28 Feb 2018
Sol No. 70Z04019QP3039700
A00001 (cont’d)
RFQ Number: 70Z04019QP3039700
SOLICITATION
SECTION:
SPECIFICATION PARA
NO.
DEFINITE/OPTION
AL ITEM NO.
D-028 PARA
NO.
3.6 &
3.6.2.1
TITLE: Standard Hoses, Renew
QUESTION 1:
Paragraph 3.6.2.1 allows contractor to reuse existing hose fittings if they are serviceable. If existing hose fittings are not serviceable and are required to be replaced will cost of new hose fittings be authorized via a change request?
If not, please advise on the type, size, and quantity of hose fittings that are to be included in pricing.
Answer 1: Yes, the cost of new fittings will be authorized via CFR/CR
SOLICITATION SECTION: SPECIFICATION PARA
DEFINITE/OPTIONAL ITEM
D-026 PARA
NO.
1.1, 3.3, 3.4
TITLE: Fuel Root Valves, Renew
QUESTION 2:
Wording of paragraphs 1.1, 3.3, and 3.4 are in conflict.
Is the intent of the government that new valves be installed or that valve internals be re-newed?
Answer 2:
The intent is to renew all VALVES. 1.1, 3.3 and 3.4 should read:
1.1 Intent. This work item describes the requirements for the Contractor to renew the designated fuel valves in Table 1.
3.3 Renewal. The Contractor shall renew all designated valves with commercial-standard type valve, conforming to the applicable standard listed in Table 2 (Valve Standards). New valves shall be equivalent (including identical material) to the valves being renewed.
3.4 Valve installation. Upon completion of all authorized work, the Contractor shall accomplish the following:
• Remove and dispose of all blank flanges and associated gaskets, or caps.
• Install all new valves with new gaskets. Renew all gaskets with spiral wound metallic gaskets conforming to MIL-G-24716A.
• Renew all valve label plates.
• Renew all bolting hardware.
• Prepare and touch-up coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, Appendix B (Cutter and Boat Interior Painting Systems).
“Apologies for the confusion”
D-033 PARA
NO.
3.5
TITLE:
Compressed Air Receivers and System Valves (All), Clean, Inspect, Hydro and Lift
QUESTION 3:
Work item 33, paragraph 3.5 , 3.6, 3.8 and subparagraphs include reference to valves and valve repairs.
There are no valves identified to be repaired in the work item.
Please confirm that there are no valves required to be repaired.
Answer #3: There are no identified valves to be repaired or renewed yet. When the valves get tested and inspected, if a valve fails or is found in a very bad condition, then a CFR / CR will be submitted for repair or replacement of the valve, and funding will be added for this.
* Please don’t get confused with 3.4 Contractor’s option for valve renewal, this only applies if the contractor does not want to test the valves and elects to replace them right away. This would be at no additional cost to the Government.*
D-024 PARA
NO.
1.1
TITLE: Keel Coolers, Clean, Inspect and Hydro
QUESTION 4:
Work item identifies keel coolers as Walter Machine Company units in paragraph 1.1 and also in the reference drawings.
Please confirm that the existing keel coolers are Walter Machine Company units which are shown in reference drawings 233-051 and 502-051.
If units are not correctly identifed, please provide correct identification and reference drawings.
Answer #4: Yes, the keel coolers are manufactured by WALTER MACHINE Co. Please see attachment.