USCG Confidence Question response.docx
DOCX document 13 KB Posted
- Attached to
- Dock-Side (DS): USCGC Confidence WMEC-619 repair
- Solicitation number
- 70Z080-21-Q-P4502600
About this file
This document contains a solicitation for commercial items and questions and answers related to a federal contract opportunity. The United States Coast Guard is seeking quotations to perform dockside repairs to the USCGC Confidence, including providing all labor and materials according to the attached statement of work. Interested vendors must submit quotes by August 16, 2020. The contract period of performance is from November 4, 2020 to December 28, 2020 and work will take place at the pier located in Cape Canaveral, Florida. The solicitation is set aside for small businesses with 1,250 employees or fewer. Questions regarding the solicitation are due by August 6, 2020 and must be submitted to the identified contracting staff.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ Dockside CGC Confidence 70Z080-21-Q-P4502600.docx | DOCX document | |
| CONFIDENCE (WMEC 210A) DS FQ1 SLE 21ER0_BLANK.xls | XLS spreadsheet | |
| RFQ Dockside CGC Confidence 70Z080-21-Q-P4502600.docx | DOCX document | |
| CONFIDENCE SPEC (WMEC 210A) DS FQ1 SLE 21R0.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCG Confidence - DS1 DOCKSIDE FY21 - Solicitation Issued 70Z080-21-Q-P4502600 Q&A on Solicitation 8/6/2020
· Work Item 1: Chill Water System, Clean and Flush, line 3.10 requires temporary berthing for the duty section. How many males and how many females should we account for?
· Work Item 1: Just provide the following as per spec: 3.1.5 The Contractor shall provide temporary cooling for CIC, Radio, IC Gyro, and ECC. The Contractor shall submit a detailed plan for providing this temporary cooling for approval to the COR 72 hours prior to Arrival Conference. No hotel services required.
· Work Item 4, Line 3.3.4 states to repair and coat each tanks interior surface. Can you please clarify what percentage of surface needs to be preserved? Is this a partial preservation based on the results written in a CFR or is this a total preservation?
· Work Item 4: CFR to be submitted post tank inspection.