Davit Overhaul 70Z08024Q21413B00 SOW- ATTACHMENT C.docx
DOCX document 45 KB Posted
- Attached to
- Overhaul Welin Lambie Davits
- Solicitation number
- 70Z08024Q21413B00
About this file
This document is a Statement of Work (SOW) for the overhaul of Welin Lambie Dual Point Davits, model TW.PIV 5.0B, under Solicitation 70Z08024Q21413B00.
The key details are:
- The contractor shall inspect, test, and overhaul 11 Government-furnished Welin Lambie TW.PIV 5.0B Dual Point Davits.
- The contractor must renew mandatory parts listed in the solicitation and may propose additional parts for renewal based on inspection.
- The work shall be performed at Welin Lambie's facility in the UK or their US overhaul facility.
- The contractor must maintain hydraulic system cleanliness, renew non-structural fasteners, elastomers, bearings, and other components, and preserve the davits per specified requirements.
- The contractor shall conduct factory operational tests to validate the davits meet performance requirements prior to return shipping to the Coast Guard.
- The contractor shall provide a 12-month warranty on the overhauled davits.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Davit Overhaul Solicitation - 70Z08024Q21413B00.docx | DOCX document | |
| Davit Overhaul TW.PIV 5.0B -ATTACHMENT B - List of Contractor Furnished Mandatory parts.xlsx | XLSX spreadsheet | |
| Davit Overhaul - 70Z08024Q21413B00 Attachment A -Schedule of SuppliesServices - PRICE FILL IN.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT C
STATEMENT OF WORK
1. GENERAL INFORMATION
1.1 Shipping Location
1.1.1 Unless specified otherwise on the resultant contract, all items within this contract shall be shipped to the following address:
USCG Surfaces Forces Logistics Center (SFLC) Receiving Room, Building 88 2401 Hawkins Point RD Baltimore, MD 21226
If shipment to a different location than above, any increase in shipping costs incurred shall be addressed and negotiated.
1.2 Preservation, Packaging and Marking (PP&M)
1.2.1 Unless otherwise stated for shipments to locations other than location identified in paragraph 1.1.1 above, the contractor shall package each kit, davit, or assembly in accordance with ASTM D3951. The contractor shall mark (stencil) the shipping/packaging container with the following information:
· National Stock Number (NSN) – (as determined/ applicable)
· Item Name: (as determined)
· Part Number: (as determined)
· Shipping weight: (as determined)
· Government Contract Number: (as determined)
· Maintenance Procedure Card (MPC) Number (as determined/ if applicable)
2. CONSOLIDATED LIST OF REFERENCES
2.1 Coast Guard Drawings
· Coast Guard Drawing 225 WLB 583-051, Rev B, Installation of Dual Arm Davit and TANB Aluminum Workboat
· Coast Guard Drawing 225 WLB 583-052, Rev F, Workboat Davit Installation & Related Modifications
· Coast Guard Drawing 240 WLB 573-002, Rev B, Weight Handling System Arrangement
· Coast Guard Drawing 618 WMEC 583-063, Rev G, OTHB Davit Arrangement
· Coast Guard Drawing 618 WMEC 583-064, Rev D, OTHB Davit Installation
· Coast Guard Drawing 627 WMEC 583-040, Rev J, OTHB Davit Arrangement
