This sources sought notice is seeking information from companies capable of providing materials, equipment, and personnel to perform dockside repairs on USCGC William Tate. The repairs include approximately 15 line items. Interested companies are invited to provide information on their capabilities, certifications as an 8(a), HUBZone, service-disabled veteran-owned, or small business, and past performance on similar projects. Statements should also affirm the submission of a proposal if a solicitation is issued. The period of performance is anticipated to be 49 calendar days from July 1st to August 18th, 2024. The NAICS code is 336611 and size standard is 1,300 employees. Responses are due by January 31st, 2024 and should be emailed to the points of contact listed.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC WILLIAM TATE (WLM 560)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2024
Developed By: Mark A Schmalstieg
(Rev-0, 8 December 2023)
USCGC WILLIAM TATE (WLM-175) DOCKSIDE AVAILABILITY FY2024
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ............................................................................................. xi Principal Characteristics - TENDER .......................................................................................................... xii General Requirements WORK ITEM 1: Hydraulically Operated Cargo Hatch, Inspect and Service WORK ITEM 2: Point of Use Potable Water Filters, Install WORK ITEM 3: Hydraulic Chain Stoppers, Inspect And Service WORK ITEM 4: Hydraulic Crossdeck Winches, Inspect And Service WORK ITEM 5: Hydraulic Inhaul Winch, Inspect And Service WORK ITEM 6: Mechanical Chain Stoppers, Inspect and Service WORK ITEM 7: Hull Fittings (Mooring and Towing), Inspect and Test WORK ITEM 8: Warping Capstan (Aft), Inspect and Service WORK ITEM 9: Single Point Davit, Disassemble and Inspect WORK ITEM 10: Buoy Crane, Inspect And Service WORK ITEM 11: Buoy Crane Main Winch, Replace WORK ITEM 12: Flame Detectors, Replace WORK ITEM 13: Lube Oil Fill Valve, Renew WORK ITEM 14: Directional Control Valve, Upgrade WORK ITEM 15: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover
Coast Guard Drawing 175 WLM 262-001 Rev J, Lube Oil System Diagram
Coast Guard Drawing 175 WLM 533-001, Rev H, Potable Water System Diagram
Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements
Coast Guard Drawing 175 WLM 549-1, Rev E, Onboard Lubrication Requirements
Coast Guard Drawing 175 WLM 556-001, Rev L, Hydraulic System Diagram
Coast Guard Drawing 175 WLM 573-001, Rev T, Buoy Deck Arrangement
Coast Guard Drawing 175 WLM 573-001, Rev T; Buoy Deck Arrangement
Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper
Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly
Coast Guard Drawing 175 WLM 573-8, Rev D, ATON Tie Downs
Coast Guard Drawing 175 WLM 582-001, Rev D, Mooring and Towing, A & D
Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles
Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels
Coast Guard Drawing 175-WLM 436-1, Rev H, Fire & Smoke Detection System Block.
Coast Guard Drawing 175-WLM 549-001, Rev E, Onboard Lubrication Requirements
Coast Guard Drawing 175-WLM 549-1, Rev C, Onboard Lubrication Requirements
Coast Guard Drawing 175-WLM 573-001, Rev R, Buoy Deck Arrangement
Coast Guard Drawing 175-WLM 635-1, Rev F, Hull Thermal & Acoustic Insulation Schedule.
Coast Guard Drawing 175-WLM-320-001, Rev AP, Electrical One-Line Diagram.
Coast Guard Drawing 175-WLM-437-007, Rev R, Buoy Dk Control Sys Block, ISO & Electric Wiring Diagram.
Coast Guard Drawing 175-WLM-573-013, Rev -, Replacement DCV Amplifier Card Wiring Diagram.
Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Chain
Coast Guard Drawing FL 2605-034, Rev D, Mechanical Chain Stopper Repair Kit: 1-7/8", 1-5/8" & 1- 1/4"
Coast Guard Drawing FL 533-001, Rev B, Placard Potable Water Flush
Coast Guard Drawing FL 533-002, Rev -, Point of Use Water Filter Install v (Rev-0)
Coast Guard Drawing FL 7101-573, Rev L, Buoy Chain Winch Assy Model CW1
Coast Guard Fleet Drawing FL-2605-029, Rev L, Chain Stopper System – Rising Sheave Assembly
Isometric, and Elementary Wiring Diagram (Circuit SM)
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) 9077.1 (series), Equipment Lockout/Tags Plus Instruction
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Maintenance Procedure Card (MPC) A-A-14033, Dec 2017, Buoy Chain Winch Wire Rope Weight.
Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3498, SWBS 573, Aug 2019, Buoy Chain Winch.
Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch - Model No. D-WK-787
Coast Guard Technical Publication (TP) 3621, SWBS 436, June 2020, Fire Detection System –
Coast Guard Technical Publication (TP) 3630, 07-JAN-97, Manufacturers Instruction Book-SWBS Group(s) 573
Coast Guard Technical Publication (TP) 3630, SWBS 573, Section A (573A), Jun 2015, Manufacturer's Instruction Book-SWBS Group 573, Buoy Crane
Coast Guard Technical Publication (TP) 3631, Mar 2007, Manufacturer’s Instruction Book-SWBS Group(s) 573-581, Section B, Cross Deck Winch – Appleton Marine Model BMD-463
Coast Guard Technical Publication (TP) 3632, March 2014, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT
Coast Guard Technical Publication (TP) 3632, Section 582-A, March 2014, Manufacturer's Instruction Book-SWBS Groups 582-583, Aft Capstan
Coast Guard Technical Publication (TP) 3749, 26-APR-05, 1-7/8 Inch ATON Mechanical Chain Stopper
Coast Guard Technical Publication (TP) 3939, SWBS 573-A, Apr 2007, Rising Sheave Chain Stopper
Fire Prevention and Response
Operation, Installation and Maintenance Manual, July 2020
Requirements for Preservation of Ship Structures.
Requirements.
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2022, General
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, 2022, Welding and Allied Processes.
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3042, 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation.
Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6310, 2022, Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements vi (Rev-0)
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2022, Overhaul AC Electrical Motors
Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2022, Shipboard Electrical Cable Test
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2022, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation.
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022 Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
AMD-2767 Winch Assembly Manual MAY 2020 Appendix W CGTP-3630
American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and Welding End
ASTM International (ASTM) D5363, 2008, Standard Specification for Anaerobic Single Component Adhesives (AN)
ASTM International (ASTM) F992, 2011, Standard Specification for Valve Label Plates
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service
MIL-G-24716, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound vii (Rev-0)
MIL-PRF-24176 , Oct 2004, Cement, Epoxy, Metal Repair And Hull Smoothing (Metric)
MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant
MIL-STD-2003-3, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Penetrations)
MIL-STD-2003-4, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Cableways)
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning viii (Rev-0)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
2 N Water Filter Assembly PN: DWS160-L (3M) NSN:
(ACN) 44330-01-F20-5959
6 ea. 160.00
2 N Water Filter Element PN: 56134-44 (3M) 6 ea. 180.00 2 N Placard - Potable Water
Flush N/A 8 ea. 50.00
3 N Repair Kit Assembly NSN: 2040-01-496-9418 2 ea. 1,968.67 3 N Rod Seal Repair Kit
(FL-2605-29 PC#37)
NSN: 2040-01-496-9422 2 ea. 3,030.07
3 N Repair Kit, Cable Chain (Includes Pads)
(FL-2605-29 PC#36)
NSN: 3020-01-538-0684 16 ea. 257.99
3 N **Cylinder Assembly Actuating, Linear
NSN: 3040-01-496-9424 4 ea. 1,969.24
4 N Hydraulic Brake Assembly
NSN: 2530-01-550-7474 4 ea. 460.69
4 N Winch Gear Box Assembly
NSN: 3010-01-F16-4570 PN:
SK9052AZ-SAEB-31.4-H1
(Nord Gear Corp) or YMD- 7914 (Appleton Marine Inc)
4 ea. 1,000.00
