45746_SPEC_REV-0_03-15-19_(RB-M_45)_UPDD.pdf

PDF 2 MB Posted

Attached to
USCG STATION (STA) WRIGHTSVILLE BEACH (45746) FY2019 DRY DOCK REPAIRS
Solicitation number
70Z04019QP3098800
Issued by

View the file

Other files

File Type Posted
70Z04019QP45C3800__A00001__SF30.pdf PDF
FIG_1_Example_Planning_Document.pdf PDF
45746____Solicitation.pdf PDF
PAST_PERFORMANCE_QUESTIONNAIRE_(PPQ)_ATTACHMENT_1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCG 45746 (RB-M 45)

SPECIFICATION FOR UNPLANNED DRYDOCK REPAIRS

FY2019

Developed By: Leoncio A Ramirez

(Rev-0, 15 March 2019)

USCG 45746 (RB-M-45) UNPLANNED AVAILABILITY FY2019

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items .............................................................................................. x Principal Characteristics ............................................................................................................................... xi General Requirements WORK ITEM 1: Lazarette Bilge, Preserve WORK ITEM 2: U/W Body, Preserve (100%) WORK ITEM 3: Water Jet Drive, Preserve WORK ITEM 4: Ultrasonic Testing (UT) (100) Shots, Perform WORK ITEM 5: Hull Plating (U/W Body), Inspect WORK ITEM 6: Main Diesel Engine(s) To Auragen Generator(s) And Jet Drive(s), Align WORK ITEM 7: Jet Drive Anodes, Renew WORK ITEM 8: Drydock WORK ITEM 9: Sea Trial Performance, Support, Provide WORK ITEM 10: Water Jet-Inspect, Perform Service iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 45 RB-M 084-002, Rev -, Docking Plan

Coast Guard Drawing 45 RB-M 084-002, Rev –, Docking Plan

Coast Guard Drawing 45 RB-M 110-001, Rev -, Hull Structure

Coast Guard Drawing 45 RB-M 170-002, Rev -, Folding Mast

Coast Guard Drawing 45 RB-M 185-001, Rev A, Auxiliary System Foundations

Coast Guard Drawing 45 RBM 201-001, Rev B, Main Engine Arrangement

Coast Guard Drawing 45 RBM 247-002, Rev -, Water Jet Propulsor Arrangement

Coast Guard Drawing 45 RB-M 247-002, Rev -, Water Jet Propulsor Arrangement

Coast Guard Drawing 45 RB-M 256-002, Rev -, Cooling System Propulsion

Coast Guard Drawing 45 RBM 311-004, Rev -, APU Generator Drive System

Coast Guard Drawing 45 RB-M 631-001, Rev -, Painting Layout

Coast Guard Drawing 45 RB-M 631-001, Rev F, Painting Schedule

Coast Guard Drawing 45 RB-M 633-002, Rev -, Cathodic Protection Sacrificial Anode

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 5737, SWBS 247, Jun 2014, Water Jet – Model FF375S

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 8634 (SFLC Std Spec 8634), 2014, Drydocking

OTHER REFERENCES

1), 2015, Solvent Cleaning

2), 2004, Mechanical Tool Cleaning

45 RB-M Water Jet Disassembly / Assembly Procedures v (Rev-0)

ASTM International (ASTM) D4138, Rev A, 2007 (R 2017), Standard Practices for Measurement of Dry Film Thickness of Protective Coating Systems by Destructive, Cross-Sectioning Means

Rolls-Royce Kamewa Water Jet Assembly Drawing 376 000 49

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 2 (SSPC-SP

The Society for Protective Coatings (SSPC), 2015 (E 2017), Paint Application Specification No. 2 (PA- 2), Procedure for Determining Conformance to Dry Coating Thickness Requirements vi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

6 Y * MDE/ TO GENERATOR

ALIGNMENT TOOL

PN: MMRBM0030 1 ea.

6 Y * MDE/ TO JET DRIVE

ALIGNMENT TOOL

PN: MMRBM0451 1 ea.