· Coast Guard Drawing 627 WMEC 583-041, Rev F, OTHB Davit Installation
· Coast Guard Drawing 901 WMEC 583-023, Rev E, OTHB Davit Installation
· Coast Guard Drawing 901 WMEC 583-024, Rev G, OTHB Davit Arrangement
· Coast Guard Drawing 905 WMEC 583-025, Rev E, OTHB Davit Installation
· Coast Guard Drawing 905 WMEC 583-025, Rev G, OTHB Davit Installation
· Coast Guard Drawing FL-2605-38, Rev A, Welin Lambie 5.0B RHI Cradle End Pads
· Coast Guard Drawing FL-2605-39, Rev -, Zodiac H733 RHI – Wood Cradle Chocks
· Coast Guard Drawing FL-8201-107, Rev A, Welin Lambie Davit OTH Gripe Assemblies
· Coast Guard Technical Publication (TP) 3943, Feb 2019, Twin Pivot Arm Davit - Type TW.PIV 5.0B - Ref. No. 5558-1 thru 5558-15
· ASTM D3951 (1990), Standard Practice for Commercial Packaging
2.2 Coast Guard Publications
· Coast Guard Technical Publication (TP) 3943, Feb 2019, Twin Pivot Arm Davit - Type TW.PIV 5.0B - Ref. No. 5558-1 Thru 5558-15
· Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
· Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements
· Surface Forces Logistics Center Standard Specification 2351 (SFLC Std Spec 2351), 2020, Overhaul DC Generators & Motors
· Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2020, Overhaul AC Electrical Motors
· Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary Machine Systems
· Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ships Structures
· Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
2.3 Other References
· ANSI/ NCSL Z540-1, Calibration Laboratories and Measuring and Test Equipment - General Requirements
· ASME BPV Code Section VIII, Division 1 & 2, Rules for the Construction of Pressure Vessels
· ASTM D3951, Standard Practice for Commercial Packaging
· British Standard (BS) BS EN 837-1, 03/1998, Pressure Gauges Part 1: Bourdon Tube Pressure Gauges – Dimensions, Metrology, Requirements and Testing
3. SPECIFIC TASKS AND REQUIREMENTS
The contractor shall perform and adhere to the work requirements:
3.1. Requirements
3.1. Open, Inspect and Report (OIR) of NSN 2030-99-454-8999, Davit, Model TW.PIV 5.0B
3.1.2. SEE ATTACHMENT B to Solicitation 70Z08024Q21413B00 for list of contractor furnished mandatory parts.
3.1.3. Scope, Factory Inspect, Test, and Overhaul Davits
3.1.3.1 Intent. This work item describes the requirements for the Contractor to inspect, test, and overhaul Government furnished Welin Lambie TW.PIV 5.0B Dual Point Davits.
Table 1 - Government Furnished Property
| Part Number |
| Item Description |
| QTY |
| Estimated Cost ($) / Unit |
| TW PIV 5.0B |
| Welin Lambie Dual Point Davit |
| EA. |
| $597,400.00 |
| N/A |
| Connex Shipping Container |
| EA. |
| $20,000.00 |
3.1.3.2 Mandatory Replacement Parts. The contractor shall renew parts listed in Schedule B, Welin Lambie Parts Catalog for Model TW.PIV 5.0B Davits. These are mandatory parts required to be renewed. The parts specified may not be all-inclusive of parts that may need to be renewed. All additional parts recommended by the contractor for renewal shall be addressed via results of inspection report and contracting officer approved change request (CR)/Modification to the contract.
