REPAIR & MAINTENANCE OF TRAINING VESSEL
Solicitation number
70Z039-20-Q-PCC168
Issued by

View the file

Other files

File Type Posted
(2) LTR SAM (ref. only).docx DOCX document
(3) WAGE GRADE DET (07-16-2019).pdf PDF
SF-1449.pdf PDF
ADDENDUM (rev 03 13 2017).doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. Coast Guard Academy Dry Dock for T/V HONOR

USCG Academy

SCOPE OF WORK

FOR

TRAINING VESSEL HONOR DRY DOCK

U.S. COAST GUARD ACADEMY

15 MOHEGAN AVE

NEW LONDON, CT 06320

JANUARY, 2020

65 Foot USCG Academy T-Boat

Background

There are three single screw 65 foot steel vessels used for ship handling training at the USCG Academy in New London, CT. The vessels were built in 1953 by Higgins Ship Building in New Orleans and referred to as T-boats. The goal of the ship handling program is to expose cadets to the man overboard (MOB), anchoring, emergency steering and mooring and unmooring evolutions onboard the 65’ T-Boat.

Each student is introduced to the principles of single screw ship handling, shipboard engineering and deck seamanship while continuing to grow and develop as leaders of peer leaders. The program culminates with a final exercise during which the students plan, brief and execute an inland/coastal transit of the Thames River and Fisher’s Island Sound. During the exercise the students perform a variety of routine ship handling and seamanship evolutions while also responding to limited shipboard emergencies.

USCG Academy T-boat Characteristics:

1. HULL

Length65 ft. 6 ¾ in. (20m)
Beam (max)17 ft. 8 in. (5.4m)
Depth (molded)8 ft. 9 7/8 in. (2.7m)
Displacement:Light66 l/t
Loaded95 l/t
Draft(light)Forward4 ft. 10 in. (1.47 m)
Aft7 ft. (2.13m)
Draft(loaded)Forward5 ft. 10 in. (1.8 m)
Aft6 ft. 10 in. (2.1m)
Freeboard (mean)Light3 ft. 7/8 in. (.94 m)
Loaded2 ft. 7 7/8 in. (.8m)

2. PROPELLER

Number of blades3
Diameter43”
Pitch of Wheel31.862
RotationRight

PART 1 GENERAL

Scope of Work

Provide supervision, labor, materials, testing and the dry docking for the USCG Academy training vessel HONOR. Work is to include the following:

1. Perform routine dry docking

2. Provide ultrasonic Testing (UT) (100) shots

· Prior to testing discuss with the USCGA COTR the location of shots along with the testing, sand blasting and priming sequence.

· Provide printed report of all UT measurements.

· The report results shall include the location of each test point, original metal thickness, measured metal thickness and percent of deterioration.

· Compare report with the USCGA supplied 2013 report

· Provide a condition found report (CFR)

3. Remove, inspect and reinstall propeller

· The Contractor shall visually inspect the propeller for any damage, cracks, and other defects.

· Provide a condition found report (CFR)

4. Remove, inspect and reinstall rudder

· The Contractor shall clean and visually inspect all rudder components, including but not limited to rudder stock/shaft and blade surfaces, bearings, bearing housing, seals, packing gland, emergency tiller, key and keyways, and grease passages, for signs of excessive wear and other mechanical defects such as nicks, cracks, and corrosion, as applicable.

· Renew tiller pins and bushings, all fasteners, gaskets, o-rings, and seals

· Renew packing in rudder stock glands

· Renew seals in the bearing housings

· Repack the bearings with grease prior to reinstalling.

· Renew rudder packing glands

· Alignment – Upon completion of reinstallation, check the rudder alignment with pilot house rudder angle indicator. Ensure the alignment adjusted to within plus or minus ½ degree

5. Renew water lubricated shaft bearings

· Remove shaft

· Remove existing water-lubricated bearing

· Fit, align and install Contractor-furnished water-lubricated bearing

6. Visually inspect raw water sea valves, sea strainers and raw water piping to the MDE

· The Contractor shall visually inspect the sea valves, strainers and raw water piping for any damage, cracks, and other defects.

· Provide a condition found report (CFR)

7. Sandblast, prime and paint underwater body

· Remove all remnants of AF coating by water-jetting or sandblasting

· Apply primer coat

· Apply two coats of copper ablative antifouling paint

8. Sandblast, prime and paint freeboard

· Etch, measure and photograph existing location of USCG stripe.

· Remove all remnants of AF coating by water-jetting or sandblasting.

· Apply one coat of primer at 5-6 mils to match existing color scheme.

· Polysiloxane Black - Hull

· Polysiloxane White - Draft marks and stripe

· Polysiloxane Blue - Stripe

· Polyziloxane Orange – Stripe

9. Prep, prime and paint superstructure

· Prepare entire superstructure for painting

· Equipment/components to be protected include, but not limited to – Antennas, cable runs, navigation lights, windows, door handles, deck surfaces and electrical cables.

· Prime spots as needed

· Polysiloxane White – Superstructure and spray shield on bridge (inboard and outboard)

· Polysiloxane Black – Cleats, top of stack, vents on stack, ladders and name plates

· Polysiloxane Spar – Bitts and towing structure

10. Prep, prime and spot paint exposed areas on deck

· Apply a nonskid broadcast grit to areas with existing nonskid

· Polysiloxane Gray

11. Prep, Prime and Paint anchor and first 4 anchor chain markings (shots)

· Polysiloxane Black – Anchor

· Repaint first 4 anchor chain shots using USCGA supplied color code pattern

· Total chain links to be repainted – 24

· Paint colors – Red, white and blue

· Determine if shorepower is necessary to lower and raise anchor for painting

· If so, provide 50A/250V service

· USCGA staff will raise/lower the anchor and remove/replace chain if shorepower is determined to be necessary for this project

12. Renew zincs

13. Replace 4 USCGA supplied engine mounts

· Support engine and reduction gear

· Mark and drill new bolt holes in engine beds

· Install USCGA supplied engine mounts

· Align engine

14. Perform sea trial to ensure engine is properly aligned

Location

Due to the limited abilities of the T/V HONOR can only transit in the following waters:

1. Thames River, New London CT

2. Mystic River, Mystic CT

3. Fishers Island Sound

4. Western Long Island Sound

5. New Haven harbor

6. Block Island Sound (Out to 3 nautical miles)

7. Providence River, Providence RI

8. Narragansett Bay

9. Rhode Island Sound

10. Buzzards Bay

The dry docking contract can only be considered for contractors who have dry docking facilities accessible by the above mentioned waters.

The dry docking faculty awarded the contract must have the ability to haul a vessel with the following characteristics:

1. Molded Beam (extreme)17' 8"
2. Length Overall65' 4"
3. Mast Height (From waterline)20'
4. Design Draft7' (forward and aft)
5. Molded displacement98 long tons

The USCG Academy will deliver T/V HONOR to the contractor who is awarded the contract.

Submittals

RFQ should include, at a minimum:

A. Price: Prices must include total costs including supervisor, labor and materials to assemble, test, maintain and disassemble all required systems.

B. Project Schedule: Provide a project schedule to include items listed in PART 1 GENERAL, Scope of Work of this document.

C. Product Data: Provide manufactures product data including literature, catalog sheets, specifications and installation instructions for all components and accessories.

Performance Period

T/V HONOR will be available for work from March 1st 2020 thru May 1st 2020.

Material Handling

Deliver all materials to job in original containers or packaging. Storage of materials and equipment can be coordinated with the project manager.

Statement of Work SOW - 7/7 image1.png