Attachment_2_-_FRANK_DREW_(WLM_175)_DS_FQ3_MAS_19R1.doc
DOC document 17 MB Posted
- Attached to
- USCGC FRANK DREW (WLM 557) FY19 DockSide Repair
- Solicitation number
- 70Z085-19-Q-P4561200
About this file
Specification Rev 01 dated 1 April 2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FRANK_DREW_-_Attachment_1_Schedule_of_Supplies_and_Services.xls | XLS spreadsheet | |
| 70Z08519Q45612000_RFC_Questions_answered.pdf | ||
| SF30_-_Amendment_0001_-_FRANK_DREW_DS.pdf | ||
| Attachment_2_-_FRANK_DREW_work_specification.doc | DOC document | |
| Attachment__4__USCG_Ombudsman_Notice.pdf | ||
| Attachment_5_Request_for_Clarifications.doc | DOC document | |
| Attachment_3__Past_Performance_Information_Form.doc | DOC document | |
| Attachment_1_-_Schedule_of_Supplies_and_Services_FRANK_DREW_(WLM_175).xls | XLS spreadsheet | |
| CSS_CGC_FRANK_DREW_DS_FY19.doc | DOC document | |
| Attachment_6_-_Redacted_FRANK_DREW__FY19DS_JA-rev0.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC FRANK DREW (WLM 557)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2019
Developed By: LT. David Rowland (Rev 1, 1 April 2019)
TABLE OF CONTENTS
iiiRevisions Record ivConsolidated List of References ixConsolidated List of Government-furnished Property xiiiConsolidated List of Critical Inspection Items xivPrincipal Characteristics
1General Requirements
13WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
16WORK ITEM 2: Voids (Accessible), Clean and Inspect
19WORK ITEM 3: Hydraulically Operated Cargo Hatch, Inspect and Service
23WORK ITEM 4: Main Diesel Engine (MDE) Exhaust Piping, Commercial Clean
26WORK ITEM 5: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean
29WORK ITEM 6: Vent Ducts (Engine And Motor Room All), Commercial Cleaning
32WORK ITEM 7: Vent Ducts (Galley and Pantry Room All), Commercial Cleaning
35WORK ITEM 8: Vent Ducts (Laundry Exhaust), Commercial Cleaning
38WORK ITEM 9: Vent Ducts (All Other), Commercial Cleaning
41WORK ITEM 10: Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift
47WORK ITEM 11: Gripes, Binders and Jacks (Loose Rigging Gear), Inspect and Test
50WORK ITEM 12: Hull Fittings (Weight Handling Rigging Hardware), Inspect and Test
55WORK ITEM 13: Hydraulic Chain Stoppers, Inspect And Service
59WORK ITEM 14: Hydraulic Inhaul Winch, Inspect And Service
68WORK ITEM 15: Mechanical Chain Stoppers, Inspect and Service
71WORK ITEM 16: Warping Capstan (Aft), Inspect and Service
75WORK ITEM 17: Single Point Davit, Disassemble and Inspect
79WORK ITEM 18: Buoy Crane, Inspect And Service
88WORK ITEM 19: Grey Water Holding Tank(s), Clean and Inspect
92WORK ITEM 20: Sewage Holding Tank(s), Clean and Inspect
96WORK ITEM 21: Sewage Piping, Clean And Flush
99WORK ITEM 22: Tanks (Sewage Vacuum Collection), Preserve “100%”
102WORK ITEM 23: Deck Covering (Interior Wet/Dry), Renew
106WORK ITEM 24: Focsle Scuttles, Renew
110WORK ITEM 25: Hydraulic Crossdeck Winches, Inspect And Service
115WORK ITEM 26: Temporary Services, Provide - Cutter
118WORK ITEM 27: Weathertight Door, Renew
122WORK ITEM 28: Shower Stall, Renew
126WORK ITEM 29: Power Circuit Breakers, Inspect, Maintain & Test
137WORK ITEM 30: Potable Water Pneumatic Tank(s), Clean and Inspect
140WORK ITEM 31: Potable Water System Relief Valve, Overhaul or Renew
143WORK ITEM 32: Sea Trial Performance, Support, Provide
147WORK ITEM 33: Both Main Diesel Engine Mounts, Renewal
164WORK ITEM 34: Both Z-Drive Propulsion Trains, Alignment
172WORK ITEM 35: Port Button Roller Chock, Renew
174WORK ITEM 36: 01 Level Deck, Repair
177WORK ITEM 37: Stanchions, Renew
179WORK ITEM 38: Buoy Deck Gunwale Repairs
183WORK ITEM 39: Weather Deck Electrical Kick Pipes, Renew
190WORK ITEM 40: Buoy Crane and Deck Machinery Hydraulic System, Circulate and Filter
Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
| DATE |
| REV# |
| WORK ITEM# |
| CHANGES MADE |
| 04/01/2019 |
| 1 |
| 30 |
| Voids (Accessible, weather deck exposed), Inspect) Removed WI-30 and re-numbered following work items due to duplicated statement of work in WI-3 (Duplicate Work Items) |
| 04/01/2019 |
| 1 |
| 34 |
| (Cargo Hatch Gasket, Renew) Removed WI-34 and re-numbered all following work items due to duplicate work that is covered in a previous work item |
