Attachment_4b,_Request_for_Clarification_WTGB.docx
DOCX document 29 KB Posted
- Solicitation number
- 70Z085-19-Q-P45C6200
About this file
This document consists of a request for clarification form and related questions and answers pertaining to solicitation number 70Z085-19-Q-P45C6200 from the United States Coast Guard for modifications to the propulsion control system on its 140-foot coastal patrol cutters. Offerors were required to submit any questions regarding the solicitation by July 15, 2019 using the attached request for clarification form, with each question submitted on a separate form and including the name of the offeror. One question concerned the requirement to quote replacement parts for new hardware being provided as part of the upgrade, but not parts for existing retained hardware; the response confirmed the offeror's understanding that quotes should only include materials being purchased for the upgrade.
Attachment 4b, question & answer
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offeror’s questions will be answered by an Amendment.
1. Offeror’s questions concerning this solicitation shall be submitted in writing, and must be submitted on the attached “Request for Clarification” form. One question should be submitted per form. Each form should indicate the name of the offeror’s firm.
2. Questions should be submitted via email to Andrew.G.Jacobs@uscg.mil.
REQUEST FOR CLARIFICATION
Submit requests not later than 15 July 2019
Offeror’s Name:
Date:
Question No.
WTGB 140 Foot Propulsion Controller Modification
| RFQ Number: |
| 70Z085-19-Q-P45C6200 |
SOLICITATION SECTION:
PARA NO.
DEFINITE/OPTIONAL ITEM NO.
PARA NO.
TITLE:
QUESTION: CLIN0003AA – We are to quote 6 sets of replacement parts for only the new hardware we are providing, not the retained hardware in the existing system, correct?
RESPONSE:
This is correct. Just quote prices for all materials being purchased for the upgrade/proposal.