PROBABILISTIC LIFE PREDICTION OF HULL STRUCTURE CORROSION IN U. S COAST GUARD CUTTERS
Solicitation number
70Z04019QPHL983
Issued by

View the file

Other files

File Type Posted
CLAUSES.docx DOCX document
SOLE_SOURCE_JUSTIFICATION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Probabilistic Life Prediction of Hull Structure Corrosion in U. S. Coast Guard Cutters

February 20, 2019

CONTENTS

1 Introduction 2 Reference Material 3 Scope of Work 4 Deliverables and Schedule 5 Quality Assurance 6 Security Clearance 7 Use of Government Furnished Material 8 Notes

1. INTRODUCTION

The U.S. Coast Guard (USCG) Surface Forces Logistics Center (SFLC) has been involved in a number of special studies to assess the remaining life of structures of USCG Cutters. These efforts required the use of risk assessment and management methods to support engineering, operational and maintenance decisions. The assessment of life expectancy of structures should include as a core set of failure modes the ultimate hull girder collapse initiated by the failure of a stiffened panel, and fatigue and fracture. Variability of corrosion experienced on USCG Cutters is a specific example of factors effecting structural integrity requiring evaluation using a probabilistic risk based evaluation approach. Factors affecting structural integrity such as operational environment and structural response are probabilistic based and require a probabilistic based approach to evaluate statistics based risk associated with various alternatives being considered for design criteria, maintenance and repair.

Corrosion in USCG cutters is a primary degradation mode that accounts for a significant portion of depot budgets and the unavailability of these cutters. Corrosion exhibits great variability spatially and temporally. Although, the "average" corrosion rates in USCG cutters are manageable under current maintenance procedures, a small amount, although unknown percentage, of corrosion, both spatially and temporally, goes undetected and becomes more severe and damaging resulting in increased repair costs and loss of availability.

The objective of this effort is to investigate the spatial statistics of corrosion rates on USCG Cutters for the purpose of predictive model development.

This project will characterize empirically the underlying stochastic processes to better understand the spatial characteristics of corrosion based on data collected by the USCG. Two primary questions will be examined as follows:

1. Internal spatial profiles.

What are the internal spatial profiles of corrosion for cutters based on statistical methods for about 12 cutters using, for example, similarity analysis and hypothesis testing among other methods as needed?

2. Geographic spatial profiles.

What are the corrosion profiles based on geographic locations of about 12 cutters using, for example, statistical methods and the similarity approach by groups, spaces, etc.?

2.0 REFERENCE MATERIAL

The Tasks of this project require information on existing cutters related to corrosion and operational profiles. Specific references are as follows:

· Structural drawings and corrosion data collected

· Other related engineering reports and operational profiles, as needed

3. SCOPE OF WORK

To achieve the objective, the following tasks shall be performed:

Task 1 – Review corrosion data, such as ultrasonic scans and visual observations, and historical data for about 12 cutters provided by the USCG.

Task 2 – Review literature on corrosion rates based on previous USCG studies and the databases of corrosion data provided by the USCG.

Task 3 – Evaluate statistics-based spatial models for corrosion in USCG cutters that would be suitable for prediction. The models that would be examined include statistical methods as applicable, such as descriptive statistics, hypothesis testing, clustering, similarity analysis, and Markov and Bayesian processes as determined from Tasks 1 and 2. This task shall be compatible with the Structural Life of Ship Hulls (SLASH) and also use data captured in MAESTRO-Corrosion Database that is being used by the USCG to evaluate structural reliability models. The ongoing reliability evaluation by the USCG is not specifically part of this task. The contractor shall meet with the USCG to discuss the interim progress on this task. The analysis shall including searching for any measurement errors and if found to correct for them. Both wastage magnitudes and percentages shall be reported.

Task 4 – Examine and analyze internal spatial profiles using statistical methods for about 12 cutters using similarity analysis and hypothesis testing among other methods to infer spatial correlations. The analysis shall include overall corrosion rates, extremes and outliers.

