PWS_Non-conventional Oils_02.22.2024.pdf
PDF 257 KB Posted
- Solicitation number
- 70Z02324GLCOER00001
About this file
This document is a Performance Work Statement (PWS) for a federal contract opportunity issued by the United States Coast Guard (USCG) Great Lakes Oil Spill Center of Expertise (GLCOE). The objective is to measure how the range of possible temperatures and light intensities in the Great Lakes area can photochemically weather conventional and nonconventional oils, and to determine how these chemical changes impact the physical characteristics of the oil. The scope addresses knowledge gaps in how conventional and unconventional oils weather in freshwater environments. Key tasks include performing controlled laboratory studies on photochemical weathering of oils, analyzing partitioning behavior and changes in physical properties, and chemical characterization of weathered oils. The solicitation release date is April 22, 2024 with a closing date of May 22, 2024. The place of performance will be the contractor's facilities with infrequent visits to collaborator's federal facilities as appropriate. The contract will be a firm fixed price with a one-year period of performance.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation.pdf | ||
| Technical Proposal Cover_Page_Template.pdf | ||
| Contractor CLIN Proposed Price Summary.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PR #: 70098PR240012833
PERFORMANCE WORK STATEMENT
LAST UPDATED: 04/22/2024 PAGE 1/9
PERFORMANCE WORK STATEMENT (PWS)
FOR
Non-conventional Oil Weathering in Freshwater
RFI release date: February 27, 2024 Close date: April 12, 2024
Solicitation release date: April 22, 2024 Close Date: May 22, 2024
1.0 GENERAL
1.1 BACKGROUND
Photochemical weathering of oil is the interaction of the chemical components of oil with portions of the electromagnetic spectrum to result in structural changes to those oil components. Photochemical weathering processes can induce physiochemical changes that affect the effectiveness of response tactics and equipment as well as altering the environmental fate of spilled oil. The majority of photochemical weathering research has been focused on marine environments. Freshwater oil photochemical weathering processes within an operationally relevant timeframe is a knowledge gap. Additionally, even less is known about these physiochemical processes with unconventional oils, emerging fuels (e.g., low sulfur fuel oils and carbon neutral fuels), and renewable energy associated products such as dielectric fluids. The study of photochemical weathering processes requires the ability to control the key factors, including the spectra and intensity of light, the thickness of the oil receiving the light, and the temperature of the oil film throughout exposure.
After exposure to light, the oil will have undergone physical and chemical changes that may affect its characteristics such as its viscosity (in turn affecting the effectiveness of different response tactics), its partitioning into the air and water phases (in turn affecting how oil recovery is determined, and changing the potential inhalation hazard to responders), and the amount of wave energy required to mechanically disperse portions of surface slicks into entrained microdroplets of a size distribution that may also be different from the original oil (in turn, affecting response option effectiveness and oil recovery accounting). Greater knowledge of how different oils weather in freshwater contexts, at different temperatures, will inform response planning and decision making as well as oil modeling (e.g., NOAA’s ADIOS database informing GNOME spill modeling).
1.2 SCOPE
The scope addresses the USCG’s Great Lakes Oil Spill Center of Expertise (GLCOE) legislative mandate. Specifically, it addresses the knowledge gaps of how conventional and unconventional oils weather in freshwater environments within a range of light levels and temperatures that represent the Great Lakes area.
1.3 OBJECTIVE
The objectives are to measure how the range of possible temperatures and light intensities in the Great Lakes area can photochemically weather conventional and nonconventional oils, and to determine how these chemical changes impact the physical characteristics of the oil. Ancillary aims to this objective may include but are not limited to determining if oil physiochemical characteristic changes can be correlated with photochemical weathering, and how photochemical weathering may impact response option choice.
