Responses to Questions (1).docx
DOCX document 53 KB Posted
- Attached to
- Repair of Nose and Main Wheel
- Solicitation number
- 70Z03820QB2000170
View the file
Other files
| File | Type | Posted |
|---|---|---|
| WD TX.pdf | ||
| Repair Terms and Conditions 70Z03820QB2000170.pdf | ||
| WD Dallas TX.pdf | ||
| WD FL.pdf | ||
| WD OH.pdf | ||
| SOW 70Z03820QB2000170.pdf | ||
| Requirements 70Z03820QB2000170.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
70Z03820QB2000170
Responses to Questions (1) Answers provided 24 June 2020
This document provides United States Coast Guard (USCG) responses for questions that have been asked regarding solicitation 70Z03820QB2000170. Question numbers are provided simply as a reference and in no way infer a prioritization of the questions.
| Number |
| Question |
| USCG Response |
| 1 |
| In the past I have worked on NAVY programs where the SOW "statement of work" later became the Contract is that process the same at the USCG? If so do you allow for a redline and comment of the SOW if there is something that might require clarification or remedy. |
| The Statement of Work (SOW) as well as the Terms and Conditions will be part of the awarded Purchase Order. If any exceptions are taken on the SOW or Terms and Conditions, it should be noted with the submitted quote. The Contracting Officer and our Engineer Division will review and address the exceptions before the Purchase Order is awarded. |
| 2 |
| Same for the T&C's if there is something that might require discussion can we offer a redline and comment draft Along with the SOW and T&C's there questions embedded on the contractors ability to perfom the maintenance services, what format would you like those answers. Simple word document , PP or other? |
Yes as stated in response one.
Stated on page 2 of the Terms and Conditions if the offer is an Original Equipment Manufacturer authorized repair facility and has not previously been approved by the United States Coast Guard to complete the repairs, they must provide proof with their quote (such as a letter from the OEM) stating that the offer is approved to complete the repairs. The detailed repair explanation can be formatted in a word document, Power Point or scanned PDF file submitted with the quote. A simple statement of capabilities will not suffice per solicitation 70Z03820QB2000170 Terms and Conditions page 1 and 2 of Technical Acceptability.