiliary machine systems, ventilation system cleaning, fire prevention and response, ship structure preservation, and temporary hull accesses. Contractors must appoint a Fire Prevention Responsible Party, develop a fire prevention plan, maintain environmental protection measures, and comply with applicable federal, state, and local regulations regarding hazardous materials and waste disposal.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC MARIA BRAY (WLM 562)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2027

Developed By: Antonio E. Rivera

(REV-0, 23 July 2026)

USCGC MARIA BRAY (WLM-175) DOCKSIDE AVAILABILITY FY2027

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - TENDER .......................................................................................................... xii General Requirements WORK ITEM 1: Fire Prevention Requirements - Dockside WORK ITEM 2: Tanks, Hydraulic Oil Stowage and Service, Clean and Inspect WORK ITEM 3: Tanks, Lube Oil, Clean and Inspect WORK ITEM 4: Hydraulically Operated Cargo Hatch, Inspect and Service WORK ITEM 5: Main Diesel Engine, MDE, Exhaust Piping, Commercial Clean WORK ITEM 6: Ship Service Diesel Generator, SSDG, Exhaust Piping, Commercial Clean WORK ITEM 7: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 8: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 9: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 10: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 11: Point of Use Potable Water Filters, Install WORK ITEM 12: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift ... 50 WORK ITEM 13: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test WORK ITEM 14: Hydraulic Chain Stoppers, Inspect and Service WORK ITEM 15: Hydraulic Crossdeck Winches, Inspect And Service WORK ITEM 16: Hydraulic Inhaul Winch, Inspect And Service WORK ITEM 17: Mechanical Chain Stoppers, Inspect and Service WORK ITEM 18: Hull Fittings (Mooring and Towing), Inspect and Test WORK ITEM 19: Warping Capstan (Aft), Inspect and Service WORK ITEM 20: Single Point Davit, Disassemble and Inspect WORK ITEM 21: Buoy Crane, Inspect And Service WORK ITEM 22: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 23: Sewage Holding Tanks, Clean and Inspect WORK ITEM 24: Grey Water Piping, Clean and Flush WORK ITEM 25: Sewage Piping, Clean and Flush WORK ITEM 26: Sewage Service Piping COV, Install WORK ITEM 27: Fixed CO2 FF Bottles, Inspect and Hydrostatic Test WORK ITEM 28: Bilges, Partial Preserve WORK ITEM 29: Deck Covering (Electrical Matting), Renew WORK ITEM 30: 01 Level Deck, Repair WORK ITEM 31: Crews Head Bulkhead Repairs iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 175-WLM-130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover Coast Guard Drawing 175-WLM-259-001, Rev A, Combustion Exhaust Diagram Coast Guard Drawing 175-WLM-259-005, Rev C, Combustion Exhaust A&D, Hull Block 970 Coast Guard Drawing 175-WLM-506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram Coast Guard Drawing 175-WLM-512-001, Rev E, HVAC Diagram Coast Guard Drawing 175-WLM-528-001, Rev F, Plumbing and Interior Deck Drains Diagram Coast Guard Drawing 175-WLM-549-001, Rev G, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM-551-001, Rev J, Compressed Air System Diagram Coast Guard Drawing 175-WLM-555-001, Rev G, CO2 System Diagram Coast Guard Drawing 175-WLM-573-001, Rev U, Buoy Deck Arrangement Coast Guard Drawing 175-WLM-573-008, Rev C, ATON Tie Downs Coast Guard Drawing 175-WLM-573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175-WLM-573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic

Roller Assembly Coast Guard Drawing 175-WLM-582-001, Rev D, Mooring and Towing, A & D Coast Guard Drawing 175-WLM-593-001, Rev G, Sewage & Waste Water System Diagram Coast Guard Drawing 175-WLM-593-001, Rev H, Sewage and Waste Water System Diagram Coast Guard Drawing 175-WLM-593-7, Rev D, Sewage & Waste Water System A & D, Hull Block 970 Coast Guard Drawing 175-WLM-593-009, Rev E, Independent Tanks, Sewage Holding Tank Coast Guard Drawing 175-WLM-601-001, Rev T, General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175-WLM-601-003, Rev N, Booklet of General Plans Coast Guard Drawing 175-WLM-633-001, Rev D, Cathodic Protection Coast Guard Drawing 175-WLM-635-001, Rev F, Hull Thermal and Acoustic Insulation Schedule Coast Guard Drawing 175-WLM-801-015, Rev C, Scantlings, Decks & Platforms Coast Guard Drawing 175-WLM 801-017, Rev B, Scantlings, Superstructure Coast Guard Drawing 175-WLM-801-019, Rev C, Shell Expansion Coast Guard Drawing 175-WLM-920-001, Rev K, Hull Block 920 Panels Coast Guard Drawing 175-WLM-970-001, Rev K, Hull Block 970 Panels Coast Guard Drawing 175-WLM-970-004, Rev G, H. B. 970 Transverse Frames & Bulkheads v (Rev-0)