| 04/02/2019 |
| 1 |
| 37 |
| Buoy Deck Gunwale Repairs. Inserted note and inserted photos. |
| 04/02/2019 |
| 1 |
| 28 |
| Shower Stall, Renew. Updated table with corrected compartment numbers |
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
Consolidated List of References The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast G Coast Guard Drawing 175-WLM- 631-002, Rev E, Painting Schedule WLM 552 and Follow Coast Guard Drawing 175 WLM 130-001, Rev -, Mods to Buoy Deck Incidental to Hawser Pipe Cover Coast Guard Drawing 175 WLM 233-2, Rev E, Propulsion Train Installation Dwg Coast Guard Drawing 175 WLM 243-2, Rev F, Propulsion Shaft Arrangement Coast Guard Drawing 175 WLM 259-001, Rev A, Combustion Exhaust Diagram Coast Guard Drawing 175 WLM 259-005, Rev C, Combustion Exhaust A&D, Hull Block 970 Coast Guard Drawing 175 WLM 506-001, Rev G, Overflows, Air Escapes & Sounding Tubes Diagram Coast Guard Drawing 175 WLM 512-001, Rev E, HVAC Diagram Coast Guard Drawing 175 WLM 533-001, Rev G, Potable Water System Diagram Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950 Coast Guard Drawing 175 WLM 549-001, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 549-1, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175 WLM 551-001, Rev J, Compressed Air System Diagram Coast Guard Drawing 175 WLM 556-001, Rev L, Hydraulic System Diagram Coast Guard Drawing 175 WLM 573-001, Rev T, Buoy Deck Arrangement Coast Guard Drawing 175 WLM 573-001, Rev T; Buoy Deck Arrangement Coast Guard Drawing 175 WLM 573-050, Rev A, Hydraulic Piping Installation for Chain Stopper Coast Guard Drawing 175 WLM 573-051, Rev B, Chain Stopper Structural Modifications for Hydraulic Roller Assembly Coast Guard Drawing 175 WLM 573-8, Rev -, ATON Tie Downs Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage & Waste Water System Diagram Coast Guard Drawing 175 WLM 593-001, Rev G, Sewage and Waste Water System Diagram Coast Guard Drawing 175 WLM 593-009, Rev E, Independent Tanks, Sewage Holding Tank Coast Guard Drawing 175 WLM 601-001, Rev P, General Arrangement, Inboard & Outboard Profiles Coast Guard Drawing 175 WLM 601-001, Rev R; General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564) Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans Coast Guard Drawing 175 WLM 633-001, Rev D, Cathodic Protection Coast Guard Drawing 175 WLM 634-001, Rev G, Deck Covering Schedule Coast Guard Drawing 175 WLM 644-001, Rev G, Sanitary Facilities & Laundry Space Arrangement & Details Coast Guard Drawing 175 WLM 801-015, Rev C, Scantlings, Decks & Platforms Coast Guard Drawing 175 WLM 920-001, Rev K, Hull Block 920 Panels Coast Guard Drawing 175 WLM-528-001, Rev E, Plumbing and Interior Deck Drains Diagram Coast Guard Drawing 175-WLB_422_001, Rev. G, Navigation, Signal, and Searchlight Block Isometric and Arrangements.
Coast Guard Drawing 175-WLB_422_002, Rev. F, Navigation, Signal, and Searchlight Elementary Wiring Diagram.
Coast Guard Drawing 175-WLM 512-1, Rev E, HVAC Diagram Coast Guard Drawing 175-WLM 528-008, Rev E, Plumbing & Deck Drains A & D, Hull Block 970 Coast Guard Drawing 175-WLM 549-001, Rev E, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM 549-1, Rev C, Onboard Lubrication Requirements Coast Guard Drawing 175-WLM 573-001, Rev R, Buoy Deck Arrangement Coast Guard Drawing 175-WLM 601-001, Rev N, General Arr, Inboard & Outboard Profiles Coast Guard Drawing 175-WLM 601-01, Rev N, Gen Arr, Inbd and Outbd Profiles Coast Guard Drawing 175-WLM 601-1, Rev G, General Arrangement, Inboard & Outboard Profile Coast Guard Drawing 175-WLM 635-1, Rev F, Hull Thermal & Acoustic Insulation Schedule Coast Guard Drawing 175-WLM 644-001, Rev G, Sanitary Facilities & Laundry Space Arrangement & Details Coast Guard Drawing 175-WLM 801-015, Rev C, Scantlings, Decks & Platforms Coast Guard Drawing 175-WLM 801-15, Rev C, Scantlings, Decks & Platforms Coast Guard Drawing 175-WLM 910-002, Rev H, Hull Block 910 Modules Coast Guard Drawing 175-WLM 990-001, Rev J, Hull Block Erection Plan Coast Guard Drawing 175-WLM_432_005, Rev E, Primary and Supplementary Sound Powered Telephone CKTS, BLK & ISO DIAG.
