This document is a Statement of Work (SOW) for the replacement and installation of dock pylon rollers at the U.S. Coast Guard Station in Fort Lauderdale, Florida.
The SOW requires a contractor to provide all labor, materials, and equipment to replace 48 top rollers and 24 bottom rollers, including brackets and hardware. The work must be performed during the facility's operating hours of 7:30am to 5:00pm, Monday through Friday, excluding holidays. The contractor must adhere to security requirements, including providing a list of personnel for base access. After completion, the contractor must conduct a final inspection with designated Coast Guard personnel and submit a notice of completion and payment request.
The related federal contract opportunity is a small business set-aside solicitation (70Z028-24-Q-0000021) for the replacement and installation work described in the SOW. Quotes are due by 3:00pm on July 12, 2024, and the anticipated award date is July 26, 2024. The contract will be awarded based on the lowest price, technically acceptable offer, considering past performance and cost factors.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Construction Clauses and Provisions.pdf | ||
| fl2.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
Replacement and Installation of Dock Pylon Rollers
General Requirements
PART 1 – General: United States Coast Guard Station Fort Lauderdale is accepting proposals for qualified individuals or firms to execute the replacement and installation of pylon dock rollers. This will be a replacement of 48 top rollers and 24 bottom rollers to include bracketing and hardware.
PART 2 – Location:
U.S. Coast Guard Station Fort Lauderdale 7000 N Ocean Drive Dani Beach, FL 33004
PART 3 – Facility Operating Hours: The facility shall remain in operation throughout the service. Contractor access to the service site shall be limited to the following: 7:30am to 5:00pm, Monday through Friday, excluding holidays. Access to the site shall not be permitted on the weekends without prior approval from the Coast Guard (COR).
PART 4 – Security Requirements 1. Contractor shall provide a list of names (including any subcontracted personnel) to the Coast Guard COR for access to the base. 2. All personnel shall present ID to the security personnel at the entrance to the base.
PART 5 – Contractor Responsibilities: 1. Contractor will provide labor, materials, and equipment for installations. 2. Conduct proposed installations. 3. Remove demolition materials and clean up debris generated during repairs. 4. MKC Benjamin Gagnon and EM1 Akeem Garcia must be present during the final inspection.
Proposed Installation: Remove the existing piling rollers. Securely mount the lower bracket and attach the lower heavy-duty pylon rollers. Install the upper piling rollers onto the designated pylon structure. Ensure the proper disposal of the old piling rollers.
PART 6– Cleanup: 1. Clean up job site when complete, ensure all tools, consumable cleaning items are disposed of and removed from premises. 2. The contractor shall not use Coast Guard dumpsters or any waste receptacles for disposal of debris.
PART 7 – Final Inspection and Acceptance: 1. When the contractor has completed all the work, they shall notify the Coast Guard (COR) for a final inspection. If the work is accepted, the contractor shall submit to the Coast Guard (COR): • Contractor’s notice of completion • Contractor’s payment request.
All questions and concerns in relation to project can be addressed to EM1 Akeem Garcia Akeem.e.garcia@uscg.mil phone: 702-908-1127 Or MKC Benjamin Gagnon Benjamin.j.gagnon@uscg.mil Phone: 207-752-6459
Invoices must be submitted into IPP for payment processing by the Coast Guard Finance Center.
U.S. Coast Guard Station Fort Lauderdale 7000 N Ocean Drive Dania, FL 33004 Office: (207) 752-6459 Email: Akeem.E.Garcia@uscg.mil
Close View of Plastic Upper Piling Roller
View of both Upper and Lower Piling Rollers
View of Corroded Bracket for Lower Piling Roller Another View of Upper Plastic Piling image1.png image2.jpg image3.jpeg image4.jpeg image5.jpeg