4 N Hydraulic Motor NSN: 4320-01-470-8467 4 ea. 478.90 4 N Wire Rope NSN: 4010-01-620-9604 4 ea. 577.95 4 N Counter Balance Valve NSN: 4820-01-324-4269 8 ea. 107.50 4 N Shuttle Valve NSN: 4820-01-317-2748 8 ea. 34.78 4 N Needle Valve NSN: 4820-01-329-0051 4 ea. 38.00 4 N **Directional Control
Valve NSN: 4810-01-543-3252 4 ea. 4,959.95
4 N Electrical Connector, Hirshmann
NSN: 5935-01-640-6747 8 ea. 32.00
5 N Roller bearing Unit NSN: 3130-01-504-4363 2 ea. 4,012.00 5 N Grease seal NSN: 5330-01-462-5544 1 ea. 79.25 5 N Level wind pivot bushing NSN: 3120-01-621-2293 1 ea. 1,139.00
5 N Level wind thrust bearing
NSN: 3120-01-621-2300 2 ea. 483.30
5 N Rexroth DCV NSN: 4810-01-507-0037 1 ea. 208.29 5 N Rexroth Sandwich
Flow Control NSN: 4810-01-505-9289 1 ea. 250.00
5 N Sun Sandwich Relief Valves
NSN: 4820-01-439-2451 2 ea. 900.00
5 Y **Level Wind Hydraulic Cylinder
NSN: 3040-01-441-3721 1 ea. 7,423.00 ix (Rev-0)
5 N 3:1 Pilot Ratio, Vented Counterbalance Valve
Assembly
NSN: 4820-01-563-5841 1 ea 98.70
5 N Fully Adjustable Needle Valve
NSN: 4820-01-416-0579 1 ea 48.75
5 N Wire Rope Assembly NSN: 4010-01-646-6972 1 ea. 500.00 5 Y **Hydraulic Motor NSN: 4320-01-445-2248 1 ea 23,998 5 N **Pump, Hydraulic
Ram, Hand Driven NSN: 4320-01-286-4065 1 ea. 419.77
5 N **Cylinder Pin NSN: 5315-01-515-9847 1 ea 500.00 5 N **Cylinder Pin NSN: 5315-01-515-9912 1 ea 520.00 6 N Hardware Kit, Pins NSN: 2030-01-485-7209 2 ea. 528.47 6 N Hardware Kit, Mechanical NSN: 2030-01-485-7215 2 ea. 538.91
9 N Swing Brake Seal Kit NSN: 2030-01-351-2820 2 ea 138.80 9 N Swing Brake Disc &
Bearing Kit NSN: 2030-01-349-9486 2 ea 937.70
9 N Wire Rope Assembly, Single Leg
NSN: 4010-01-602-8365 1 ea. 234.00
9 Y **Winch Assembly NSN: 2030-01-505-1581 1 ea. 17,454.50 10 N Wire Rope, Crane Aux
Fall NSN: 3950-01-617-1692 1 ea 522.54
10 N Wire Rope, Crane Main Fall
NSN: 3950-01-617-1700 1 ea 1,275.49
10 N Luff Cylinder Seal kit NSN: 5330-01-433-6307 1 ea 357.99 10 N Holding Valve NSN: 4810-01-353-0586 2 ea 67.33 10 N Shuttle Valve NSN: 4820-01-317-2748 2 ea 24.32 10 N Needle Valve NSN: 4820-01-329-0051 1 ea 38.11 10 Y Valve Assembly, Manifold NSN: 4810-01-506-7738 1 ea. 19,892.60
10 N Bushing, Heel NSN: 5365-01-F12-2920 4 ea 67.00 10 N Hydraulic swivel seal kit NSN: 4730-01-566-2864 1 ea 1,298.00
10 N **Pin, Heel NSN: 5315-01-500-6931 2 ea 2,463.45 10 N **Hand pump w/
Stainless Steel Option, P18
NSN: 4320-01-517-1444 1 ea 1,724.57
10 N **Plate, Backing, Brake (Item 231 and
234)
NSN: 3040-00-119-9848 2 ea 1,500.40
10 N **Plate, Brake (Item 232)
NSN: 3040-01-068-7647 1 ea. 377.00
10 N **Driver Plate (Item 233)
NSN: 3040-01-F14-3994 1 ea. 138.34
10 N Packing Assortment, Preformed
NSN: 5330-01-191-2622 1 ea. 10.94
10 N Disc-Friction, Brake NSN: 3040-01-051-3606 1 ea. 15.74 10 N **Spring, Helical, Comp NSN: 5360-01-268-0044 12 ea 12.12 x (Rev-0)
10 N PD12C Seal kit NSN: 2590-01-398-5741 1 ea 147.76 10 N **Disc, Steel NSN: 2530-01-066-9585 1 ea 38.38 10 N **Master brake rebuild kit
NSN: 5330-01-F16-4572 PN:
98-015-3001 (Eskridge Inc)
3 ea 556.39
10 N Aux Hoist Hook (Overhaul Ball)
NSN: 4030-01-572-3945 1 ea 2,800.00
10 Y Block, Tackle NSN: 3940-01-566-2929 1 ea 3,806.87 10 N **Relief Valve
Cartridge
NSN: 4820-01-481-7116 PN:
RPIC-LAN (Sun Hydraulics
Inc)
1 ea 117.35
10 N **Control Stand Selector Valve
Assembly
NSN: 4730-01-507-3516 1 ea 1,247.94
10 N **Bushing, Luff Cylinder
NSN: 3120-01-363-7629 4 ea 89.53
10 N **Pin, Luff Cylinder NSN: 5315-01-F12-2922 PN:
MMD-2232
2 ea 2,432.30
11 Y Main Winch NSN: 3950-01-671-2105 PN:
AMD-2767
1 57,250.00
12 Y Semiconductor Device, Photo
NSN: 5961-01-599-4004 PN:
20/20MI-11SF
9 ea. 1,489.00
12 N Bracket, Mounting NSN: 5340-01-599-4015 PN:
20/20-005 (ST.ST.316L)
9 ea. 45.55
13 N Gate Valve 2inch Commercial Purchase 1 1,200.00 14 N Directional Control
Valve (DCV)
NSN: 4810-01-F19-5719 PN:
4WRE10E75-2X/G24K4/V
1 ea. 1,748.00
14 N Amplifier Card NSN: 4810-01-F19-5719 PN:
PN: 4WRE10E75-
2X/G24K4/V