3.1.3.3 References.
· Coast Guard Drawing 225 WLB 583-051, Rev B, Installation of Dual Arm Davit and TANB Aluminum Workboat
· Coast Guard Drawing 225 WLB 583-052, Rev F, Workboat Davit Installation & Related Modifications
· Coast Guard Drawing 240 WLB 573-002, Rev B, Weight Handling System Arrangement
· Coast Guard Drawing 618 WMEC 583-063, Rev G, OTHB Davit Arrangement
· Coast Guard Drawing 618 WMEC 583-064, Rev D, OTHB Davit Installation
· Coast Guard Drawing 627 WMEC 583-040, Rev J, OTHB Davit Arrangement
· Coast Guard Drawing 627 WMEC 583-041, Rev F, OTHB Davit Installation
· Coast Guard Drawing 901 WMEC 583-023, Rev E, OTHB Davit Installation
· Coast Guard Drawing 901 WMEC 583-024, Rev G, OTHB Davit Arrangement
· Coast Guard Drawing 905 WMEC 583-024, Rev G, OTHB Davit Arrangement
· Coast Guard Drawing 905 WMEC 583-025, Rev E, OTHB Davit Installation
· Coast Guard Drawing FL-2605-038, Rev A, Welin Lambie 5.0B RHI Cradle End Pads
· Coast Guard Drawing FL-2605-039, Rev -, Zodiac H733 RHI – Wood Cradle Chocks
· Coast Guard Drawing FL-8201-107, Rev A, Welin Lambie Davit OTH Gripe Assemblies
· Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes
· Surface Forces Logistics Center Standard Specification 2351 (SFLC Std Spec 2351), 2020, Overhaul DC Generators & Motors
· Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2020, Overhaul AC Electrical Motors
· Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary Machine Systems
· Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship’s Structures
· Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Jun 2006, Coatings and Color Manual
· Coast Guard Technical Publication (TP) 3943, Feb 2019, Twin Pivot Arm Davit - Type TW.PIV 5.0B - Ref. No. 5558-1 Thru 5558-15
· ANSI/ NCSL Z540-1, Calibration Laboratories and Measuring and Test Equipment - General Requirements
· ASME BPV Code Section VIII, Division 1 & 2, Rules for the Construction of Pressure Vessels
· ASTM D3951, Standard Practice for Commercial Packaging
· British Standard (BS) BS EN 837-1, 03/1998, Pressure Gauges Part 1: Bourdon Tube Pressure Gauges – Dimensions, Metrology, Requirements and Testing
3.1.4. Requirements
3.1.4.1 General. The contractor shall accomplish all work herein in accordance with SFLC Std Spec 5000, TP 3943, and using references above for guidance and direction. For reference, the Safe Working Load (SWL) of davit is 11,000 lbs.
3.1.4.2 Place of Performance. The contractor shall accomplish the "Factory Inspect, Test, and Overhaul Davits (Model TW.PIV 5.0B)” requirements at Welin Lambie in the United Kingdom or Welin Lambie Overhaul facility within the continental United States.
3.1.4.3 Protective Measures - Hydraulic System. The contractor shall maintain existing hydraulic system cleanliness and take all necessary precautions to prevent the introduction of contaminants into the hydraulic system. Whenever disconnecting or removing components from the hydraulic system, the contractor shall completely seal all openings to the rest of the system, immediately, using either caps (for externally threaded connection points), bolt-on blanks, or taped-on discs/covers composed of durable plastic or sheet-metal no less than 1/16-inch thick.
NOTE
Plastic bags may be used only when arrangement or configuration prevents the use of the other sealing methods specified above.
3.1.4.4 Non-structural Fasteners and Grease Fittings. The contractor shall renew all non-structural fasteners and grease fittings with 300-series stainless steel. Non-Structural fasteners include roll pins, circlips, cotter pins and other fasteners.
3.1.4.5 Elastomer renewal. The contractor shall renew all O-rings, oil seals, gaskets, and seals.
3.1.4.6 Bearings and Bushings. The contractor shall renew all bearings and bushings.
3.1.4.7 Pipe Clamps and Hangers. The contractor shall renew all pipe clamps and pipe hangers.
3.1.4.8 Junction Boxes. The contractor shall renew all Frame and Arm mounted GRP junction boxes.
3.1.4.9 Labels and Tags. The contractor shall renew all labels and tags.
3.1.4.10 Hydraulic Test Points. The contractor shall renew all exterior hydraulic test points.
3.1.5 Receipt Report
Within fourteen (14) days from receipt of the davit at contractor’s facility, the contractor shall inspect and inventory the davit assembly and submit a receiving report on the following:
· General condition of the shipping container and davit assembly
· Davit model and serial number
· Missing or damaged parts/components with photographs of each
3.1.5.1 Additional part renewal. Based upon Receipt Report above, the contractor shall provide an inspection report identifying all additional parts deemed necessary for renewal (beyond Mandatory Replacement Parts referenced above), with supporting reasons for each part identified for renewal. All parts recommended for renewal shall be handled via a change request requiring Contracting Officer approval and resulting in a formal modification to the contract.
