Decks Questions and Answers.pdf

PDF 67 KB Posted

Attached to
USCGC Harry Claiborne deck renewal
Solicitation number
70Z08425QDL930003
Issued by

About this file

This is a Questions and Answers document containing 11 questions related to a deck renewal project for the USCG vessel Harry Claiborne in Galveston, TX.

The Q&A addresses key logistical and technical requirements for the deck renewal work. The contractor must provide and install protective coverings and handle interferences, with equipment staging allowed 20-30 feet from the vessel on the pier. The Coast Guard will provide water and power on the pier. The work requires stripping to bare metal with visual inspection before priming, and underlayment must be installed as needed to smooth steel surfaces and slope toward deck drains. The 2020 revision of STD SPEC 6341 for Installing Interior Deck Covering Systems will be provided. Other details include confirmation that project drawings will be supplied, photos of current deck conditions are available, and contractors must coordinate with the site visit POC for vessel access. The solicitation deadline was extended to accommodate holiday schedules.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Decks Questions and Answers Number Question Answer

Do you have any pics of the crew heads, showers, change out rooms requiring deck renewals, we would like to see current conditions?

yes

Are all interferences going to be removed by USCG? If we are required to remove interferences, could you send us pics of the inteferences?

Contractor shall provide and install protective coverings and handle interferences.

3 How far away from the vessel will we be able to stage equipment?

On the Pier, approximatley 20-30 feet from vessel

4 Will CG supply water and power? Yes, water is on the pier and

5 Are we required to do down to bare metal? Yes, visual inspection prior to priming deck is required.

Also for the PPQ, lots of CG personnel are on vacation this week, can we submit our Job completion report/certificates for the previous projects/work completed. No. The soliciation was extended due to the holiday schedules

7 Can we visit the boat tomorrow ? Contact the site visit POC for scheduling

Would you consider “rely all” with the 202 revision of SFLC 6341 for Installing Interior Deck Covering Systems? The 2020 revision of STD SPEC 6341 can be provided

Is there a way to indicate if underlayment will be required and what type?

Underlayment will be required as needed to smooth steel surfaces and slope towards deck drains.

Could you please provide the drawings for each of the work items? Yes

Also, are there any pictures available showing the current condition of the deck? Yes