Coast Guard Drawing FL-2605-029, Rev M, Chain Stopper System – Rising Sheave Assembly Coast Guard Drawing FL-2605-031, Rev D, Mechanical Chain Stopper, 1-7/8 Inch Buoy Chain Coast Guard Drawing FL-2605-034, Rev D, Mechanical Chain Stopper Repair Kit: 1-7/8", 1-5/8”, 1-1/4" Coast Guard Drawing FL-533-001, Rev B, Placard Potable Water Flush Coast Guard Drawing FL-533-002, Rev A, Point of Use Water Filter Install Coast Guard Drawing FL-7101-573, Rev L, Buoy Chain Winch Assy Model CW1

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, January 2014, Coatings and Color

Manual Coast Guard Technical Publication (TP) 3498, Buoy Chain Winch Coast Guard Technical Publication (TP) 3610A, Hydraulic Cargo Hatch – Model D-WK-787 Coast Guard Technical Publication (TP) 3611, Manufacturer’s Instruction Book – SWBS Group(s) 202 Coast Guard Technical Publication (TP) 3627, Manufacturer's Instruction Book – SWBS Group(s) 541-

Coast Guard Technical Publication (TP) 3630, Buoy Crane Model SB230-42 Operation, Maintenance, and Repair Instructions Coast Guard Technical Publication (TP) 3631, Manufacturer’s Instruction Book-SWBS Group(s) 573-581 Coast Guard Technical Publication (TP) 3632, Manufacturer's Instruction Book – SWBS Group(s) 582-

Coast Guard Technical Publication (TP) 3632, Manufacturer's Instruction Book-SWBS Group(s) 582-583 Coast Guard Technical Publication (TP) 3749, Mechanical Chain Stopper Coast Guard Technical Publication (TP) 3939, Manufacturer’s Instruction Book – Rising Sheave Chain

Stopper Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and

Allied Processes.

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC

Electrical Motors Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary

Machine Systems Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2022, Clean

Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2022, Install Interior

Deck Covering Systems Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2022, Temporary

Hull Accesses vi (Rev-0)

OTHER REFERENCES

American Society of Mechanical Engineers (ASME) B16.34, 2025, Valves-Flanged, Threaded, and

Welding End American Society for Testing and Materials (ASTM) International D1330-04, 2022, Standard

Specification for Rubber Sheet Gaskets American Society for Testing and Materials (ASTM) International D3951-18, 2023, Standard Practice for

Commercial Packaging American Society for Testing and Materials (ASTM) International D4417-21, 2021, Standard Test

Methods for Field Measurement of Surface Profile of Blast Cleaned Steel American Society for Testing and Materials (ASTM) International D5363-16, 2024, Standard

Specification for Anaerobic Single Component Adhesives (AN) American Society for Testing and Materials (ASTM) International F683-25, 2025, Standard Practice for

Selection and Application of Thermal Insulation for Piping and Machinery American Society for Testing and Materials (ASTM) International F1508-96, 2021, Standard

Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment Code of Federal Regulations (CFR) Title 33, Part 154, Facilities Transferring Oil or Hazardous Material in Bulk Code of Federal Regulations (CFR) Title 40, Protection of Environment Commercial Item Description (CID) A-A-59316, 2016, Abrasive Materials; for Blasting International Standard Organization (ISO) 21940-21:2022, Mechanical Vibration - Rotor balancing - Part

21: Description and Evaluation of Balancing Machines Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61-2019 Edition, Pressure Testing of Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67-2022 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72-2012a Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80-2019 Edition, Bronze Gate, Globe, Angle and Check Valves Military Specification MIL-S-45180D, Notice 2, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant NAVSEA Drawing 167-7379842, Rev A, Procedure & Welding Sequence for Non-Ballistic, Watertight