Coast Guard Drawing 175-WLM-167-001, Rev L, Structural Closures Coast Guard Drawing 175-WLM-320-001, Rev AL, Electrical One-Line Diagram Coast Guard Drawing 175-WLM-320-006, Rev G Power System Deck Plan FR 52-88, Hull Block 960 & 970 Partial.
Coast Guard Drawing 175-WLM-320-007, Rev T, Power System Deck Plan 01 Level & Above Coast Guard Drawing 175-WLM-582-001, Rev D, Mooring &Towing. A & D Coast Guard Drawing 175-WLM-601-001, Rev T, General Arrangement Inboard and Outboard Profiles Coast Guard Drawing 175-WLM-601-002, Rev H, Booklet of General Plans Coast Guard Drawing 175-WLM-612-001, Rev G, Lifelines, Rails & Stanchions Coast Guard Drawing FL 2605-031, Rev D, Mechanical Chain Stopper, 1-7/8" Buoy Chain Coast Guard Drawing FL 2605-034, Rev C, Mechanical Chain Stopper Repair Kit: 1-7/8", 1-5/8" & 1-1/4" Coast Guard Drawing FL 7101-573, Rev L, Buoy Chain Winch Assy Model CW1 Coast Guard Drawing FL-1602-89, Rev , Fleet 26’ x 66” Weathertight Doors Coast Guard Fleet Drawing FL-2605-29, Rev L, Chain Stopper System – Rising Sheave Assembly
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch Coast Guard Technical Publication (TP) 3610, Section 167-A, July 2002, Power Operated Cargo Hatch, Coastal Buoy Tender, Model No. D-WK-787 Coast Guard Technical Publication (TP) 3610, Section 167-A, Nov 2005, Hydraulic Cargo Hatch - Model No. D-WK-787 Coast Guard Technical Publication (TP) 3613, Oct 1997; Flexible Coupling Coast Guard Technical Publication (TP) 3626, 12/16/1996; Manufacturers Instruction Book-SWBS Group(s) 516-533 Coast Guard Technical Publication (TP) 3627, Manufacturer's Instruction Book-SWBS 556, Section A, HPU Deck Machinery – Model 7D3-05575 Coast Guard Technical Publication (TP) 3630, SWBS 573, Section A (573A), Jun 2015, Manufacturer's Instruction Book-SWBS Group 573, Buoy Crane Coast Guard Technical Publication (TP) 3631, Mar 2007, Manufacturer’s Instruction Book-SWBS Group(s) 573-581, Section B, Cross Deck Winch – Appleton Marine Model BMD-463 Coast Guard Technical Publication (TP) 3632, March 2014, Chapter 583, Section C, Technical Manual for Slewing Arm Davit Model D6000CT Coast Guard Technical Publication (TP) 3632, Section 582-A, March 2014, Manufacturer's Instruction Book-SWBS Groups 582-583, Aft Capstan Coast Guard Technical Publication (TP) 3653, Jul 2013; SWBS 245, Section A; Z-DRIVE - MODEL 1350-H Coast Guard Technical Publication (TP) 3749, 26-APR-05, 1-7/8 Inch ATON Mechanical Chain Stopper Coast Guard Technical Publication (TP) 3939, SWBS 573-A, Apr 2007, Rising Sheave Chain Stopper Coast Guard Technical Publication 3631 Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install New Deck Covering Systems Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0000, 2014, General Requirements Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 0740, 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3041, 2014, Shipboard Electrical Cable Test Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 3042, 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification (SFLC Std Spec) 6310, 2014, Requirements for Preservation of Ship Structures (COMDIST M10360.3 Series) Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Requirements for Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes.
Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2014, Overhaul AC Electrical Motors Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, And Installation Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Auxiliary Machine Systems Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2014, Install Interior Deck Covering Systems Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2014, Temporary Services Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2014, Temporary Hull Accesses
OTHER REFERENCES
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services American Society for Testing and Materials (ASTM), F1508, 2010, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services American Society of Mechanical Engineers (ASME) B16.34, 2013, Valves-Flanged, Threaded, and Welding End ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets ASTM International (ASTM) D5363, 2008, Standard Specification for Anaerobic Single Component Adhesives (AN) ASTM International (ASTM) D5363, 2008; Standard Specification for Anaerobic Single-Component Adhesives (An) Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment DOD-STD-2187, Aug 1987, Chemical Cleaning of Salt Water Piping Systems Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2013 Edition, Pressure Testing Of Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2011 Edition, Butterfly Valves Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2013 Edition, Bronze Gate, Globe, Angle and Check Valves MIL PRF-16173E INT AMD 1, Sep 2006, Corrosion Prevention Compound, Solvent Cut Back, Cold Application MIL-I-3064, Mar 1991, Insulation, Electrical, Plastic-Sealer MIL-PRF-24176 , Oct 2004, Cement, Epoxy, Metal Repair And Hull Smoothing (Metric) MIL-PRF-24613, Dec 1990, Deck Covering Materials, Interior, Cosmetic Polymeric Mil-S-24235/9E, Dec 1992, Stuffing Tubes, Metal, And Packing Assemblies For Electric Cables, Brass and Steel, for Decks and Bulkhead With Pipe Protection MIL-S-45180, 1998; Sealing Compound, Gasket, Hydrocarbon Fluid and Water Resistant MIL-STD-2003-3A, Sep 2009, Electric Plant Installation Standard Methods for Surface Ships & Submarines (Penetrations) NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation Details The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2004, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2004, Near-White Blast Cleaning The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning Consolidated List of Government-furnished Property The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
| WORK ITEM |
| MTI |
| ITEM DESCRIPTION |
| NSN/PN |
| QTY |
| ESTIMATED COST |
($/Unit)
| 13 |
| N |
| Repair Kit Assembly |
| NSN: 2040-01-496-9418 |
| 2 ea. |
| 1,968.67 |
| 13 |
| N |
| Rod Seal Repair Kit (FL-2605-29 PC#37) |
| NSN: 2040-01-496-9422 |
| 2 ea. |
| 3,030.07 |
| 13 |
| N |
| Repair Kit, Cable Chain (Includes Pads) (FL-2605-29 PC#36) |
| NSN: 3020-01-538-0684 |
| 16 ea. |
| 257.99 |
| 13 |
| N |
| Cylinder Assembly Actuating, Linear |
| NSN: 3040-01-496-9424 |
| 2 ea. |
| 1,969.24 |
| 14 |
| N |
| Roller bearing Unit |
| NSN: 3130-01-504-4363 |
| 2 ea. |
| 4,012.00 |
| 14 |
| N |
| Grease seal |
| NSN: 5330-01-462-5544 |
| 4 ea. |
| 79.25 |
| 14 |
| N |
| Level wind pivot bushing |
| NSN: 3120-01-621-2293 |
| 1 ea. |
| 1,139.00 |
| 14 |
| N |
| Level wind thrust bearing |
| NSN: 3120-01-621-2300 |
| 2 ea. |
| 483.30 |
| 14 |
| N |
| Rexroth DCV |
| NSN: 4810-01-507-0037 |
| 1 ea. |
| 208.29 |
| 14 |
| N |
| Rexroth Sandwich Flow Control |
| NSN: 4810-01-505-9289 |
| 1 ea. |
| 250.00 |
| 14 |
| N |
| Sun Sandwich Relief Valves |
| NSN: 4820-01-439-2451 |
| 2 ea. |
| 900.00 |
| 14 |
| Y |
| Level Wind Hydraulic Cylinder |
| NSN: 3040-01-441-3721 |
| 1 ea. |
| 7,423.00 |
| 14 |
| N |
| 3:1 Pilot Ratio, Vented Counterbalance Valve Assembly |
| NSN: 4820-01-563-5841 |
| 1 ea |
| 98.70 |