3.1.5.2 American Bureau of Shipping (ABS) and Safety of Life at Sea (SOLAS) Certification. All davit work performed by the Contractor shall meet ABS/SOLAS certification requirements. All davits provided to the Coast Guard shall have current/renewed ABS/SOLAS certification.
No work conducted by the contractor on the Welin Lambie TW.PIV 5.0B Dual Point Davit system shall have the effect of invalidating the ABS/SOLAS certification status of the davit. Contractor will replace such certification at no additional expense to the Government, if adversely impacted by repairs.
3.1.6 Inspections
3.1.6.1 Clean, Visually Inspect and Report. The Contractor shall clean and visually inspect the following and submit an inspection report to include Condition Found Reports (CFR’s) within 84 calendar days of receipt of davit. The contractor shall identify and include any work not specified in this requirement as part of the CFR’s submitted, to include additional work and/or replacement parts recommended by the contractor as a result of this inspection in the inspection report (CFR’s), along with an associated cost proposal for COR review and Contracting Officer approval. Items for inspections are: Davit assembly
· Davit Assembly
· Sheaves
· Boat block assembly
· Hydraulic reservoir(s)
· Exterior electrical cables, wiring, and conduit
NOTE
Do not inspect any mandatory replacement parts.
3.1.6.2 Non-Destructive Inspection (NDI). The contractor shall perform NDI of the following in accordance with SFLC Std Spec 0740, Appendix C:
· All machinery foundation welds
· Davit Frame
· Winches
· Forward davit arm
· Aft davit arm
3.1.6.3 Overhaul. Upon receipt of the Contracting Officer’s authorization to proceed, the contractor shall overhaul and preserve (as applicable), the following components/assemblies and subcomponents/assemblies including any additional work approved by the Contracting Officer as a result of CFRs.
3.1.6.4 Mechanical.
3.1.6.4.1 Structural and rigging gear, including the following:
· Cranston hook assemblies
· Sheave assemblies
· Sixteen galvanized steel roller assemblies
· Forward davit arm hinge pin assembly
· Aft davit arm hinge pin assembly
3.1.6.4.2 Main winch, including the following:
· Main winch brake assembly
· Turning handle safety device
· Winch mounted, luffing hydraulic cylinder directional control valve (lever valve)
3.1.6.4.3 HPU, including the following:
· Forward main system relief valve
· Aft main system relief valve
· Forward hydraulic pump assembly
· Aft hydraulic pump assembly
· Forward high-pressure hydraulic filter assembly
· Aft high-pressure hydraulic filter assembly
· Two return hydraulic filter assemblies
· Rotary flow divider assembly
· Brake directional control valve assembly
· Brake hydraulic cylinder rod end flow control valve
· Brake hydraulic cylinder cap end flow control valve
· Forward luffing cylinder 2-position directional control valve assembly
· Aft luffing cylinder 2-position directional control valve assembly
· Forward luffing cylinder 3-position directional control valve assembly
· Aft luffing cylinder 3-position directional control valve assembly
· Two forward luffing cylinder shuttle valves
· Two aft luffing cylinder shuttle valves
· Hydraulic sump tank assembly
· Hydraulic fluid heater and thermostat assembly
3.1.6.4.4 Accumulators, including the following:
NOTE
The contractor shall test and certify the accumulators/cylinders using ASME BPV Code Section III as guidance.