& Airtight Quick Acting or Individually Dogged Personnel Doors NAVSEA Drawing 804-1385781, Pipe Hangers for Surface Ships (Superseding NAVSEA Dwg. 810-

1385781) NAVSEA Drawing 804-5773931, Rev-A, Insulation for Compartments, Acoustic and Thermal –

Installation Details NAVSEA Drawing 804-5959214, Rev-, Piping Insulation - Installation Details Performance Specification MIL PRF-16173E, w/Interim Amendment 1, September 2006, Corrosion

Prevention Compound, Solvent Cutback, Cold-Application Performance Specification MIL-PRF-24176C, October 2004, Cement, Epoxy, Metal Repair and Hull

Smoothing (Metric) vii (Rev-0)

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) AMSC6183B, June 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) SSPC-PA2, April 2022, Procedure for Determining Conformance to Dry Coating Thickness Requirements

The Society for Protective Coatings (SSPC) Surface Preparation Standard No. 11 (SSPC-SP 11), 2013, Power-Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10-NACE No. 2-2024, Near-White Blast Cleaning viii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

11 N Water Filter Assembly PN: DWS160-L (3M) NSN:

(ACN) 4330-01-F20-5959

6 ea. 160.00

11 N Water Filter Element PN: 56134-44 (3M) NSN:

4330-01-F20-5960

6 ea. 180.00

14 N Repair Kit Assembly NSN: 2040-01-496-9418 2 ea. 1968.67 14 N Rod Seal Repair Kit

(FL-2605-29 PC#37)

NSN: 2040-01-496-9422 2 ea. 3030.07

14 N Repair Kit, Cable Chain (Includes Pads)

(FL-2605-29 PC#36)

NSN: 3020-01-538-0684 16 ea. 257.99

14 N **Cylinder Assembly Actuating, Linear

NSN: 3040-01-496-9424 4 ea. 1969.24

15 N Hydraulic Brake Assembly

NSN: 2530-01-550-7474 4 ea. 460.69

15 Y Winch Gear Box Assembly

NSN: 3010-01-F16-4570 PN:

SK9052AZ-SAEB-31.4-H1

(Nord Gear Corp) or YMD- 7914 (Appleton Marine Inc)

4 ea. 7060.09

15 N Hydraulic Motor NSN: 4320-01-470-8467 4 ea. 478.90 15 N Wire Rope NSN: 4010-01-620-9604 4 ea. 577.95 15 N Counter Balance Valve NSN: 4820-01-324-4269 8 ea. 107.50 15 N Shuttle Valve NSN: 4820-01-317-2748 8 ea. 34.78 15 N Needle Valve NSN: 4820-01-329-0051 4 ea. 38.00 15 N **Directional Control

Valve NSN: 4810-01-543-3252 4 ea. 4959.95

15 N Electrical Connector, Hirshmann

NSN: 5935-01-640-6747 8 ea. 32.00

16 N Roller bearing Unit NSN: 3130-01-504-4363 2 ea. 4012.00 16 N Grease seal NSN: 5330-01-462-5544 4 ea. 79.25 16 N Level wind pivot bushing NSN: 3120-01-621-2293 1 ea. 1139.00

16 N Level wind thrust bearing

NSN: 3120-01-621-2300 2 ea. 483.30

16 N Rexroth DCV NSN: 4810-01-507-0037 1 ea. 208.29 16 N Rexroth Sandwich

Flow Control NSN: 4810-01-505-9289 1 ea. 250.00

16 N Sun Sandwich Relief Valves

NSN: 4820-01-439-2451 2 ea. 900.00

16 Y Level Wind Hydraulic Cylinder

NSN: 3040-01-441-3721 1 ea. 7423.00

16 N 3:1 Pilot Ratio, Vented NSN: 4820-01-563-5841 1 ea. 98.70 ix (Rev-0)

Counterbalance Valve Assembly

16 N Fully Adjustable Needle Valve

NSN: 4820-01-416-0579 1 ea. 48.75

16 N Wire Rope Assembly NSN: 4010-01-646-6972 1 ea. 500.00 16 Y **Hydraulic Motor NSN: 4320-01-445-2248 1 ea. 23998.00 16 N **Pump, Hydraulic

