SUMMARY OF CHANGES.doc

DOC document 37 KB Posted

Attached to
USCG SFLC 87' WPB MTU Component Overhauls & Parts Purchase
Solicitation number
70Z08021R13002B00
Issued by

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY OF CHANGES

For Solicitation Number 70Z080-21-R-13002B00 Several questions were presented during the solicitation period. Below are the questions asked, answers to those questions and change(s), if any, that were made as a result of the question.

Question 1: In regards to FAR 52.222-22 - PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999), The offeror represents that— It has, has not participated in a previous contract or subcontract subject to the Equal Opportunity clause of this solicitation; (Is this ONLY as it relates to the USCG or any other contract?)

Answer: No, the clause applies to any previous contract or subcontract held by the offeror.

Change: No change was required as a result of this question.

Question 2: In regards to FAR 52.222-22 - PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999), It has, has not filed all required compliance reports; and Representations indicating submission of required compliance reports, (Is this our yearly Federal report or is it a specific report?)

Answer: FAR 52.222 covers Equal Employment Opportunity, so this clause is referring to Equal

Employment Opportunity compliance reports.

Change: No change was required as a result of this question.

Question 3: In regards to FAR 52.222-22 - PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999), signed by proposed subcontractors, will be obtained before subcontract awards. (Can you please explain what this means?)

Answer: This part of the clause means that the offeror represents in their proposal that any subcontractors proposed for this acquisition will complete required Equal Employment Opportunity compliance reports before obtaining subcontract awards in regards to the resulting contract for this solicitation.

Change: No change was required as a result of this question.

Question 4: There’s a little issue with the calculations on the MTU 8V396 Parts Price List tab of attachment #4. The inflation rate (Column U line1) is not being calculated properly for all ordering periods. It’s only calculating lines 3,4 &5.

Answer: The offeror can fix the inflation rate calculations in the Attachment 4 spreadsheet.

Change: No change was required as a result of this question.

File details come from the government source that posted it. Updated .