| 14 |
| N |
| Fully Adjustable Needle Valve |
| NSN: 4820-01-416-0579 |
| 1 ea |
| 48.75 |
| 14 |
| N |
| Wire Rope Assembly |
| NSN: 4010-01-646-6972 |
| 1 ea. |
| 500.00 |
| 14 |
| Y |
| **Hydraulic Motor |
| NSN: 4320-01-445-2248 |
| 1 ea |
| 23,998 |
| 14 |
| N |
| **Pump, Hydraulic Ram, Hand Driven |
| NSN: 4320-01-286-4065 |
| 1 ea. |
| 419.77 |
| 14 |
| N |
| **Cylinder Pin |
| NSN: 5315-01-515-9847 |
| 1 ea |
| 500.00 |
| 14 |
| N |
| **Cylinder Pin |
| NSN: 5315-01-515-9912 |
| 1 ea |
| 520.00 |
| 15 |
| N |
| Hardware Kit |
| NSN: 5430-01-494-2479 |
| 2 ea. |
| 618.54 |
| 15 |
| N |
| Hardware Kit, Mechanical |
| NSN: 2030-01-485-7215 |
| 2 ea. |
| 784.35 |
| 17 |
| N |
| Swing Brake Seal Kit |
| NSN: 2030-01-351-2820 |
| 2 ea |
| 138.80 |
| 17 |
| N |
| Swing Brake Disc & Bearing Kit |
| NSN: 2030-01-349-9486 |
| 2 ea |
| 937.70 |
| 17 |
| N |
| Wire Rope Assembly, Single Leg |
| NSN: 4010-01-602-8365 |
| 1 ea. |
| 234.00 |
| 17 |
| Y |
| **Winch Assembly |
| NSN: 2030-01-505-1581 |
| 1 ea. |
| 17,454.50 |
| 18 |
| N |
| Wire Rope, Crane Aux Fall |
| NSN: 3950-01-617-1692 |
| 1 ea |
| 629.00 |
| 18 |
| N |
| Wire Rope, Crane Main Fall |
| NSN: 3950-01-617-1700 |
| 1 ea |
| 1,425.00 |
| 18 |
| N |
| Luff Cylinder Seal kit |
| NSN: 5330-01-433-6307 |
| 1 ea |
| 380.00 |
| 18 |
| N |
| Holding Valve |
| NSN: 4810-01-353-0586 |
| 2 ea |
| 84.88 |
| 18 |
| N |
| Shuttle Valve |
| NSN: 4820-01-317-2748 |
| 2 ea |
| 18.97 |
| 18 |
| N |
| Needle Valve |
| NSN: 4820-01-329-0051 |
| 1 ea |
| 36.17 |
| 18 |
| Y |
| Luff Cylinder Control Valve |
| NSN: 4820-01-602-7668 |
| 1 ea |
| 5,259.00 |
| 18 |
| N |
| Bushing, Heel |
| NSN: 5365-01-F12-2920 |
| 4 ea |
| 81.00 |
| 18 |
| N |
| Hydraulic swivel seal kit |
| NSN: 4730-01-566-2864 |
| 1 ea |
| 1,125.00 |
| 18 |
| N |
| **Pin, Heel |
| NSN: 5315-01-500-6931 |
| 2 ea |
| 1006.60 |
| 18 |
| N |
| **Hand pump w/ Stainless Steel Option, P18 |
| NSN: 4320-01-517-1444 |
| 1 ea |
| 473.00 |
| 18 |
| N |
| **Plate, Backing, Brake (Item 231) |
| NSN: 3040-00-119-9848 |
| 1 ea |
| 1,575.00 |
| 18 |
| N |
| **Plate, Brake (Item 232) |
| NSN: 3040-01-068-7647 |
| 1 ea. |
| 377.00 |
| 18 |
| N |
| **Driver Plate (Item 233) |
| NSN: 3040-01-F14-3994 |
| 1 ea. |
| 197.00 |
| 18 |
| N |
| **Plate, Backing, Brake (Item 234) |
| NSN: 3040-00-119-9848 |
| 1 ea |
| 1,575.00 |
| 18 |
| N |
| **Packing Assortment, Preformed |
| NSN: 5330-01-191-2622 |
| 1 ea. |
| 10.94 |
| 18 |
| N |
| **GH30 seal kit |
| 1 ea. |
| 165.23 |
| 18 |
| N |
| **Disc-Friction, Brake |
| NSN: 3040-01-051-3606 |
| 1 ea. |
| 24.42 |
| 18 |
| N |
| **Spring, Helical, Comp |
| NSN: 5360-01-268-0044 |
| 12 ea |
| 13.13 |
| 18 |
| N |
| **PD12C Seal kit |
| NSN: 2590-01-398-5741 |
| 1 ea |
| 60.73 |
| 18 |
| N |
| **Disc, Steel |
| NSN: 2530-01-066-9585 |
| 1 ea |
| 18 |
| Y |
| **Master brake rebuild kit |
| NSN: 5330-01-F16-4572 PN: 98-015-3001 (Eskridge Inc) |
| 3 ea |
| 1,758.00 |
| 18 |
| Y |
| **Hydraulic Control Valve Assembly (winch) |
| NSN: 4810-01-566-2663 |
| 1 ea. |
| 9,222.00 |
| 18 |
| N |
| **Hydraulic Control Valve Assembly (Swing/Luff) |
| NSN: 4820-01-602-7668 |
| 1 ea. |
| 5.259.00 |
| 18 |
| Y |
| **Aux Hoist Hook (Overhaul Ball) |
| NSN: 4030-01-572-3945 |
| 1 ea |
| 629.31 |
| 18 |
| N |
| Block, Tackle |
| NSN: 3940-01-566-2929 |
| 1 ea |
| 1,425.45 |
| 18 |
| N |
| **Relief Valve Cartridge |
| NSN: 4820-01-481-7116 PN: RPIC-LAN (Sun Hydraulics Inc) |
| 1 ea |
| 425.00 |
| 18 |
| N |
| **Control Stand Selector Valve Assembly |
| NSN: 4730-01-507-3516 |
| 1 ea |
| 1,145.21 |
| 18 |
| N |
| **Bushing, Luff Cylinder |
| NSN: 3120-01-363-7629 |
| 4 ea |
| 105.91 |
| 18 |
| N |
| **Pin, Luff Cylinder |
| NSN: 5315-01-F12-2922 PN: MMD-2232 |
| 2 ea |
| 1,576.00 |
| 24 |
| N |
| 18� Diameter Quick-Acting Watertight Raised Scuttle, Steel, 3-Dog, Fwd Hinge (including associated 12�coaming) |