6 Y * ENGINE LIFTING BAR PN: MMRBM0956 1 ea.

7 N Anode, Inspection Hatch

(Port & Stbd) NSN: 5342580003759 or PN:

10108231 2 ea. 46.63

7 N Transom Anode NSN: 5342016020658 or PN:

10108230

4 ea. 52.76

7 N Tunnel Anode NSN: 5342016020668 or PN:

10108220

4 ea. 26.88

7 N Impeller Housing/Bucket/Interceptor

Anode

NSN: 5342226078672 or PN:

10107701

10 ea. 24.94

7 N Guide Vane Chamber Anode

NSN: 5342016020669 or PN:

37517411

2 ea. 44.43

7 N Anode, Anode Hatch NSN: 5342251465439 or PN:

10108210

2 ea. 28.20

7 N Screw Connection NSN: 5305016022100 or PN:

93310025H

4 ea. 2.52

7 N Screw Connection NSN: 5305016275854 or PN:

93308025H

14 ea. 1.30

7 N Screw Connection NSN:5305016022105 or PN:

91206020E

8 ea. 0.49

7 N Screw Connection NSN: 5340016243271 or PN:

93308025E

8 ea. 1.00

7 N O-ring NSN: 5331016020670 or PN:

10202639

2 ea. 6.60

7 N Screw Connection NSN: 5305016240905 or PN:

93310016E

8 ea. 1.58

7 N Screw Connection NSN: 5306016309800 or PN:

93312030E

2 ea. 2.42

7 N Screw Connection NSN: 5305016204602 or PN:

91212025E

8 ea. 1.93

7 N O-ring NSN: 5331226078691 or PN:

10202626

2 ea. 9.26

7 N Tube Extension NSN: 4730016210708 or PN:

37610802

2 ea. 148.88

7 N Tube Clamp NSN: 4730016200951 or PN:

10217881

2 ea. 20.05

7 N Screw Connection NSN: 5305016022101 or PN:

93310030H

2 ea. 2.08 vii (Rev-0)

7 N Connecting Cable NSN: 6145016203663 or PN:

10234301

4 ea. 21.23

7 N Screw Connection NSN: 5305016176732 or PN:

93306016E

8 ea. 0.44

7 N Anode, Corrosion NSN: 5340015899440 or PN:

51125

2 ea. 32.56

7 N Anode, Corrosion NSN: 5340015899425 or PN:

89287

2 ea. 12.34

10 N Stainless Steel Ball Joint NSN: 3040016152117 or PN:

59915K483

10 ea. 12.26

10 N Stainless Steel Threaded Rod

NSN: 5306016152224 or PN:

93250A140

1 ea. 10.67

10 N Bearing Bushing NSN: 3120014555212 or PN:

10106911

4 ea. 9.80

10 N Bearing Bushing NSN: 3120580006242 or PN:

36M05101

4 ea. 49.00

10 N **Socket Head Screw NSN: 5305016171580 or PN:

91210050

16 ea. 2.71

10 N **Bolt Kit NSN: 2815016171688 or PN:

93112085A

2 ea. 15.64

10 N **Key NSN: 5315016166360 or PN:

10100824

3 ea. 28.14

10 N Seal NSN: 5330580006238 or PN:

10118902

2 ea. 4.35

10 N Bushing NSN: 3120580006239 or PN:

10105511

2 ea. 48.19

10 N Bearing Bushing NSN: 3120014555272 or PN:

10105111

4 ea. 35.33

10 N **Bolt Kit NSN: 2815016171974 or PN:

93112080F

2 ea. 6.13

10 N **Bolt Kit NSN: 5340016167191 or PN:

93112065K

12 ea. 13.07

10 N Bearing Unit NSN: 3110016166342 or PN:

37506201

2 ea. 614.35

10 N Bushing NSN: 3120580006240 or PN:

10106011

4 ea. 47.21

10 N **Set Screw NSN: 5305016020672 or PN:

91608012

6 ea. 0.58

10 N **Bolt Kit NSN: 5305016173161 or PN:

93112090K

10 ea. 12.56

10 N O-ring NSN: 5331580006241 or PN:

10202606

6 ea. 14.56

10 N **Mechanical Sealing NSN: 4320580006403 or PN:

10203870

2 ea. 1052.97

10 N Bolt Kit NSN: 5306016164058 or PN:

93310030E

6 ea. 1.92

10 N O-ring NSN: 5331016020679 or PN:

10202631

2 ea. 4.39

10 N O-ring NSN: 5331016020680 or PN: 4 ea. 15.15 viii (Rev-0)

10202625 10 N Sealing NSN: 5365016233174 or PN:

