QUESTIONS AND ANSWERS - 70Z08523QIBCT0007

Question : “Will the new contract awardee have access to last year’s test results, Pre-groom Survey Performance Test Plan, and the results of the test plan?”

Answer: No, contract awardees will not have access to last year’s test results, test plan, or the results of the plan as they were developed by the prior contractor.

Question: “Is the BT or SSMG Diagnostics groom due this coming year?”

Answer: Generally, Work Item 1: Integrated Power Plant, Groom is activated every year and is the basis of this specification and contract.

Question: Would the government consider increasing the page count for the Technical and Past Performance sections so that a more comprehensive response can be provided?

Answer: Yes, no more than 10 pages will be accepted