· Forward hydraulic accumulator assembly
· Aft hydraulic accumulator assembly
· Safety block and pressure gauge assembly
· Poppet valve assembly
· Renew Accumulator safety burst disc
3.1.6.5 Electrical.
· Forward tension winch assembly (assembly, brake assembly, and gearbox
· Aft tension winch assembly (assembly, brake assembly, and gearbox)
3.1.6.5.1 Sensors and controls, including the following:
· Forward luffing arm encoder assembly
· Aft luffing arm encoder assembly
· Control stand assembly
3.1.6.5.2 Electric motor initial open, inspect, and report. The contractor shall perform an initial inspection of motors in accordance with SFLC Std Spec 3020 (Initial Inspection) and SFLC Std Spec 2351 (Initial Inspections) and submit a CFR:
· Main winch electric motor
· Forward hydraulic pump electric motor
· Aft hydraulic pump electric motor
· Forward falls tension electric motor
· Aft falls tension electric motor
3.1.6.6 Other.
· Sump tank level indicator
· Forward pump pressure transducer
· Aft pump pressure transducer
· Forward hydraulic cylinder rod-end pressure transducer
· Forward hydraulic cylinder cap-end pressure transducer
· Aft hydraulic cylinder cap-end pressure transducer
· Aft hydraulic cylinder rod end pressure transducer
3.1.6.7 Renewals.
The contractor shall furnish and renew all hydraulic hose assemblies in accordance with SFLC Std Spec 5000, Appendix C, Paragraph C2.2 (Hose assemblies).
NOTE
The contractor shall test and certify new hydraulic hose assemblies.
3.1.6.8 If required, the Contractor shall renew aluminum blocks via an inspection report and Contracting Officer approved change request.
3.1.6.9 Updates and Upgrades. Update or upgrade the following, as required:
3.1.6.9.1 Operating system and electrical updates and upgrades:
· Auto-launch, control & diagnostics software
· Inverter, PLC & Magellis screen
· Firmware and hardware (memory, counter cards, batteries)
· Zelio software / hardware replacement if required
· Fuse holders
3.1.6.9.2 Component upgrades.
· Limit switches
· Others, as necessary
3.1.6.10 Pressure gauge calibration. The contractor shall ensure all pressure gauges are in accordance with BS EN 837-1 and are calibrated with reference to the contractor’s master calibration gauge. Affix calibration labels to the faces of all gauges noting the calibration facility name and date tested.
3.1.6.11 Accumulator and HPU relief valves setting. The contractor shall properly set the accumulator and HPU relief valves and tag each with the date of calibration and pressure settings.
3.1.6.12 Surface preservation. The contractor shall preserve the davit in accordance with SFLC Std Spec 5000 and SFLC Std Spec 6310 as follows.
3.1.6.12.1 Ferrous components – 100% preservation. The contractor shall prepare and preserve in accordance with SFLC Std Spec 6310 Appendix A5 Machinery, Deck, Option 1, with the following exception. The contractor shall substitute the use of Sigma Zinc 109 HS zinc rich primer, Color 10371 (Spar) as a replacement for Dimetcote 302 H zinc rich primer.
3.1.6.12.2 Ferrous components – partial preservation. The contractor shall prepare and preserve in accordance with paint manufacturers data sheets with the following exception. The contractor shall substitute the use of Sigma Zinc 109 HS zinc rich primer, Color 10371(Spar) as a replacement for Dimetcote 302 H zinc rich primer.
3.1.6.12.3 Non-ferrous components. The contractor shall prepare and preserve in accordance with SFLC Std Spec 6310 Appendix A5 Machinery, Deck, Option 1, with the following exception. The contractor shall substitute the use of Sigma Cover 280 primer: Color 10371 (Spar) as a replacement for Intergard 269 primer.
3.1.6.13 Groom and lubricate. The contractor shall groom and lubricate the Welin Lambie davit system in accordance with SFLC Std Spec 5000(can be made available upon request).
3.1.6.13.1 Hydraulic fluid. The contractor shall flush the davit hydraulic system in accordance with SFLC Std Spec 5000, Appendix C, Paragraph C2.1 (Fluids) and submit an inspection report, prior to performing Factory Tests, detailing work accomplished as outlined therein.