41018801 2 ea. 8.87

10 N O-ring NSN: 5331016200368 or PN:

10202611

2 ea. 5.21

10 N Seal Lip NSN: 4730016204613 or PN:

10202590

4 ea. 39.47

10 N Sealing NSN: 5330016163186 or PN:

45002010

2 ea. 535.93

10 N **Lock Nut NSN: 5310016162982 or PN:

10202908

2 ea. 16.63

10 N Lock Washer NSN: 5310016232756 or PN:

10203008

2 ea. 2.34

10 N **Ring Nut NSN: 5310016164016 or PN:

10202912

2 ea. 32.60

10 N Seal NSN: 5330016243735 or PN:

10202540R

6 ea. 19.68

10 N **Screw NSN: 5305016162955 or PN:

93305025

8 ea. 0.28

10 N **Washer NSN: 5310016162966 or PN:

912505

8 ea. 0.06

10 N Gasket NSN: 5330016232867 or PN:

37527805

2 ea. 63.43

10 N Bushing NSN: 5365016202680 or PN:

10108416

8 ea. 15.91

10 N **Bolt Kit NSN: 5305016242899 or PN:

93110060A

4 ea. 12.91

10 N **Bolt Kit NSN: 5305016242922 or PN:

99110040G

14 ea. 6.60

10 N Bushing NSN: 3120014555268 or PN:

10106902

8 ea. 7.90

10 N Gasket NSN: 5330016163014 or PN:

10108901

2 ea. 5.65

10 N **Bolt Kit NSN: 5305016231019 or PN:

93110090A

4 ea. 5.05

10 N Lock Washer NSN: 5310016232699 or PN:

10203012

2 ea. 5.62

10 N O-ring NSN: 5331016242120 or PN:

10202603

2 ea. 3.89

10 N **Screw, Countersunk NSN: 5305016309734 or PN:

99106016

8 ea. 5.65

10 N Seal/Gasket NSN: 1040016337691 or PN:

45011611

2 ea. 57.64

10 N Woodruff Key NSN: 5315016172999 or PN:

10100823

2 ea. 19.09

10 N Washer, Sealing NSN: 5310016452084 or PN:

8755000050

24 ea. 0.06

10 N Screw, Connection NSN: 5305016476396 or PN:

91212045L

8 ea. 6.45 ix (Rev-0)

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter x (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item

Title

1 Lazarette Bilge, Preserve

2 U/W Body, Preserve (100%)

3 Water Jet Drive, Preserve

4 Ultrasonic Testing (UT) (100) Shots, Perform

6 Main Diesel Engine(s) To Auragen Generator(s) And Jet Drive(s), Align

10 Water Jet-Inspect, Perform Service xi (Rev-0)

PRINCIPAL CHARACTERISTICS

45' RB-M

PHYSICAL

Length overall 44 feet, 10.5 inches Unfixed height 20 feet 9 inches Beam, maximum 14 feet, 7.75 inches Full load draft 3 feet, 4 inches Full load displacement 36,500 pounds Max sustained speed 42.5 knots Range 250 nautical miles at 30 knots Mission limits 8 foot seas / 30 knot winds Survivability limits 12 foot seas / 50 knot winds

HULL

Hull manufacturer Marinette Marine Corp.

5086 (GRADE) Aluminum Hin- 2009

MACHINERY

Type 6, cylinder diesel engine Number of units 2, MTU's 60 series 825 hp Propulsion type 2, Rolls-royce water-jet

TANKS

1 (Rev-0)

00000_0618_FLT

REC_00000_FLT_Boats @ CG Facility (0914)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting boat repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 Contractor operated (non USCG) facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public

3 (Rev-0) notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Hazardous Waste Manifest. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.7 Facilities Response Plans. Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy.

