Fire_Suppression_Inspection_SOW.doc

DOC document 103 KB Posted

Attached to
ANNUAL FIRE ALARM INSPECTION Federal contract opportunity
Solicitation number
70Z03119QLBA26000
Issued by
Department of Homeland Security US Coast Guard

About this file

Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to ANNUAL FIRE ALARM INSPECTION, newest first.
File Type Posted
Request_for_Information_(RFI).PDF PDF
FAR_Clauses.doc DOC document
Wages.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK FOR ANNUAL FIRE SUPPRESSION SYSTEM INSPECTIONS AND MONITIORING

Department of Homeland Security

United States Coast Guard

Scope of Work For

Annual Fire Suppression System Inspections/ Monitoring

PSN:

At

U.S. Coast Guard

AIR STATION SAN FRANCISCO

SAN FRANCISCO, CA

19 Feb 2018 Commanding Officer

United States Coast Guard

Air Station San Francisco San Francisco, CA 94128 Submitted: LT Anders Manley

Asst Facilities Engineering Officer

TABLE OF CONTENTS

Section
Title
Page
1
Description of Work
3
2
Submittals and Outcome
3
3
Project Performance Timeline
3
4
Location
4
5
Point of Contact
4
6
Coordination
4
7
Contractor Use of Premises
4
8
Security
4
9
Quality
4
10
Safety
5

1 DESCRIPTION OF WORK

1.1 Problem: Air Station San Francisco currently employs a complex Johnson Controls fire suppression system in its hangar. This system requires four annual inspections, three quarterly inspections and one semiannual inspection in order to keep the system in compliance with National Fire Protection Association (NFPA) standards. Currently an individual PR is put in for each inspection or groups of inspections falling under the same timeline/requirement, amounting to repetitive annual and quarterly man-hours spent submitting for the same services year after year.

1.2 Request: Coast Guard Air Station San Francisco would like to submit base plus four option year PR that covers the total sum of inspections completed by Johnson Controls on an annual basis. This would simplify the entirety of our Fire Suppression maintenance process and significantly diminish the potential for administrative errors. Establishing a recurring PR would also promote smoother transitions between Air Station Facility Engineering personnel over transfer season. Air Station San Francisco requests the following specific inspections and monitoring from Johnson Controls:

Inspection
Frequency
Fire Alarm Battery Test
Annual
Smoke Sensor Addressable
Annual
Pull Station
Annual
Waterflow Test
Quarterly
Tamper Switch
Quarterly
Main Fire Alarm Panel
Annual
Wet Sprinkler System
Quarterly
Foam System
Semi-Annual
Digital Alarm Communicator Transmitter Programming
One time investment
Alarm & Detection-Monitoring Simplex 4100U System
Annual

2 SUBMITTALS AND OUTCOMES

2.1 Work Schedule: The Contractor shall submit a service solution outlining the inspection, frequency and total dollar amount for each inspection required of our fire suppression system over the course of a year.

3 PROJECT PERFORMANCE TIME

The contractor must complete each inspection in its required frequency window.

4 LOCATION AND PERIOD OF PERFORMANCE

All work shall take place at:

U.S. Coast Guard Air Station San Francisco 1020 N. Access Rd San Francisco, CA 94128 Period of Performance

Base: 5/1/2019 - 4/30/2020

Option Year 1: 5/1/2020 – 4/30/2021

Option Year 2: 5/1/2021 – 4/30/2022

Option Year 3: 5/1/2022 – 4/30/2023

Option Year 4: 5/1/2023 – 4/30/2024

5 POINT OF CONTACT

The Government Point of Contact (POC) for this work is DCC John Travis, (650) 808 2940, John.R.Travis@uscg.mil. All work shall be coordinated through the POC to minimize operational impacts to the unit during the execution of the work.

6 COORDINATION

The Contractor shall coordinate with the POC to minimize interference with Coast Guard operations or personnel.

7 CONTRACTOR USE OF PREMISES

The Contractor will be working on a Coast Guard operational military installation. Contractor will become familiar with and obey all facility fire, traffic, and security regulations. Personnel shall not stray from the immediate area of work nor direct avenues of ingress and egress unless authorized in advance by the Government. Personnel will be accompanied by an escort at all times of operation upon the military premises.

8 SECURITY

8.1 Working Personnel List: The Contractor shall provide the government POC with a list of names of all personnel who will be working on base. The Contractor may submit a revised list at any time during the project, but newly added personnel will not be authorized on property until confirmed by the government POC. Only personnel on the approved listing will be allowed on the site.

8.2 Personnel Identification: All personnel shall carry proper identification (ID) when on site. Proper ID is defined as either the individual’s driver’s license, or a company issued ID. The identification must be laminated, and show facial picture of the individual. Individuals without proper ID will be escorted off the premises.

9 QUALITY

Quality of Contractor inspections shall be up to NFPA standards.

10 SAFETY

10.1 Compliance: The Contractor is specifically required to comply with the requirements of the U. S. Army Corps of Engineers "Safety and Health Requirements Manual" (EM 385-1-1, latest version available) and the “Accident Prevention” clause (FAR 52.236-13). Once accepted, this safety plan shall become part of the contract requirements. Note: This review/acceptance does not in any way relinquish the Contractor from responsibility for work site safety nor the obligation to comply with the OSHA regulations found in 29 CFR 1910 & 1926 or any other State or Local safety law, rule or regulation applicable to the contract work. The Coast Guard will cooperate fully with the Department of Labor (Occupational Safety and Health Administration) in their enforcement of OSHA regulations.