This document is a Statement of Work (SOW) for biennial maintenance of a Dual Point Davit on the USCGC BERTHOLF (WMSL 750), a US Coast Guard vessel. The maintenance work is to be performed at the pier on Spencer Road in Alameda, CA from February 17 to April 9, 2025. The contractor must perform comprehensive maintenance tasks including operational inspections, hydraulic system analysis, disassembly and inspection of power sheave assemblies, wire rope renewal, non-destructive evaluation (NDE), lubrication, weight testing, and motor insulation testing on the Allied Systems Dual Point Davit (Models DDP11000CTS & SP2200).
Key requirements include providing a qualified technical representative from Allied Systems Company familiar with the davit system, maintaining hydraulic system cleanliness, and conducting multiple test scenarios including no-load operational, static load, dynamic load, and rated load tests. The work involves renewing specific components like wire ropes and hook assemblies, performing touch-up preservation, and supporting both dockside and sea trials to ensure the davit's operational capability. The contractor must submit various Contractor Inspection Reports (CIRs) and Contractor Furnished Reports (CFRs) throughout the maintenance process, with a working load limit of 11,000 pounds and specific testing load requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 2.pdf | ||
| ATTACHMENT 1-SOW Rv2.pdf | ||
| RFQ BERTHOLF DPD BIENNIAL MAINTENANCE Rv1.pdf | ||
| Amendment 1.pdf | ||
| ATTACHMENT 1-SOW Rv1.pdf | ||
| ATTACHMENT 2 - Schedule of Price.xlsx | XLSX spreadsheet | |
| Solicitation BERTHOLF DPD BIENNIAL MAINTENANCE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 9618, SWBS 583, Sept 2023, Boat Davit - Models DDP11000CTS &
SP2200 (S/N: 2328-753, 2329-751, 2332-750)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
International Maritime Organization (IMO) International Convention for the Safety of Life At Sea (SOLAS), 2009 as amended in 2010 and 2011
International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition
ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical Apparatus.
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI apply to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Materials. The Contractor must obtain all of the materials required to complete this job with the exception of the Government-furnished Property shown in Paragraph 1.2 of Work Item.
3.3. Period of Performance. The period of performance window for this work starts on 17 February 2025 and ends on 09 April 2025.
3.4. Location. The Contractor must perform the work while the USCGC BERTHOLF (WMSL 750) is alongside the pier on Spencer Road, Alameda, CA 94501.
58300_RTK_1223_418
Dual Point Davit, Biennial Maintenance, Perform
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform Biennial Maintenance on Dual Point Davit listed in Table 1.
TABLE 1 – DUAL POINT DAVIT NAMEPLATE DATA
description LOCATION davit total gross weight
Allied Systems Dual Point Davit with Control Console
Models: DDP11000CTS & SP2200
Weather Deck, STBD Side, Frame 47
29,000 lbs
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY
ESTIMATED
COST ($/UNIT)
Y CB-OTH Mark IV
(Coast Guard Drawing 26B-CB-IV-801-001) N/A 1 ea. N/A
Y Hook Model APR-356-CBH 2 ea. 5000.00
N
KIT, ELEMENT
REPLACEMENT
593533 1 1500
N
KIT, ELEMENT
REPLACEMENT
593532 1 500
N ELEMENT, FILTER 70196 2 900
N FILTER, BREATHER 71975 2 400
N HUB 73441 2 1300
2. REFERENCES
Coast Guard Drawings
Coast Guard Drawing 418A-WMSL-100-001, Rev B, General Arrangements
Coast Guard Drawing 418A-WMSL-801-001, Rev A, Booklet of General Plans
Coast Guard Publications
Coast Guard Technical Publication (TP) 9618, SWBS 583, Sept 2023, Boat Davit - Models DDP11000CTS &
SP2200 (S/N: 2328-753, 2329-751, 2332-750)
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Other References
International Maritime Organization (IMO) International Convention for the Safety of Life At Sea (SOLAS), 2009 as amended in 2010 and 2011
International Maritime Organization (IMO) International Life Saving Appliances Code (LSA), 2010 edition
ANSI/EASA Standard AR100-2020, Recommended Practice for the Repair of Rotating Electrical Apparatus.
3. REQUIREMENTS
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.2 Biannual maintenance inspection and repair task particulars (Task #1 and #2)
3.2.1 Hook certification.
3.1.2 Tech Rep. The Contractor must provide the services of a Qualified Technical Representative who is familiar with the Dual Point Davit (i.e. Allied System Co. Model No. DDP11000CTS) to accomplish the following on site:
Advise on manufacturer's proprietary system information.
Ensure compliance with manufacturer's procedures and standards during system disassembly, inspection, repair, reassembly, and testing as applicable.
3.1.2.1 Ensure the Tech Rep has experience with the system/equipment stated above and demonstrated on their résumé.
3.1.2.2 Submit the name and résumé of the Tech Rep to the COR at the Arrival Conference.
3.1.2.3 Point of contact:
Heath Munger
Heath.munger@alliedsystems.com
Allied Systems Company
(503) 825-3366
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.3.1 Protection of fine surfaces. The Contractor must protect all fine surfaces in accordance with SFLC Std. Spec 5000.
3.1.3.2 Hydraulic system contamination protection. The Contractor must maintain existing hydraulic cleanliness in accordance with SFLC Std. Spec 5000.
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Piping
Electrical Cables
Capstan
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.5 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.