3.6.1 Coast Guard facility usage and provisions. The Contractor shall be aware of the following:

3.6.1.1 Coast Guard personnel will haul and block the boat on a Coast Guard installation; consequently, the Contractor shall not include the cost of lifting or re-floating the vessel in the bid price estimates

3.6.1.2 All work described herein is intended to be accomplished at this location.

3.6.1.3 The COR will submit to the Contractor a copy of the “Coast Guard Facility Survey”/”Landlord Survey” which contains utilities and/or equipment that the Coast Guard Facility will make available for use by the

4 (Rev-0)

Contractor.

3.6.2 Contractor equipment. The Contractor shall make arrangements to provide all other necessary equipment to accomplish the work described in this specification package including (as applicable) but not limited to generators, compressors, welding equipment, power tools, consumables, and storage containers.

3.6.2.1 The Contractor shall be responsible for storing own equipment.

3.6.2.2 Prior to setting up equipment and/or storage containers for long-term duration, the Contractor shall obtain approval from the COR at least 48 hours prior to placing the equipment in order to avoid conflict with other base activities.

3.6.3 Sewage Facilities. If the Coast Guard facility opts to provide sewage facilities (as listed on the Landlord Survey) for use by the Contractor, the Contractor shall supply sanitary supplies such as toilet paper, paper towels, soap, etc. for use by contract personnel. Use of Government toilet paper, and other sanitary supplies shall not be authorized and the additional caveats apply as well.

3.6.3.1 The Contractor shall ensure the sanitary facilities (bathrooms) are left in a clean and neat condition as found.

3.6.3.2 The Contractor is NOT authorized to use any shower facilities which may or may not be located in the same room as the toilet facilities.

3.6.3.3 The Contractor shall adhere to any special requirements or regulations listed in the comments section of the Landlord survey forms, provided at the end of this document.

3.6.4 Coast Guard turn-over preparation. The Contractor shall be aware that, upon arrival, after haul out, and prior to departing the Contractor’s facility, the Coast Guard crew shall be allowed to accomplish various tasks in preparation for the turn-over of the boat to the Contractor. The following conditions apply to this paragraph:

3.6.4.1 The Coast Guard requires a maximum of three days at the beginning of the contract, and three days at the end to accomplish various tasks.

3.6.4.2 The Contractor may commence/continue work during these time frames.

3.6.4.3 Coast Guard personnel will disconnect the Detroit Diesel Electronic Control (DDEC) System and any other electronic equipment, as required to avoid damage to systems arising from hotwork on the vessel during the availability.

3.6.4.4 Coast Guard personnel will remove the transducers after initial haul-out and reinstall prior to re-floating the vessel.

3.6.4.5 The Unit will contact the servicing ESD or ESU to setup removal/installation of the transducer if Unit personnel are unable to accomplish this task.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 Change to SFLC Std Spec 0000, paragraph 1.3. ‘Acronyms and term definitions’, page 5, “PCL (Paint

5 (Rev-0)

Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.1.1 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

3.7.2 Change to Std Spec 5000, paragraph D2.2.1.1 bullet, "For running rigging, furnish class 6x37, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope," to "For running rigging, furnish class 6x36, uncoated, independent wire rope core (IWRC), right regular lay (RRL) wire rope or Dyform-18, rotation resistant wire rope."

3.7.2.1 Change to Std Spec 5000, page D-2, Table D-1 title from "DYFORM-18, 6X19 AND 6X37 IWRC RRL," to " DYFORM-18, 6X19 AND 6X36 IWRC RRL"

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

8 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

9 (Rev-0)

TIME

10 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

11 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

12 (Rev-0)

13 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

14 (Rev-0)

S19_110_11021_AKP_0418_45RBM_45746

WORK ITEM 1: Lazarette Bilge, Preserve

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve the bilge surfaces for the locations and frames identified in Table 1.

TABLE 1 - BILGES

LOCATION SQFT

Under the port and starboard strainers extending from the transom forward to Bulkhead 2, from the weld seam on the outboard side of the jet drive tunnel to the 1st longitudinal outboard of the Miller Leman strainer mounting girder. Refer to Figure 1.