Ram, Hand Driven NSN: 4320-01-286-4065 1 ea. 419.77

16 N **Cylinder Pin NSN: 5315-01-515-9847 1 ea. 500.00 16 N **Cylinder Pin NSN: 5315-01-515-9912 1 ea. 520.00 17 N Hardware Kit, Pins NSN: 2030-01-485-7209 2 ea. 528.47 17 N Hardware Kit, Mechanical NSN: 2030-01-485-7215 2 ea. 538.91

20 N Swing Brake Seal Kit NSN: 2030-01-351-2820 2 ea. 138.80 20 N Swing Brake Disc &

Bearing Kit NSN: 2030-01-349-9486 2 ea. 937.70

20 N Wire Rope Assembly, Single Leg

NSN: 4010-01-602-8365 1 ea. 234.00

20 Y **Winch Assembly NSN: 2030-01-505-1581 1 ea. 17454.50 21 N Wire Rope, Crane Aux

Fall NSN: 3950-01-617-1692 1 ea. 522.54

21 N Wire Rope, Crane Main Fall

NSN: 3950-01-617-1700 1 ea. 1275.49

21 N Luff Cylinder Seal kit NSN: 5330-01-433-6307 1 ea. 357.99 21 N Holding Valve NSN: 4810-01-353-0586 2 ea. 67.33 21 N Shuttle Valve NSN: 4820-01-317-2748 2 ea. 24.32 21 N Needle Valve NSN: 4820-01-329-0051 1 ea. 38.11 21 Y Valve Assembly, Manifold NSN: 4810-01-506-7738 1 ea. 19892.60

21 N Bushing, Heel NSN: 5365-01-F12-2920 4 ea. 67.00 21 N **Hydraulic swivel seal kit NSN: 4730-01-566-2864 1 ea. 1298.00

21 N **Pin, Heel NSN: 5315-01-500-6931 2 ea. 2463.45 21 N **Hand pump w/

Stainless Steel Option, P18

NSN: 4320-01-517-1444 1 ea. 1724.57

21 N **Plate, Backing, Brake (Item 231 and

234)

NSN: 3040-00-119-9848 2 ea. 1500.40

21 N **Plate, Brake (Item 232)

NSN: 3040-01-068-7647 1 ea. 377.00

21 N **Driver Plate (Item 233)

NSN: 3040-01-F14-3994 1 ea. 138.34

21 N Packing Assortment, Preformed

NSN: 5330-01-191-2622 1 ea. 10.94

21 N Disc-Friction, Brake NSN: 3040-01-051-3606 1 ea. 15.74 21 N **Spring, Helical, Comp NSN: 5360-01-268-0044 12 ea. 12.12

21 N PD12C Seal kit NSN: 2590-01-398-5741 1 ea. 147.76 x (Rev-0)

21 N **Disc, Steel NSN: 2530-01-066-9585 1 ea. 38.38 21 N **Master brake rebuild kit

NSN: 5330-01-F16-4572 PN:

98-015-3001 (Eskridge Inc)

3 ea. 556.39

21 N Aux Hoist Hook (Overhaul Ball)

NSN: 4030-01-572-3945 1 ea. 2800.00

21 N Block, Tackle NSN: 3940-01-566-2929 1 ea. 5229.07 21 N **Relief Valve

Cartridge

NSN: 4820-01-481-7116 PN:

RPIC-LAN (Sun Hydraulics

Inc)

1 ea. 117.35

21 N **Control Stand Selector Valve

Assembly

NSN: 4730-01-507-3516 1 ea. 1247.94

21 N **Bushing, Luff Cylinder

NSN: 3120-01-363-7629 4 ea. 89.53

21 N **Pin, Luff Cylinder NSN: 5315-01-F12-2922 PN:

MMD-2232

2 ea. 2432.30

21 Y **Valve Assembly, Directional Control

NSN: 4810-01-F17-5027 1 ea. 14806.50

*Government-loaned property, which must be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xi (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item Title

4 Hydraulically Operated Cargo Hatch, Inspect and Service

12 Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift

14 Hydraulic Chain Stoppers, Inspect and Service

15 Hydraulic Crossdeck Winches, Inspect And Service

16 Hydraulic Inhaul Winch, Inspect And Service

17 Mechanical Chain Stoppers, Inspect and Service

19 Warping Capstan (Aft), Inspect and Service

20 Single Point Davit, Disassemble and Inspect

21 Buoy Crane, Inspect And Service

28 Bilges, Partial Preserve xii (Rev-0)

PRINCIPAL CHARACTERISTICS - TENDER

175' WLM, BUOY TENDER

PHYSICAL

Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW

HULL

Hull material Steel

MACHINERY

Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM

Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800

RPM

Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM

TANK CAPACITIES

Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal

1 (Rev-0)