3.1.6 Materials. The Contractor must furnish and install parts listed in Table 2.
TABLE 2 – LIST OF PARTS
QUANTITY PART NUMBER DESCRIPTION SOURCE OF SUPPLY
2 74130 Seal Kits Allied System Co.
214 S.W. Oregon Street, Sherwood OR 97140
1 71754 Tank Cover Gasket
2 71042 Wire Rope
3.2 Biannual maintenance inspection and repair task particulars. The Contractor with Tech Rep support must perform the tasks designated in Table 3 below and Figure 1 in accordance with SFLC Std Spec 5000 and CG Tech Pub as applicable.
TABLE 3 – Recurring Maintenance task
ADDITION REQUIREMENTS
# TASK TYPE QTY COMPONENT OR
ASSEMBLY
APPENDIX AND PARA. FROM
SFLC STD 5000
OTHER
1 Operate and Inspect
1 Dual Point Davit System 3.2.1 (Operate and Inspect) Appendix A (General Inspection
Requirements)
Submit CIR.
2 Hydraulic Lube Oil Analysis
1 Hydraulic System C2.1.3.1 Submit a CIR.
3 Service and Inspect
1 Hydraulic Winch Assembly (Constant Tension and Normal) which are powered by Main Hydraulic Pump/Motor
Assembly (ST1) and Back Up powered by Emergency (ST2), Accumulators.
3.2.2 (Service and Inspect) D2.3 (Brakes and clutches. D2.4 (Open gearing and gear reducers)
Submit CFR.
4 Disassemble and Inspect
2 Power Sheave Assembly 3.2.3 (Disassemble and Inspect) Renew the hub with CFE. If hubs are not available, clean, inspect, and reinstall hubs.
5 Renew 2 Wire Rope Assembly
(Allied System Part No. 71042)
D2.2 (Wire rope assemblies) Wire rope particulars:
Nominal diameter:
5/8 inch
Minimum Breaking Strength: 56,040 lbs.
Total length of each wire rope required:
110 ft.
End fitting type:
Fiege. Submit a
CFR.
6 Service and Inspect
1 Control Panel 3.2.2 (Service and Inspect) Verify all mechanical and electrical signals to the control panel.
Submit a CFR.
7 NDE 1 Dual Point Davit System 3.2.5 (NDE) Areas to NDE: all weld joints and boom and turret structures.
Submit a CFR.
8 Groom and Lubricate
1 Dual Point Davit System 3.2.6 (Groom and Lubricate)
9 Weight Test 1 Dual Point Davit System B2.7.2 (Dual Point Davits)
B2.7.2.1 No-load Operational Test
B2.7.2.2 Static Load Test
B2.7.2.3 Winch/Brake/Modified static load Test
B2.7.2.4 Dynamic Load Test
B2.7.2.5 Rated Load test
Test weight particulars:
Working Load Limit (11,000 lb.).
"Modified static / brake" test load:
16,500 pounds (150% of WLL)
“Modified Dynamic Test Load: 12,650 pounds (115% of
WLL)
10 Electric Motors
1 Normal RIHB Boat Davit and Emergency RIHB Davit HPU
Motors
Perform Insulation Resistance Test in accordance with
ANSI/EASA AR
100-2020.and Para
6.5.4.3 of TP 9618.
Submit a CFR.
11 Fabricate and Install
1 Label plate B2.9 (Label Plates)
12 Partially Preserve
1 Dual Point Davit Assembly (including pedestal, foundation, and all previously/normally painted components or surfaces)
3.2.4 (Partial Preservation)
3.2.1 Hook certification. The Contractor with Tech Rep support must inspect the hooks and verify their certification. Submit a CIR. Hooks (i.e. P/N: Model APR-356-CBH) must be renewed at every 48 months with GFP.
Renew hooks if certification is expired.
3.2.1.1 Mandatory Turn-in Item (MTI) removal. If required to be renewed, the Contractor must remove the existing MTI hooks and turn over to the COR.
3.3 Special requirements for various components. If a Change Request has been authorized for additional work on any of the components listed in Table 4 below, the Contractor must perform work in accordance with the corresponding Appendix or paragraph of SFLC Std Spec 5000.
TABLE 4 - SPECIAL REQUIREMENTS
Component Appendix & Paragraph in sflc std spec 5000
Fluids C2.1
Hose assemblies C2.2
Piping and tubing C2.3
Valves and manifolds C2.4
Gages C2.5
Gas charged accumulators C2.6
Heat exchangers and fluid coolers C2.7
Systems C2.8
Fastener assemblies D2.1
Wire rope assemblies D2.2
Brakes and clutches D2.3
Open gearing and gear reducers D2.4
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.4 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.
3.4.1 The Contractor with Tech Rep support must perform a dockside test, consisting of launching the GFP boat to test Constant Tension Function, Wire Rope Tension, CT Select Button, Control function, CT Engage, Brake Release etc. Submit a CFR.
3.5 Touch-up preservation. The Contractor must prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310. Abide by all touch-up requirements outlined in SFLC Std Spec 6310.
NOTE
Government will provide 72 Hours of advance notice to the Contractor for sea trial support by the Tech Rep.
3.6 Sea trial. The Contractor must provide Tech Rep support to test operational capability of the Dual Point Davit with GFP in accordance with TP. Estimated time for sea trial is eight hours. Perform an at sea test launching the GFP boat to test Constant Tension Function, Wire Rope Tension, CT Select Button, Control function, CT Engage, Brake Release etc. Ensure all functions are in satisfactory operating conditions. Submit a CFR.
4. NOTES