Port/ starboard of the keel extending from the transom forward to Bulkhead 2, from the keel plate outboard to the jet drive tunnel weld seam on the port and starboard sides. Refer to Figure 2.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 45 RB-M 185-001, Rev A, Auxiliary System Foundations

Coast Guard Drawing 45 RB-M 256-002, Rev -, Cooling System Propulsion

Coast Guard Drawing 45 RB-M 631-001, Rev F, Painting Schedule

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 2 (SSPC-SP

2), 2004, Mechanical Tool Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP

15 (Rev-0)

1), 2015, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.3 Visual inspection.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

Piping

Hoses

Strainers

Deck grating

3.2 Preservation. The Contractor shall preserve the bilge surfaces listed in Table 1 in accordance with the references listed in section 2.

3.3 Visual inspection. The Contractor shall visually inspect this designated bilge surfaces for weld and hull damage. Submit a CIR.

3.4 Surface preservation. The Contractor shall clean, prepare, and coat the designated bilge surfaces, including all adjacent structural members, using the system specified for “Bulkheads and Overheads, and Uninsulated Aluminum”, in SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems). Select the following:

Option I system.

Top /finish coat color: Light gray (26622)

WARNING

Abrasive-blasting is not permissible in machinery spaces.

3.4.1 Remove and dispose of all bilge contaminants from the identified surfaces in accordance with all federal, state, and local regulations.

16 (Rev-0)

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

3.5 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).

4. NOTES

This section is not applicable to this work item.

FIGURE 1. BILGE AREA UNDER STRAINERS

17 (Rev-0)

FIGURE 2. BILGE AREA BETWEEN WATER JET TUNNELS

18 (Rev-0)

63130_AKP_0318_45RBM

WORK ITEM 2: U/W Body, Preserve (100%)

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve 100% of the U/W body surface.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 45 RB-M 631-001, Rev -, Painting Layout

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.2.4 Clean and inspect.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against

19 (Rev-0) contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Protective measures - preservation. The Contractor shall protect all non-affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

Specific equipment/components include, but are not limited to:

Fathometer transducer surfaces

Sea valve openings

Water jet propulsion units

Zinc anodes (unless anodes are being renewed)

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Water jet intake grating.

Water jet propulsion unit

3.2 Preservation requirements. The Contractor shall prepare and preserve 100% of the U/W body in accordance with Coast Guard Drawing 45 RB-M 631-001 and SFLC Std Spec 6310.

3.2.1 Fleeting. The Contractor shall fleet the vessel as necessary to preserve the entire U/W body.

3.2.2 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.

3.2.3 Surface preparation. The Contractor shall prepare the surface in accordance with the surface preparation method stated in Table I- Paint Schedule 45 RB-M and SFLC Std Spec 6310.

3.2.4 Clean and inspect. Upon completion of surface preparation and prior to coating application the Contractor shall clean and inspect the prepared U/W body aluminum substrate. Submit A CIR.

3.2.4.1 The Contractor shall perform a visual inspection of the prepared U/W body aluminum substrate.

3.2.4.2 The Contractor shall solvent clean the prepared surfaces in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations.

TABLE 1 - PAINT SCHEDULE 45 RB-M (REF CGDWG 45 RB-M 631-001 PAINTING

LAYOUT)

EXTERIOR

SURFACES TO

BE

PRESERVED

SURFACE PREPARATION COATING SYSTEM DFT

(MILS)

COLOR

UNDERWATER

BODY

(SALTWATER

NEAR WHITE BLAST PER

SSPC-SP10 WITH CLEAN, FINE

ALUMINUM OXIDE, GARNET

1) SHERWIN WILLIAMS

SEAGUARD 5000 HS

5.0-6.0

Red

20 (Rev-0)

BOATS) OR EQUIVALENT INERT

MATERIAL CONFORMING TO

CID A-A-59316, TYPE I & IV

WITH A 1.5-2.5 MIL ANCHOR

PROFILE

2) SHERWIN WILLIAMS

SEAGUARD 5000 HS

3) *SHERWIN WILLIAMS

SEAVOYAGE COPPER FREE

AF – (MUST BE APPLIED

WHILE EPOXY IS STILL

TACKY)

4) *SHERWIN WILLIAMS

SEAVOYAGE COPPER FREE

AF

5) *SHERWIN WILLIAMS

SEAVOYAGE COPPER FREE

AF

Grey

Black

* Do not apply AF coating to anode mounting surfaces.