00000_0226_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3D, January 2014, Coatings and Color

Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General

Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and

Allied Processes Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures

OTHER REFERENCES

American Society for Testing and Materials (ASTM) International D4417-21, 2021, Standard Test

Methods for Field Measurement of Surface Profile of Blast Cleaned Steel Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for

Shipyard Employment Code of Federal Regulations (CFR) Title 33, Part 154, Facilities Transferring Oil or Hazardous Material in Bulk Code of Federal Regulations (CFR) Title 40, Protection of Environment

2 (Rev-0)

The Society for Protective Coatings (SSPC) SSPC-PA2, April 2022, Procedure for Determining Conformance to Dry Coating Thickness Requirements

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.

3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the 29 CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.

3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan as requested in the Fire Protection and Response work item, with the Contractor’s bid.

NOTE

NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.

Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

• Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

• Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3 (Rev-0)

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

• ASTM D4417-21, Method B: One profile measurement is the average (mean) of 10 individual readings.

• ASTM D4417-21, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:

• SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

• SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is small quantity cond.

exempt.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

4 (Rev-0)

• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

5 (Rev-0)

3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.

3.7.1 SFLC Standard Specification 5550: Replace paragraph 3.11.3 to state, “Material supporting imminent work shall be brought on the cutter and stored where the work is being performed. Material that appreciably contributes to fire load shall be removed at the end of each work shift when personnel are not present. Trash, debris, and packaging materials shall be promptly removed from the vessel at the end of each work shift and not allowed to accumulate.” Advance the paragraph numbering of the Fire Prevention and Safety Inspection form to 3.11.4.

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK

ITEM #

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

7 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL # WORK

ITEM # WORK ITEM TITLE

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER

COAT, BARRIER COAT, TOP

COAT, ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFAC

E

AMBIEN

T

ΔT

| DP -

SURFACE |

8 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/AMPP INSPECTOR SIGNATURE CERT. # DATE /

TIME

9 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/AMPP No. 2

SSPC-SP WJ-2/AMPP WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT

QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK

ITEM #

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL # WORK ITEM

# WORK ITEM TITLE

COATING MFG PRODUCT NAME BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5 AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-0)

4.2 Tank and Void Assessment form.

13 (Rev-0)

14 (Rev-0)

55500_ACC_0323_IBCT

WORK ITEM 1: Fire Prevention Requirements - Dockside

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to minimize shipboard fire risk and to clarify the Contractors’ role in fire prevention and response.

NOTE

This work item is not separately priced. Factor fire prevention and response costs into bid of affected work items.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), 2022, Fire

Prevention and Response

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 Fire Plan. The Contractor must develop and implement a written fire plan in accordance SFLC Std Spec 5550. The Contractors Fire Plan must address Fire Protection and Response specifics as required in this Work Item.

3.1.1 The availability’s specific Fire Plan must always address the following:

• material condition and fire protection boundary obstruction mitigations

• inoperable fittings log

15 (Rev-0)

• fire alarms

• firefighting equipment disposition

3.1.2 The Fire Plan must also address the following:

• fire protection system status

• communication links

• temporary services

• power disconnects

• fire prevention and safety inspections

3.2 Fire Prevention Responsible Party. The Contractor must appoint a Fire Prevention Responsible Party (FPRP) who acts as the Contractor’s Responsible Person for fire prevention concerns during the entire availability.

3.3 Fire Prevention and Response Conference. The Contractor must participate in the Fire Prevention and Response Conference as required in Std Spec 5550, paragraph 3.12. The participants must address the contents of SFLC Std Spec 5550, paragraph 3.12.1, as applicable.

3.4 Fire Responsibility Familiarization Tour and Initial Inspection. The Contractor must participate in the Fire Responsibility Familiarization Tour and Initial Inspection as required in Std Spec 5550, paragraphs

3.12.2 through 3.12.4.

3.5 Material Condition and Fire Protection Boundary Obstruction Mitigation Requirements. The Contractor must conform to all material condition and fire protection boundary obstruction mitigation requirements detailed in SFLC Std Spec 5550, paragraph 3.2.

3.6 Inoperable Fittings Log Requirements. The Contractor must conform to all inoperable fittings log requirements detailed in SFLC Std Spec 5550, paragraph 3.3.