| NAVSEADWG 803-1401890 |
| 2 ea. |
| 4500 |
| 25 |
| Y |
| Hydraulic Brake Assembly |
| NSN: 2530-01-550-7474 |
| 2 ea. |
| 399.00 |
| 25 |
| N |
| Winch Gear Box Assembly |
| NSN: 3010-01-F16-4570 PN: SK9052AZ-SAEB-31.4-H1 (Nord Gear Corp) or YMD-7914 (Appleton Marine Inc) |
| 2 ea. |
| 1,000.00 |
| 25 |
| Y |
| Hydraulic Motor |
| NSN: 4320-01-470-8467 |
| 2 ea. |
| 900.00 |
| 25 |
| N |
| Wire Rope |
| NSN: 4010-01-620-9604 |
| 2 ea. |
| 577.95 |
| 25 |
| N |
| Counter Balance Valve |
| NSN: 4820-01-324-4269 |
| 4 ea. |
| 107.50 |
| 25 |
| N |
| Shuttle Valve |
| NSN: 4820-01-317-2748 |
| 4 ea. |
| 34.78 |
| 25 |
| N |
| Needle Valve |
| NSN: 4820-01-329-0051 |
| 2 ea. |
| 38.00 |
| 25 |
| Y |
| **Directional Control Valve |
| NSN: 4810-01-543-3252 |
| 2 ea. |
| 3,465.17 |
| 25 |
| N |
| Electrical Connector, Hirshmann |
| NSN: 5935-01-640-6747 |
| 4 ea. |
| 32.00 |
| 27 |
| N |
| Steel Weathertight Door, 26� x 66�; 2 dog; RH; w/14� X 18� Window Light |
| 0216701-12 |
| 1 |
| 5,700 |
| 27 |
| N |
| Steel Weathertight Door, 26� x 66�; 2 dog; LH; w/14� X 18� Window Light |
| 0216701-13 |
| 1 |
| 5,700 |
| 35 |
| N |
| Christie & Grey Resilient Engine Mount |
| TSC T10 65/400 |
| 4 ea. |
| 600.00 |
| 35 |
| Y |
| Christie & Grey Resilient Engine Mount |
| TSC T10 65/800 |
| 4 ea. |
| 600.00 |
| 35 |
| N |
| Vulkan RATO Flexible Coupling Element (EG1721R000) |
| 01-466-3015 |
| 2.ea. |
| 25,020.00 |
| 37 |
| N |
| Chock, Roller Button, 16� |
| Part No. 89188 Nashville Bridge Co. Model No, DF-511-5 |
| 1 ea. |
| 3,000 |
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter
Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):
| Work Item |
| Title |
| 3 |
| Hydraulically Operated Cargo Hatch, Inspect and Service |
| 13 |
| Hydraulic Chain Stoppers, Inspect And Service |
| 14 |
| Hydraulic Inhaul Winch, Inspect And Service |
| 15 |
| Mechanical Chain Stoppers, Inspect and Service |
| 16 |
| Warping Capstan (Aft), Inspect and Service |
| 17 |
| Single Point Davit, Disassemble and Inspect |
| 18 |
| Buoy Crane, Inspect And Service |
| 25 |
| Hydraulic Crossdeck Winches, Inspect And Service |
| 29 |
| Voids (Accessible, Weather Deck Exposed), Inspect |
| 40 |
| Deck Covering (Interior Wet/Dry), Renew |
Principal Characteristics
175' WLM, BUOY TENDER
Physical
| Length overall |
| 174' 8" |
| Length between perpendiculars |
| 155' 1" |
| Depth |
| 14' 8" |
| Maximum beam |
| 36' 0" |
| Designed draft |
| 8' 0" |
| Mast height (above 8' waterline) |
| 58' 8" |
| Frame spacing |
| 20" |
| Full load displacement |
| 855.15 Long Tons SW |
| Light load displacement |
| 719.78 Long Tons SW |
| Minimum op condition displ |
| 852.19 Long Tons SW |
HULL
| Hull material |
| Steel |
Machinery
| Main propulsion |
| Two Caterpillar 3508 DITA V-8 diesel; 999 BHP ea @ 1500 RPM |
Two Ulstein 360 degree steerable Z-Drives, 403 SRPM @ 1600 ERPM
| Reduction gears |
| Two Z-Drive units, Cardan shafting; 3.973:1 gear ratio |
| Shaft seal |
| John Crane Type ND |
| Shaft bearings |
| Five pedestal mounted, Cooper split roller bearings |
| Number of propellers |
| 2 |
| Number of blades |
| 4 |
| Diameter |
| 57.1" |
| Rudders |
| None; Z-drive |
| Ship's service generators |
| Three Caterpillar Model 3406 DITA Turbocharged; 285KW, 450V, 60 Hz, 1800 RPM |
| Emergency diesel generator |
| One Caterpillar Model 3406 DIT 210 KW, 24V, 60 Hz, 1800 RPM |
Tank Capacities
| Diesel oil capacity (100%) |
| 16,385 gal |
| Fresh water capacity (100%) |
| 7,339 gal |
| Lubricating oil (100%) |
| 86 gal |
00000_0618_FLT
REC_00000_FLT_Commercial Project @ CG Facility (1212) General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
Coast Guard Drawings None Coast Guard Publications Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Other References None
3. REQUIREMENTS
3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.
