Statement_of_Work_USCGC_Mellon_Galley_Cabinet_and_Drawer_Repair.pdf
PDF 16 KB Posted
- Attached to
- Ship Galley Cabinet and Drawers Repair
- Solicitation number
- 70Z085-19-Q-DHL200
About this file
Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| image6.jpeg | JPEG file | |
| image2.jpeg | JPEG file | |
| SCA_WD.pdf | ||
| image4.jpeg | JPEG file | |
| FAR_52.212_and_HSAM_Clauses_for_SERVICES,_FAC_2005-83.pdf | ||
| image3.jpeg | JPEG file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
USCGC MELLON
SHIP GALLEY METAL DRAWERS & CABINET
REPAIRS
SCOPE OF WORK
USCGC MELLON is a 50 year old ship located Seattle moored to CG Base Seattle. The ship has a galley for preparing and serving food that has several metal cabinets and drawers that need repairs and/or replacements. There are few that have broken door latches, tracks, and shelves, as well as a couple warped doors. The ship is set to sail in a few short weeks and will need a contractor to effect repairs with urgency.
1.0 OBJECTIVE
1.1 Repair and/or replace metal cabinet doors and drawers in the ship’s galley within 10 business days of award.
2.0 REQUIREMENTS
Contractor will provide the labor, materials and equipment to perform the following:
2.1 Repair doors to one stand-up cabinet: 59.5” x 14.5”
2.2 Repair doors to two cabinet shelfs: 47.5”x12.5”
2.3 Repair/install inside shelf to one cabinet
2.4 Repair eight metal drawers with latch and track problems:
21.75”Lx8”Hx20.5”D
3.0 TECHNICAL POINT OF CONTACT
Primary
3.1 Casey A Bettega
Casey.A.Bettega@uscg.mil (206)-217-6290
Secondary
3.2 Steven D. Dull
Steven.D.Dull@uscg.mil (206)-217-6290 mailto:Casey.A.Bettega@uscg.mil mailto:Steven.D.Dull@uscg.mil
4.0 PLACE OF PERFORMANCE
4.1 USCG Base Seattle – Pier 36
1519 Alaskan Way S Seattle, WA 98134
5.0 SITE VISIT
5.1 Site visits are highly encouraged prior to proposal submission.
Safety Protections of Personnel and Property
01. During the execution of project, the contractor shall conform to the rules and regulations as set forth by OSHA Safety Standards, 29 CFR Part 1926- Safety and Health Regulations for Constructions and Title 8, California Administrative Code-Construction Standards. When the Standards differ, the more restrictive standard will apply.
02. Contractor will be responsible for initiating, maintaining, and supervising all safety precautions and programs in connection with the performance of this project.
03. Contractor shall take all necessary precautions for their own safety and for the safety of others.
04. Hearing protection may be required throughout the project due to aircraft operation.
File details come from the government source that posted it.