1 ea. 1,552.00
14 N Mating Connector, 4P
G4WIF PG7 SW
NSN: 5935-01-F19-5722 PN:
R900023126
1 ea. 46.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter xi (Rev-0)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
Work Item
Title
1 Hydraulically Operated Cargo Hatch, Inspect and Service
3 Hydraulic Chain Stoppers, Inspect And Service
4 Hydraulic Crossdeck Winches, Inspect And Service
5 Hydraulic Inhaul Winch, Inspect And Service
6 Mechanical Chain Stoppers, Inspect and Service
8 Warping Capstan (Aft), Inspect and Service
9 Single Point Davit, Disassemble and Inspect
10 Buoy Crane, Inspect And Service
11 Buoy Crane Main Winch, Replace
14 Directional Control Valve, Upgrade xii (Rev-0)
PRINCIPAL CHARACTERISTICS - TENDER
175' WLM, BUOY TENDER
PHYSICAL
Length overall 174' 8" Length between perpendiculars 155' 1" Depth 14' 8" Maximum beam 36' 0" Designed draft 8' 0" Mast height (above 8' waterline) 58' 8" Frame spacing 20" Full load displacement 855.15 Long Tons SW Light load displacement 719.78 Long Tons SW Minimum op condition displ 852.19 Long Tons SW
HULL
Hull material Steel
MACHINERY
Main propulsion Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM
Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM
Reduction gears Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio Shaft seal John Crane Type ND Shaft bearings Five pedestal mounted, Cooper split roller bearings Number of propellers 2 Number of blades 4 Diameter 57.1" Rudders None; Z-drive Ship's service generators Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800
RPM
Emergency diesel generator One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM
TANK CAPACITIES
Diesel oil capacity (100%) 16,385 gal Fresh water capacity (100%) 7,339 gal Lubricating oil (100%) 86 gal
1 (Rev-0)
00000_0623_FLT
REC_00000_FLT_Commercial Project @ CG Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), Latest Version, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), Latest Version, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5550 (SFLC Std Spec 5550), Latest Version, Fire Prevention and Response
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), Latest Version, Requirements for Preservation of Ship Structures
OTHER REFERENCES
Code of Federal Regulations (CFR) Title 29, Part 1915, Occupational Safety and Health Standards for Shipyard Employment
NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure
2 (Rev-0)
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements in this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.1.1 The Contractor must conform to all requirements specified in SFLC Std Spec 5550 and in the Fire Protection and Response work item, as applicable, during the performance of this availability.
3.1.1.1 Fire Safety Plan submission. The Contractor must submit a copy of the CFR 1915, Subpart P, Fire Safety Plan with the Contractor’s bid when work will be conducted in a Contractor–owned facility. Include any MOA(s) with local firefighting facilities.
3.1.1.2 Fire Plan submission. The Contractor must submit a copy of the developed availability specific fire plan, as requested in the Fire Protection and Response work item, seven (7) days before the Arrival Conference.
NOTE
NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents.
Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3 (Rev-0)
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurement” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5-inch diameter circle defining the spot.
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.
3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.
3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.
NOTE
NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.
4 (Rev-0)
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Small Quantity Generator.