3.2.5 Preservation. The Contractor shall preserve the U/W hull using the coating system in Table 1- Paint Schedule 45 RB-M and in accordance with SFLC Std Spec 6310.

3.2.5.1 The Contractor shall ensure that the following anode fastener studs are clean and free of paint:

Transom Anodes (2)

Sea Chest Anodes (2)

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

3.3 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

4. NOTES

4.1 Definitions.

4.1.1 U/W Body. The underwater body is defined as the aluminum hull surfaces from the bottom of the keel to the waterline, as shown on Coast Guard Drawing 45 RB-M 631-001.

4.2 Related work. Water Jet Preservation, Anode Renewal.

21 (Rev-0)

63100_AKP_0318_45RBM

WORK ITEM 3: Water Jet Drive, Preserve

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to preserve the port and starboard water jet-drive units.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Technical Publication (TP) 5737, SWBS 247, Jun 2014, Water Jet – Model FF375S

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.2.4 Clean and Inspect

3.1.2 Tech Rep.

Not applicable.

22 (Rev-0)

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Protective measures - preservation. The Contractor shall protect all non-affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

NOTE

Coast Guard personnel will operate all vessel machinery and equipment.

3.1.5 Operational test - initial. Prior to commencement of work, the Contractor shall witness Coast Guard Personnel perform an initial operational test of the port and starboard water jet propulsion units to demonstrate existing operational condition. Submit a CFR.

3.2 Preservation. The Contractor shall preserve the port and starboard water jet-drive units in accordance with Table 1 - Paint Schedule External Water Jet Components and Table 2- Paint Schedule Internal Water Jet components.

3.2.1 Pre-surface preparation wash. Accomplish low-pressure (less than 5,000 psi) fresh water wash of all affected surfaces, to remove soluble chlorides and other surface contaminants. Refer to SSPC-SP 1, for guidance.

3.2.2 Surface preparation. The Contractor shall prepare the external surfaces in accordance with the surface preparation method stated in Table 1, and the internal surfaces in accordance with the surface preparation method stated in Table 2 and SFLC Std Spec 6310.

3.2.3 Clean and inspect. Upon completion of surface preparation and prior to coating application, the Contractor shall clean and visually inspect the prepared port and starboard water jet-drive units’ aluminum substrate. Submit a CIR.

3.2.4 Solvent clean the prepared surfaces in accordance with SSPC-SP 1. Capture, contain, and dispose of all wastes from solvent cleaning, in accordance with all Federal, state and local regulations.

TABLE 1- PAINT SCHEDULE EXTERNALWATER JET COMPONENTS

EXTERIOR

SURFACES TO

BE

PRESERVED

SURFACE PREPARATION COATING SYSTEM DFT

(MILS)

COLOR

Water jet drive (saltwater boats)

Near white blast per SSPC-SP10 with clean, fine aluminum oxide, garnet or equivalent inert material conforming to CID A-A-59316, Type I & IV with a 1.5-2.5 mil anchor profile

1) Seaguard 5000 HS

2) Seaguard 5000 HS

3) *Seavoyage Copper Free AF

23 (Rev-0)

4) *Seavoyage Copper Free AF (must be applied while epoxy is still tacky)

5) *Seavoyage Copper Free AF

* Do not apply AF coating to anode mounting surfaces.