3.1.7 Test Requirements – Post Repairs.
3.1.7.1 Test plan. 45 Days prior to the proposed start date of testing, the contractor shall submit a test plan to the Contracting Officer for review and approval. The contractor’s test plan shall include all tests prescribed, to be performed upon completion of all work specified in this requirement. For reference, the Safe Working Load (SWL) for the davit is 11,000 lbs.
3.1.7.2 Test notification. The contractor shall give Coast Guard personnel 45 days of notice prior to testing. If requested in writing by the Coast Guard within 30 days in advance of factory tests, a designated Coast Guard Quality Assurance (QA) Representative shall be permitted to witness all tests, on-site, at the discretion of the Coast Guard.
3.1.7.3 Factory tests. After completion of the work the contractor shall conduct the following factory operational tests of the davit system, on a level plane, to prove satisfactory operating conditions, in accordance with SFLC Std Spec 5000 and as specified herein. The contractor shall submit a Final Report summarizing all test results to the Contracting Officer and the COR within 14 days of completing factory tests.
3.1.7.4 No load test. The contractor shall conduct an operational test of the davit using no load over the entire range of motion.
3.1.7.5 The Contractor shall operate the davit and test all emergency stop(s), limit switch activation, brake turning handle, and emergency luffing mode (using accumulators).
3.1.7.6 Automatic and manual Brake Test Load (BTL). The contractor shall conduct a static brake test in accordance with SFLC Std Spec 5000 paragraph B2.7.2.3 using 150% of the Safe Working Load (SWL) of one drum revolution and hold the load for a minimum of 10 minutes. The contractor shall allow sufficient time to inspect the brake for slippage or creep before performing a controlled release of the load.
3.1.7.7 Dynamic Test Load (DTL) tests. The contractor shall conduct the Dynamic Load Test in accordance with SFLC Std Spec 5000 paragraph B2.7.2.4 while operating the system in the normal power mode and the hydraulically stored energy mode (emergency operation). The contractor shall conduct these tests using a total combined weight of (13,750 lbs.) with a 50-50 weight distribution and a 40% forward – 60% aft weight distribution for each operation mode.
3.1.7.8 Luffing speed test at SWL. The contractor shall record luffing speeds from the fully retracted to the fully extended positions and then, from the fully extended to fully retracted positions at SWL.
3.1.7.8.1 Luffing speed test at 125% SWL. Record luffing speeds from the fully retracted to the fully extended positions and then, from the fully extended to fully retracted positions at 125% of SWL.
NOTE
Both luffing speed tests in normal operation mode shall meet a 30 to 33 second nominal luff-in and 40 to 43 second nominal luff-out time.
Both luffing speed tests in emergency operation adode shall meet a 24 to 28 second nominal luff-in and 24 to 28 second nominal luff-out time.
Times are approximate +/- 03 seconds
3.1.7.9 Dynamic test (at SWL) data recording. During the SWL dynamic test, the contractor shall record the following.
3.1.7.10 Main winch running speed test – gravity lower. The contractor shall measure and record the main winch speed.
NOTE
The minimum speed shall be 69.9 RPM rope drum speed.
3.1.7.11 Main winch hoist test – demonstrate variable speed. The contractor shall measure and record fast and slow hoist under power.
NOTE
The minimum fast speed and low hoist speeds shall be 52 RPM and 17.5 RPM rope drum speed, respectively.
3.1.7.12 Main winch lower test – demonstrate variable speed. The contractor shall measure and record fast and slow lowering under power.
NOTE
The minimum fast speed and low lowering speeds shall be 52 RPM and 17.5 RPM rope drum speed, respectively.