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements
5 (Rev-0) and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor must be aware of the following:
3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. The Contractor must refer to site (e.g., Base) Regulations and Instructions for details regarding local policies (e.g., crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. Approved updates to the 2022 SFLC Standard Specifications will appear here.
3.7.1 None.
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
6 (Rev-0)
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
VESSEL NAME HULL # WORK ITEM
WORK ITEM TITLE
LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME
NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME
7 (Rev-0)
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
VESSEL NAME HULL #
WORK ITEM
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
DATE
TIME
ACTIVITY (SURFACE
PREPARATION, PRIMER COAT,
BARRIER COAT, TOP COAT,
ETC…)
LOCATION (FRAME &
DECK, RELATION TO
EQUIPMENT, ETC.)
TEMPERATURE % REL.
HUMID-
ITY
DEW
PT.
SURFACE AMBIENT ΔT
| DP -
SURFACE |
8 (Rev-0)
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
VESSEL NAME HULL # WORK ITEM
LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS
PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS
DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Place Surface Profile Replica Tape Here
Reading (mils): Reading (mils): Reading (mils):
MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:
NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /
TIME
9 (Rev-0)
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
VESSEL NAME HULL # WORK ITEM
SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)
MIN MAX MEAN
SSPC-SP-10/NACE No. 2
SSPC-SP WJ-2/NACE WJ-2
SSPC-SP-3
SSPC-SP-11
SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)
ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:
RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA
RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO
SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):
Mean Reading (mils)
10 (Rev-0)
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
VESSEL NAME HULL # WORK ITEM
SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.
DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)
11 (Rev-0)
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
VESSEL NAME HULL #
WORK ITEM
COATING MFG PRODUCT NAME
BATC
H #
INDUCTI
ON TIME
COATING SYSTEM
SEQUENCE
(PRIMER/TOUCHUP/3RD
COAT, ETC.)
DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.
SPOT 1 2 3 4 5
AVERAGE
VALUE
*BASE METAL READING
(BMR)
*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
LOCATION (FRAME REFERENCE):
SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS
1 AVG. BMR DEVIATION
3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS
AVG.
APPLICATION METHOD (AIRLESS,
CONVENTIONAL SPRAY, ROLLED)
AVERAGE DFT
12 (Rev-0)
4.2 Tank and Void Assessment form.
13 (Rev-0)
14 (Rev-0)
16700_ACC_0121_IBCT
REC_16700_CrgHtchInspctSrvc_IBCT_175 WLM (ALL)(0815)
WORK ITEM 1: Hydraulically Operated Cargo Hatch, Inspect and Service
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to perform inspections and service for the hydraulically-operated cargo hatch.
1.2 Government-furnished property.
None.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover
Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements
Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles
Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels
COAST GUARD PUBLICATIONS
Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch
- Model No. D-WK-787
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2022, Auxiliary Machine Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
15 (Rev-0)
3.1 General.
3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):
3.2 (Tasks to be accomplished) – Task #1.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
Electrical and hydraulic switches.
Dogs.
Toggles.
Hydraulic cylinders.
Hydraulic lines.
Electrical cables.
Hoses.
Overhead insulation.
3.2 Tasks to be accomplished. The Contractor must perform the following tasks:
CAUTION
Do not paint gaskets or any moving parts, including dogs, nuts, wedges, spindles, yokes, packing, connecting rods and hinge pins.
CAUTION
For Task #2, failure to remove hinge interferences during hatch removal/reinstallation may result in damage to coaming and hinges. Protect hinges during hatch removal and reinstallation.
ADDITION REQUIREMENTS
# TASK TYPE QTY COMPONENT
OR ASSEMBLY
APPENDIX
AND PARA.
FROM
5000_STD
OTHER
1 Operate and Inspect
1 Cargo hatch assembly
3.2.1 (Operate and inspect)
1. Check hatch for proper operation of all indicators, switches, dogging un-dogging
16 (Rev-0)
OR ASSEMBLY
APPENDIX
AND PARA.
FROM
5000_STD
OTHER
and overall operation.
2. Check entire coaming and drains for signs or debris or clogging of drains.
3. Conduct a visual inspection of the hatch. Check all linkages.
4. Inspect both inner and outer knife-edges for proper height and evenness of wear.
5. Inspect entire hatch structure, for signs of paint wear and corrosion.
6. Inspect gasket channels for corrosion.
7. Take 10 UT measurements of gasket channel surfaces, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec 0740, Appendix C.
8. Inspect hydraulic hose condition.
9. Check condition of dogs and wedges.
Submit A CIR.