TABLE 2- PAINT SCHEDULE INTERNAL WATER JET COMPONENTS

INTERNAL

SURFACES TO

BE

PRESERVED

SURFACE PREPARATION COATING SYSTEM DFT

(MILS)

COLOR

Water jet drive-intake tunnel and intake grid (saltwater boats)

Near white blast per SSPC-SP10 with clean, fine aluminum oxide, garnet or equivalent inert material conforming to CID A-A-59316, Type I & IV with a 1.5-2.5 mil anchor profile

1) Intershield 803

2) Intershield 803

3) Intershield 803

4) Seaguard 5000 HS

5) Seavoyage Copper Free AF (must be applied while epoxy is still tacky)

5.0

5.0

5.0

4.0

Red

3.2.5 Preservation. The Contractor shall preserve the external surfaces in accordance with the surface preservation method stated in Table 1, and the internal surfaces in accordance with the surface preservation method stated in Table 2 and SFLC Std Spec 6310.

3.2.5.1 The Contractor shall ensure that the following anode threaded fastener holes are clean and free of paint:

Water Jet Transom

Guide Vane Chamber

Impeller

Housing

Reverse Bucket

Inspection Port Anodes

NOTE

Surfaces being preserved are considered “critical-coated surfaces”.

3.3 In-process quality control measures. The Contractor shall abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces).

Coast Guard personnel will operate all vessel machinery and equipment.

24 (Rev-0)

4.1 Related work. Complete the following work items in conjunction with this work item:

Water Jet, Inspect and Perform Service

Anode, Renew

U/W Body Preservation, 100%

25 (Rev-0)

10000_AKP_0418_45RBM

WORK ITEM 4: Ultrasonic Testing (UT) (100) Shots, Perform

1. Scope

1.1 Intent. This work item describes the requirements for the Contractor to take 100 UT shots.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor shall submit a CIR for the inspections listed in the following paragraph(s):

3.3 Reporting

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures - general. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces in the vicinity of the work area against contamination during the performance of work. Upon completion of work, the

26 (Rev-0)

Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 UT measurement. The Contractor shall perform a total of 100 UT measurements in accordance with SFLC Std Spec 0000 and SFLC Std Spec 0740.

3.2.1 Standard measurements. The Contractor shall take 70 standard thickness measurements for the designated locations numbered 1 thru 70 between the boot top and keel, (Refer to Figure 1 and Figure 2).

3.2.1.1 The Contractor shall record each measured metal thickness in the Standard Underwater (U/W) Body Test Results Report, (Refer to Table 1 and Table 2).

3.2.1.2 The Contractor shall calculate each percent loss.

3.2.1.3 The Contractor shall record each percent loss in the Standard U/W Body Test Results Report.

3.2.2 Additional measurements. The Contractor shall take 30 additional thickness measurements at locations designated by the Coast Guard inspector and numbered 1A through 30A between the boot top and keel, (Refer to Figure 1 and Figure 2).

3.2.2.1 The Contractor shall record each measured metal thickness in the Additional U/W Body Test Results Report, (Refer to Table 3).

3.2.2.2 The Contractor shall calculate each percent loss.

3.2.2.3 The Contractor shall record each percent loss in the Additional U/W Body Test Results Report.

3.2.3 Minimum thickness. The Contractor shall record the minimum thickness found for each designated hull section. (A, B, and C) in the Underwater Hull Body Minimum Thickness Test Results Report, (Refer to Table 4).

3.3 Reporting. The Contractor shall submit a CIR to include a marked up drawing of Figure 1 and 2 and the completed tables.

4.1 Coast Guard Personnel. The Coast Guard inspector will witness all readings.

27 (Rev-0)

FIGURE 1. BOTTOM SHELL PLATING EXPANDED

28 (Rev-0)

FIGURE 2. STERN SECTION SHELL PLATING

TABLE 1 - STANDARD U/W BODY TEST RESULTS REPORT

DATE: ____________________________

*CALCULATING PERCENT LOSS = 100- (UT READING / DESIGN THICKNESS X 100)

29 (Rev-0)

30 (Rev-0)

TABLE 2 - STANDARD U/W BODY TEST RESULTS REPORT (STERN)

*CALCULATING PERCENT LOSS = 100- (UT READING / DESIGN THICKNESS X 100)

LOCATION

AREA

DESIGN

THICKNESS

MINIMUM

ALLOWABLE THICKNESS

U…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.