3.1.7.13 Emergency hand hoisting at 110% of SWL. The hand hoist shall be operated satisfactorily at 110% of SWL.
3.1.7.14 Automatic launch and recovery testing. The contractor shall operate the davit in the automatic launch and recovery modes.
3.1.7.15 Test certification. The contractor shall provide a factory test certification, identified by davit serial number and date of completion, upon successful completion of all testing.
3.1.7.16 Label plate. The contractor shall install a label plate to document satisfactory test completion in accordance with SFLC Std Spec 5000, Appendix B, Paragraph B2.9 (Label Plates). Label plate shall be the same as figure B-2 in appendix B of the SFLC Standard Spec 5000. The contractor shall affix the label plate to the front of the control station on the davit using a suitable weatherproof adhesive.
3.1.7.17 Preservation, Packaging and Marking (PP&M). The contractor shall package each davit individually in accordance with ASTM D3951. The contractor shall mark (stencil) each preserved and packaged unit on the rear door of the shipping container. If the lettering is stenciled, lettering shall be at least ¼” high, in print lettering highly contrasting to the background color of the storage container with the information provided in paragraph 3.3.3.2 below. The Davits shall be shipped in storage containers approved by ABS under ABS Rules for Certification of Cargo Containers (1998). The containers shall be capable of being stored in a warehouse or outside exposed to the weather for periods of up to one year. Damage to the equipment resulting from improper packaging and/or preservation shall be the responsibility of the contractor and shall be replaced or repaired at no expense to the Government. The contractor shall note special handling requirements clearly on each item and on the Bill of Lading. Equipment shall be separated by shipset; material for delivery to multiple ships shall not be in the same container. Any shipments required due to equipment failures, defect correction, and/or non-conformance to specification, shall be the responsibility of the contractor and at no expense to the Government.
NOTES
The contractor shall ensure any exposed areas on the hydraulic cylinders are lubricated with an appropriate light preservative and wrapped with moisture barrier paper during storage.
The contractor shall ensure storage protection of the shipping container and davit preservation is adequate for up to 1 year of outdoor storage.
3.1.7.18 Return shipping. Unless otherwise specified all davits for this task shall be shipped to the location listed in the General Information section of this document.
3.1.7.19 Upon completion of the davit overhaul and testing, the packaged overhauled davit shall be shipped in the certified Government-furnished Conex container used for initial davit shipment from the Coast Guard to Welin Lambie in the U.K. If the Government-furnished Connex container certification expires during the period it is at the contractor’s facility, or is estimated to expire while at the facility, the contractor shall submit an inspection report documenting the container deficiencies and the cost to have container re-certified. The contractor must obtain contracting officer approval before expending any cost for container re-certification.
3.1.7.20 Return shipment of the overhauled and test-certified davit to the Coast Guard shall be completed within 164 days of receipt of the inspection report.
3.1.7.21 Warranty. The contractor shall provide a 12-month warranty from the date of equipment installation to a maximum of 24 months from the date of receipt, whichever comes first, for each davit system overhaul.
The contractor shall provide, at no cost to the Government, technical support services during the period of the warranty. A contractor designated service representative shall be available for response by telephone within 24 hours and shall be capable of meeting a vessel in any port of the continental United States within 72 hours of request, at no additional cost to the Government.
3.1.7.22 Quality assurance.
3.1.7.22.1 General. The contractor shall maintain an inspection system which shall insure that each item offered to the Coast Guard for inspection and acceptance conforms to the contract requirements. The inspection system shall be documented and available for review by the Coast Guard.
3.1.7.22.2 Records/Reports. The contractor shall maintain records of all inspections and tests. The records at a minimum shall indicate the nature and number of observations made, the number and type of deficiencies found, and the corrective action taken. The contractor shall provide the COR with completed copies of the ABS testing results upon completion of testing. A copy of the ABS test certification shall be provided to the Contracting Officer when issued.