10. Inspect hinge pins to insure roundness, wear or damage.
2 Remove and reinstall
1 Cargo hatch assembly
N/A Remove hatch, to facilitate inspections and service tasks, then reinstall hatch, at reassembly.
Coaming in way of hatch hinges may be an interference to hatch removal. Inspect hinge clearance and inspect hinge pins for roundness and signs of wear. Before unshipping the hatch, determine if modifications are required, then modify/remove/repair as necessary and return to original configuration when reinstalling the hatch.
Failure to remove interferences may result in damage to coaming and hinges. Protect hinges during hatch removal and reinstallation.
3 NDE 1 Cargo hatch assembly
3.2.5 (NDE) Components designated for NDE: All welds.
Submit a CFR.
4 Service and Inspect
1 Hydraulic hatch lift cylinder
3.2.2 (Service and inspect)
Submit CFR
5 Renew 1 Cargo hatch gasket
N/A See CG TP-3610.
Conduct gasket compression test, upon installation. Submit CFR.
6 Preserve 1 Cargo hatch 3.2.4 Use Coating System: Preserve interior
17 (Rev-0)
OR ASSEMBLY
APPENDIX
AND PARA.
FROM
5000_STD
OTHER
assembly (Preservation) side of hatch and channels (under gaskets) Use coating system: Bulkheads, and Overheads, uninsulated Metal)” in accordance with in SFLC Std Spec 6310, Appendix A Submit CFR.
7 Groom And Lubricate
1 Cargo hatch assembly
3.2.6 (Groom and lubricate)
See Coast Guard Drawing 175 WLM 549- 001.
8 Boundary Testing
1 Cargo hatch assembly
N/A Accomplish a chalk test and water hose test, in accordance with SFLC Std Spec 0740, Appendix C. Adjust dogs in accordance with CG TP-3610.
Submit a CFR.
9 Operational Testing – Post
Repairs
1 Cargo hatch assembly
N/A 1. Raise and lower, dog and un-dog, the hatch three complete cycles.
2. Verify hatch operates in accordance with parameters specified in TP-3610 with no unusual noise or binding.
Submit CFR.
10 Touch-Up Preservation
All New and disturbed surfaces
N/A Prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Appendix A (Cutter and Boat Exterior Painting Systems) and Appendix B (Cutter and Boat Interior Painting Systems), respectively, and as applicable.
4. NOTES
This section is not applicable to this work item.
18 (Rev-0)
53300_0320_IBCT_FLT
REC_53300_IBCT_FLT175 WLM (ALL) (0320)
WORK ITEM 2: Point of Use Potable Water Filters, Install
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to install potable water lead removing filters at all point of use (i.e., drinking fountains {aka water coolers & scuttlebutts}; ice makers and coffee makers).
1.2 Government-furnished property.
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
N Water Filter Assembly PN: DWS160-L (3M)
NSN: (ACN) 44330-01-F20-
6 ea. 160.00
N Water Filter Element PN: 56134-44 (3M) 6 ea. 180.00 N Placard - Potable Water Flush N/A 8 ea. 50.00
***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.
2. REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 175 WLM 533-001, Rev H, Potable Water System Diagram
Coast Guard Drawing FL 533-001, Rev B, Placard Potable Water Flush
Coast Guard Drawing FL 533-002, Rev -, Point of Use Water Filter Install
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2022, Requirements for Preservation of Ship Structures
19 (Rev-0)
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
Sheathing
Insulation
Piping
Electrical wiring
3.2 Potable water filter installation. The Contractor shall install potable water filters provided as Government furnished property (i.e., Paragraph 1.2) and as addressed in those Coast Guard Drawings listed in paragraph 2 REFERENCES.
NOTE
Coast Guard referenced drawings for the most part represents actual shipboard potable water configuration. However, there can be instances where fixtures identified in new table “WATER FILTER INSTALLATION LOCATIONS” do not exist or are not shown in drawing views.
3.2.1 Water filter location. The Contractor shall refer to applicable potable water system diagram drawing specified in paragraph 2 for point of use locations. This drawing has been updated to include a new table titled “WATER FILTER INSTALLATION LOCATIONS”.
NOTE
There is a chance actual shipboard potable water piping on some cutters do not directly service fixtures noted on system diagram drawing “WATER FILTER INSTALLATION LOCATIONS” Table.
20 (Rev-0)
3.2.2 Water filter installation. The contractor shall install potable water filters in accordance with CG Dwg FL 533-002.
3.3 Potable…