Task 5 – Examine and analyze corrosion profiles based on geographic locations of about 12 cutters using statistical methods and the similarity approach by groups, and spaces based on cutter arrangements.

Task 6 – Recommend approaches for monitoring the corrosion based on prediction modeling. The probability of detection of each approach shall be considered based on similar applications and input by the USCG based on its experiences. Illustrative examples will be developed for prediction and use in corrosion inspection planning although the illustrations will not include the economics associated with the planning but they would be compatible with inspection planning and lifecycle economics.

Task 7 – The contractor shall document the results of Tasks 1 to 6 in a final report prepared in Excel, PowerPoint and Word. The report in Word shall be in a style and length similar to manuscripts submitted to journals. The contractor shall consider using visualization methods to display corrosion locations if determined by the contractor to be feasible and effective. The contractor shall present the findings from the project at the USCG SFLC in Baltimore MD or other location in the Washington Metropolitan area as defined by the U.S. Coast Guard.

4. DELIVERABLES AND SCHEDULE

4.1 DELIVERABLES – The Contractor shall include in the report deliverable of Tasks 1 through 6 to SFLC-ESD-NAME-Nav Arch, as applicable, all photographs, illustrations, charts, graphs, tables, calculations, text, analyses, algorithms, conclusions and recommendations developed completely and exclusively as a part of this project. After receiving SFLC-ESD-NAME-Nav Arch comments, the Contractor shall produce the updated deliverable within four weeks. Each deliverable, both draft and final, shall be transmitted to the SFLC-ESD-NAME-Nav Arch with a documenting cover letter and a copy of the cover letter shall be provided directly to the Contracting Officer.

4.2 Modifications to contractor submittals required by the government reviewers, if judged by the contractor to be outside the scope of this Statement of Work, shall be discussed at a meeting of the government technical and contracting personnel with contractor representatives.

4.3 SCHEDULE – The following schedule of events shall be followed by both the U.S. Coast Guard and the Contractor in carrying out the provisions of this Statement of Work. When either party becomes aware of their inability to conform to this schedule, they shall so advise the other party, in writing, propose an alternate schedule, and provide justification.

Item No.
Description
Quantity
Deliverable Due
1
Tasks 1-7 Draft Report Documentation in an electronic format
1 copy
42 weeks after Contract Award
2
Tasks 1-7 Final Report Documentation in an electronic format
1 copy
4 weeks after Receipt of USCG comments on Draft Report

5. QUALITY ASSURANCE

5.1 The government reserves the right to witness the validation procedures and validation processes of any part of the project development at whatever site such action is taking place.

5.2 The government will review the contents and format of the deliverables in their entirety prior to issuing approval.

6. SECURITY CLEARANCE

6.1 This work is not classified. No security clearance is required.

6.2 Foreign nationals may be used on the project as long as USCG data are not shared with them.

7. USE OF GOVERNMENT FURNISHED MATERIAL

7.1 Government furnished material shall be used for the delivery order only and shall not be used or disseminated for any other purpose.

8. NOTES

8.1 DELIVERY DESTINATION – All items to be delivered under this work statement shall be delivered to the SFLC-ESD-NAME-NAS technical point of contact, Mr. Karl Stambaugh, with a documenting cover letter at the following address:

Commander (SFLC-ESD)
USCG SFLC (SFLC-ESD-NAVARCH)
707 East Ordnance Rd, Suite 410
Baltimore, MD 21226-5000
Attn: Mr. Karl Stambaugh

For each deliverable a copy of the cover letter shall be provided directly to the Contracting Officer at the following address:

Commander (SFLC-CPD-3)
U.S. Coast Guard Surface Forces Logistics Center
707 East Ordnance Rd, Suite 410
Baltimore, MD 21226-5000
Attn: TBD

8.2 RIGHTS IN DATA – All data produced exclusively and completely based on this effort, regardless of form or medium, are considered to be solely the property of the U.S. Coast Guard and shall not be released without the written consent of the U.S. Coast Guard.