NOTE
The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
3.2 Fire watch requirements. The Contractor shall refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:
· Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).
NOTE
Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.
3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is a “Large Quantity Generator. ”
3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:
· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.
· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.
· Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.
3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.
3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).
3.5.6 Additional Requirements. The Contractor shall be aware of the following:
3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.
3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.
3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.
3.6 Local Policy. None.
3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:
3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”
3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”
3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."
3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"
4. NOTES
4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.
QA-1 - QUALITY ASSURANCE INSPECTION FORM
(PRESERVATION CHECKLIST)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
CHECKPOINT 1 – COATING SYSTEM COMPLIANCE
Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.
CHECKPOINT 2 - PAINT STORAGE
Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.
CHECKPOINT 3 - AMBIENT CONDITIONS
Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).
Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).
Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.
CHECKPOINT 4 - PRE-SURFACE PREPARATION
Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.
Verify equipment setup, blast media, and surface preparation methods match designated test coupon.
CHECKPOINT 5 - SURFACE PREPARATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).
Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.
Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).
CHECKPOINT 6 - PRIMER COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Verify proper mixing and stand-in (induction) times.
Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.
Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).
Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.
Brush out all runs, sags, drips, and puddles.
Perform visual inspection for holidays and other defects.
CHECKPOINT 7 – STRIPE COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).
CHECKPOINT 8 – TOP COAT APPLICATION
Verify environmental conditions (see CHECKPOINT 3).
Ensure overcoating window is as per manufacturer’s instructions.
Verify proper mixing and stand-in (induction) times, as applicable.
Verify wet film thickness at random, to prevent under or over application.
Brush out all runs, sags, drips, and puddles.
CHECKPOINT 9 – FINAL INSPECTION
Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.
Ensure that system cure is in accordance with manufacturer's recommendation for intended service.
Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.
For immersion coatings (including tank U/W body), record date and time of the following events:
Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____
CHECKPOINT 10 – RECORD KEEPING
Complete, sign, and submit all provided QA Inspection Forms.
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-2 - QUALITY ASSURANCE INSPECTION FORM
(ENVIRONMENTAL READINGS)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.
| DATE & TIME |
| ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…) |
| LOCATION (Frame & Deck, relation to equipment, etc.) |
| TEMPERATURE |
| % REL. HUMID-ITY |
| DEW PT. |
| SURFACE |
| AMBIENT |
| ΔT |
| DP - Surface |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-3a - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
| SURFACE PREPARATION METHOD |
| PROFILE ACHIEVED (mils) |
| Min |
| Max |
| Mean |
| SSPC-SP-10/NACE No. 2 |
| ( |
| SSPC-SP WJ-1/NACE WJ-1 |
| ( |
| SSPC-SP WJ-2/NACE WJ-2 |
| ( |
| SSPC-SP WJ-3/NACE WJ-3 |
| ( |
| SSPC-SP WJ-4/NACE WJ-4 |
| ( |
| SSPC-SP-3 |
| ( |
| SSPC-SP-11 |
| ( |
| SSPC-SP-11 (inaccessible area) |
| ( |
| Brush-blasting (non-metallic substrate) |
| ( |
Abrasive Manufacturer:
Abrasive Sieve Size:
Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here
Reading (mils):
Reading (mils):
Reading (mils):
Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here
Reading (mils):
Reading (mils):
Reading (mils):
Place Surface Profile
Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here
Reading (mils):
Reading (mils):
Reading (mils):
Place Surface Profile
Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here
Reading (mils):
Reading (mils):
Reading (mils):
Place Surface Profile
Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here
Reading (mils):
Reading (mils):
Reading (mils):
Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-3b - QUALITY ASSURANCE INSPECTION FORM
(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
| SURFACE PREPARATION METHOD |
| PROFILE ACHIEVED (mils) |
| Min |
| Max |
| Mean |
| SSPC-SP-10/NACE No. 2 |
| ( |
| SSPC-SP WJ-1/NACE WJ-1 |
| ( |
| SSPC-SP WJ-2/NACE WJ-2 |
| ( |
| SSPC-SP WJ-3/NACE WJ-3 |
| ( |
| SSPC-SP WJ-4/NACE WJ-4 |
| ( |
| SSPC-SP-3 |
| ( |
| SSPC-SP-11 |
| ( |
| SSPC-SP-11 (inaccessible area) |
| ( |
| Brush-blasting (non-metallic substrate) |
| ( |
Abrasive Manufacturer:
Abrasive Sieve Size:
Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Reading (mils):
Mean Reading (mils)
Mean Reading (mils) IAW ASTM DD4417).
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-4 - QUALITY ASSURANCE INSPECTION FORM
(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Location of Work (incl. frame #’s) |
| Area (sqft) |
SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.
| Date |
| Test Locations |
| Conductivity (Microsiemens/CM) |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
QA-5 - QUALITY ASSURANCE DATA FORM
(COATING THICKNESS)
(Use one sheet for each sequence)
| Vessel Name |
| Hull # |
| Work Item # |
| Work Item Title |
| Coating Mfg |
| Product Name |
| Batch # |
| Induction Time |
| Coating System Sequence (Primer/Touchup/3rd Coat, etc.) |
Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| AVERAGE VALUE |
*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.