3.1.7.22.3 Calibration system. The Contractor, as well as any subcontractors, shall be required to maintain a test equipment calibration program in compliance with American National Standards Institute/National Conference of Standards Laboratories (ANSI/NCSL) Z540-1. The program shall be documented and traceable to the National Institute of Standards (NIST) or a European equivalent (BS EN 837-1). The contractor shall submit to the contracting officer sufficient information to permit approval of the equipment calibration program. The contractor may choose to use gauges calibrated with reference to the contractor’s master calibration gauge in accordance with BS EN 837-1).
3.1.7.22.4 Responsibility for inspection. The contractor shall be responsible for the performance of all inspection requirements specified herein. The contractor shall provide space, personnel, and test equipment for conducting all inspection requirements. All inspection and testing shall be performed at the contractor’s plant or at other facilities acceptable to the Coast Guard.
NOTE
The Coast Guard requires 45-day notice to schedule the QA visit to verify that supplies and services conform to the prescribed requirements.
3.1.7.22.5 Responsibility for compliance. The inspections set forth in this specification shall become part of the contractor’s overall inspection system or quality program. The absence of any inspection requirements in the specification shall not relieve the contractor of the responsibility of assuring that all products or supplies submitted to the Government for acceptance comply with all requirements of the contract. Sampling for quality control purposes does not justify or excuse submission of known defective material (either indicated or actual) nor does it commit the Government to acceptance of defective material.
3.1.7.23 Quality assurance plan. The contractor shall maintain a quality assurance and inspection system during the manufacture of the davit system. During the performance of this contract, the inspection system and manufacturing and testing processes shall be subject to review by the Coast Guard Contracting Officer/Quality Assurance Representative.
3.1.8 Notes
3.1.8.1 Davit information is as follows.
· National Stock Number (NSN) 2030-99-454-8999
· Item name: Dual Point Davit
· Part Number (PN): TW.PIV 5.0B
· Original Equipment Manufacturer (OEM): Welin Lambie LTD
3.1.8.2 Shipping marking is as follows.
· National Stock Number (NSN) 2030-99-454-8999
· Item Name: Boat Davit, Dual Point
· Part Number: TW.PIV 5.0B
· Shipping weight: (as determined)
· Government Contract Number: (as determined)
· Statement: Coast Guard Material Condition “A”, 1 each
· Serial Number: 5558/CURRENT SERIAL NUMBER/ALPHA CHARACTER Example: (5558/15/A (A-Being First Overhaul then B-Second Overhaul)
3.1.8.3 Test plan submittals. The initial Test Plan submitted per paragraph 3.1.7 shall have a unique identification number for the plan.
· For each subsequent test performed, the contractor shall notify the Coast Guard in writing that the same test plan identified in Section 3.1.7 submittal shall be the plan used, referencing the unique identification number referenced above.
· There is no need to modify test plan due to design changes, modifications in configuration, materials, etc. Any deviations from initial Test Plan submitted per Section 3.1.7 above shall require the contractor to provide a new/updated Test Plan Submission and require Coast Guard approval of any new/modified Test Plan prior to deviating from initial Test Plan approved in Section 3.1.7 above.
3.1.8.4 Test plan notification. In accordance with paragraph 3.1.7.1/3.1.7.2 above, the contractor is required to submit their test plan notice 45 days in advance of test date. On occasion the Coast Guard may request a change in test date to accommodate QA representative travel arrangements. Any additional costs incurred by the contractor to accommodate requested test date changes shall be addressed by submitting a CFR to the COR and contracting officer documenting the additional incurred as a result of Coast Guard requests.
3.1.8.5 Warranty support services. Warranty support and all warrantees required (paragraph 3.1.7.21 above) shall be void in the event the davit is subject to parts removal during the storage period or any davit modifications are made by any party other than Welin Lambie during the warranty period. Standard preventative and corrective davit maintenance done by trained Coast Guard personnel in adherence to Welin Lambie maintenance procedures shall not void the warranty.