3.7 Fire Prevention Service Particulars. The Contractor must conform to the below listed fire prevention service requirements, in accordance with SFLC Std Spec 5550.

TABLE 1 – FIRE PREVENTION SERVICE SELECTION

*SUB-PARAGRAPH TITLE Y/N

3.4 Fire prevention system status N

3.4.1 Temporary firefighting system proposal N

3.4.2 Emergent firefighting system inoperability approval and notification N

3.4.3 “Disabled equipment” signage for disabled initial responder equipment N

3.4.4 Firefighting system inoperability allowance for removed hazards N

3.4.5 Maintain sprinkling zone operability N

3.4.6 including all subparagraphs Hazard mitigation for maintenance of fixed extinguishing systems N

3.4.7 Procedure implementation for enabling/disabling fire suppression systems N

3.4.8 Portable water pumping requirement for vessels w/o installed capability N

3.4.9 Limitations on operation of major machinery while firefighting systems are offline N

16 (Rev-0)

*SUB-PARAGRAPH TITLE Y/N

3.4.10 Liquid fuel pumping requirement for operational permanent or temporary firefighting systems N

3.4.11 Mechanical AFFF equipment must be available to initial responders in compartments with risk of flammable/combustible liquid spillage N

3.4.12 including all subparagraphs

Portable fire extinguisher requirements N

3.4.13 Hose and reel protection N

3.4.14 including all subparagraphs

Drydock firefighting requirements

3.4.15 Fire protection system status in Fire Plan N

3.5 Fire response related communication links in Fire Plan N

3.6 Fire response related temporary services in Fire Plan N

3.6.1 Minimize downtime of fixed extinguishing systems N

3.6.2 through 3.6.10 Firemain and related equipment requirements N

3.6.11 Permanent lighting requirements Y

3.6.12 including all subparagraphs

Temporary lighting requirements Y

3.6.13 Electrical power, firefighting water, and lighting source location and testing identified in Fire Plan N

3.7 including all subparagraphs

Fire alarm requirements Y

3.8 Shore power manual disconnect locations identified in Fire Plan N

3.9 Other power manual disconnect locations identified in the Fire Plan N

3.10 including subparagraph

Vessel firefighting equipment placement and disposition info in Fire Plan Y

3.11 Fire prevention and safety inspections in Fire Plan Y

3.11.1 Initial and daily inspection requirements Y

3.11.2 Additional details in fire inspection reports N

*Each sub-paragraph number relates directly to the identical sub-paragraph number in SFLC Std Spec 5550.

3.5 Extended fire prevention services. If the performance period of the contract is extended by the KO, the contractor must continue to provide all fire prevention services as specified herein for the extension period.

4. NOTES

This section is not applicable to this work item.

17 (Rev-0)

12300_TSI_0325_IBCT

REC_12300(AccessibleVoidsWeather)_IBCT_175 WLM (ALL) (1213)

WORK ITEM 2: Tanks, Hydraulic Oil Stowage and Service, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TABLE 1 - TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION

(GALLONS)

Crane HPU 3-15-0-E 500 0

Port Z-Drive 3-79-1-E 92 10

Stbd Z-Drive 3-79-2-E 92 10

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 175-WLM-601-003, Rev N, Booklet Of General Plans

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems

18 (Rev-0)

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) AMSC6183B, June 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

3. REQUIREMENTS

3.1 General. The Contractor must accomplish the following for all designated tanks in paragraph 1.1 (Intent). Use Coast Guard Drawing 175-WLM-601-003 for guidance.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

• TLI

3.3 Tank contents. The Contractor must remove and dispose of up to a total of 100 gallons of hydraulic oil.

NOTE

Vessel may come in with less tank fluid contents than specified above.

3.4 Plug log. The Contractor must keep a written record of all plugs put in any tank vents. A separate list must be kept for each tank being entered.

3.4.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.4.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

19 (Rev-0)

3.5 Cleaning requirements. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as sediment or sludge, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths.

3.6 Tank content and waste disposal. The Contractor must dispose of residual tank contents and all cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.7 Inspection. The Contractor must visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Complete the “Tank and Void Assessment Form” (found in the Work Item titled “General Requirements”) and submit via CFR. Electronic PDF version of this form will be furnished by the COR upon request. Include the following, as applicable:

• Tank structural condition.

•…

This is the start of the file's text. The full file is on GovTribe.