Location (Frame Reference):
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
Location (Frame Reference):
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
Location (Frame Reference):
| SPOT |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| Overall Avg. DFT |
| ADJUSTMENTS |
| Avg. BMR |
| Deviation |
| Before Adjustments |
| After Adjustments |
Avg.
| Application Method (Airless, Conventional Spray, Rolled) |
| Average DFT |
| Name of QP-1/NACE Inspector |
| Signature |
| Cert. # |
| Date / Time |
12314_1117_FLT
REC_12314_FLT175’ WLM (ALL) (0611)
WORK ITEM 1: Tanks (Potable Water), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):
Table 1 - Tanks
| TYPE OF TANK |
| LOCATION |
| CAPACITY - 95% |
(gallons)
LOW SUCTION
(gallons)
| Potable Water |
| 1-94-0-W |
| 2,167 |
| 68 |
| Potable Water |
| 2-36-1-W |
| 5,172 |
| 163 |
1.2 Government-furnished property.
None.
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Plans Coast Guard Drawing 175 WLM 533-006, Rev D, Independent Tank Potable Water Hb 950 Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Other References American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System Components - Health Effects American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:
· Fluid contents
· Piping
· RO system components
· Deck grating.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard Personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.
3.3 Plug log. The Contractor shall keep a written record of all plugs put in any tanks vents. A separate list shall be kept for each tank being entered.
3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.
3.4 Tank content removal. The Contractor shall remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. The Contractor shall notify the Dockmaster prior to filling or draining the potable water tank(s), when this item is being executed in a drydock availability. The Contractor shall refer to Coast Guard drawings 175 WLM 601-003 and 175 WLM 533-006 for guidance.
3.5 Tank cleaning. The Contractor shall remove tank cover(s); clean tank interior surfaces free of all foreign materials, such as sediment, sludge and bacterial growth. Remove all persistent residues, taking care not to damage any tank coating system. Remove cleaning media and residues continuously from the tank during the washing process. Remove any residual wash media and wipe up residual moisture with clean lint-free cloths. Collect, contain, and dispose of all wash media, residues, and cleaning materials in accordance with all Federal, state, and local regulations.
3.6 Inspection. The Contractor shall visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces. Submit a CFR including the following, as applicable:
· Tank structural condition.
· Inaccessible areas, if any.
· Condition of tank coating, including measurements taken, percentage, location, and type of coating failure.
· Tank level indicator (TLI) and/or float switch condition (if applicable).
· Sounding tube and striker plate condition.
· Suction and discharge piping condition.
· Fastener material and condition.
3.7 Tank closing. The Contractor shall notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector, and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to ANSI/NSF 61. Renew all stud cotton grommets (as applicable) upon reinstallation of manhole cover(s).
3.7.1 The Contractor shall renew up to 10% of missing or damaged nuts and washers.
3.8 Tank disinfecting. After all other work involving the potable water system and tank closing have been completed, the Contractor shall disinfect and treat the affected potable water tank(s) and associated disturbed piping and components, as necessary, to meet or exceed the requirements of AWWA C652. After tank disinfecting; remove and dispose of all treated water in accordance with all Federal, state and local regulations. Ensure that no one enters the tanks once disinfection is completed.
NOTE
Coast Guard personnel will operate all shipboard machinery and equipment.
3.9 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate the designated tank TLI’s to be in satisfactory operating condition. Submit a CFR.
4. NOTES
This section is not applicable to this work item.
12316_0617_FLT
REC_12316_FLT175’ WLM (ALL) (0813)
WORK ITEM 2: Voids (Accessible), Clean and Inspect
1. SCOPE
1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following void(s):
TABLE 1 - VOIDS
| TYPE OF STRUCTURE |
| LOCATION |
| CAPACITY - 95% |
(gallons)
LOW SUCTION
(gallons)
| Void |
| 3-18-0-T |
| 2,000 |
| 50 |
| Void |
| 3-52-0-V |
| 5,000 |
| 50 |
2. REFERENCES
Coast Guard Drawings Coast Guard Drawing 175 WLM 601-003, Rev F, Booklet of General Drawings (552-564) Coast Guard Publications Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements Other References ASTM International (ASTM) D1330, 2004, Standard Specification for Rubber Sheet Gaskets
3. REQUIREMENTS
3.1 General.
3.1.1 CIR.
None.
3.1.2 Tech Rep.
Not applicable.
3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel’s components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.
3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).
note Coast Guard personnel will operate all shipboard machinery and equipment.
3.1.5 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard personnel perform an initial operational test of the TLI’s for tanks listed in paragraph 1.1 (Intent), to demonstrate existing operational condition. Submit a CFR.
3.2 Cleaning and inspection requirements. The Contractor shall refer to Coast Guard Drawing 175…