1.4 APPLICABLE DOCUMENTS
1.4.1 Reference Documents
LAST UPDATED: 04/22/2024 PAGE 2/9
The following documents may be helpful to the Contractor in performing the work described in this document:
Frank LoBiondo Coast Guard Authorization Act of 2018 - Section 807. [14 U.S.C. 313 note]
1.5 PERFORMANCE REQUIREMENTS SUMMARY.
This contract includes a Performance Requirements Summary (PRS) at PWS 9.0. The PRS plays an integral role in the administration of the contract. In addition to any applicable inspection clauses or other related terms and conditions contained in the contract, the PRS must serve as a primary tool for inspection and acceptance of services as facilitated by the Contracting Officer’s Representative (COR). Evaluation of the Contractor’s overall performance must be in accordance with the performance standards set forth in the PRS, and will be conducted by the COR. The PRS constitutes a material aspect of the contract and will not be changed or otherwise modified without prior written approval of the Contracting Officer.
2.0 SPECIFIC REQUIREMENTS/TASKS
2.1 TASK ONE. POST AWARD CONFERENCE
The Contractor must provide agenda items for the meeting to the Contracting Officer Representative (COR) and attend the Post Award Conference within fourteen (14) days after award. At the meeting, the Contractor must provide details on how the capability gap will be addressed by the technology, technique or strategy being proposed. Key milestones and any issues/concerns will be discussed. The meeting will also serve to ensure that all deliverables and their deadlines are understood by both parties. The Contractor must deliver Post Award Conference Meeting Minutes (Deliverable 1).
2.1.1 Project Management Plan
The Contractor must provide a draft Project Management Plan (Deliverable 2) at Post Award Conference for Government review and comment. The Contractor must provide a final Project Management Plan to the COR based upon feedback from the Post Award Conference.
2.1.2 Data Management Plan
The Contractor must provide a draft Data Management Plan (Deliverable 3) at Post Award Conference for Government review and comment. The Contractor must provide a final Data Management Plan to the COR based upon feedback from the Post Award Conference.
2.2 TASK TWO. LABORATORY STUDY.
2.2.1 Photochemical Weathering of Oil
Known quantities of oil will be exposed to tightly controlled spectra of light in known light intensities for set durations at controlled temperatures. The spectra and intensity of light exposures will be well monitored and characterized to assure data integrity and reproducibility. The resulting weathered oils will be collected for further analysis and experimentation.
2.2.2 Partitioning Behavior of Photochemically Weathered Oil
Oils exposed as per 2.2.1 and unexposed oils will be contrasted by partitioning experiments using waters that are representative of the physiochemical characteristics of the Great Lakes. Partitioning experiments will be constrained within the range of operationally relevant timeframes. The different phases will be separated and collected for further analyses and experimentation.
2.2.3 Characterization of Changes in Physical Properties of Photochemically Weathered Oil Unweathered oil, photochemically weathered oil, and partition waters from 2.2.2 will be analyzed through an array of instrumentation. The basic physical properties will be measured and contrasted among
LAST UPDATED: 04/22/2024 PAGE 3/9
unweathered oil and oils in different stages of photochemical weathering. Properties measured will include, but are not limited to dynamic viscosity, density, interfacial tension, and specific gravity.
2.2.4 Chemical Characterization of Photochemically Weathered Oil Samples produced from 2.2.1 and 2.2.2 will be analyzed by a variety of instruments and approaches.
These will range from gross measurements of total organic carbon, compound family by gas chromatography, and compound specific analyses by state-of-the-art approaches.
2.3 TASK THREE. PROGRESS REPORTING AND DELIVERABLES ARCHIVE.
2.3.1 Progress Meetings
The Lead Principal Investigator must meet with the COR or GLCOE Project Lead, at a minimum, on a monthly basis to discuss progress, exchange information and resolve emergent technical problems and issues. These meetings will take place via virtual platform or in-person. Progress Meeting Minutes (Deliverable 4) must be provided within five days of the meeting.
2.3.2 Quarterly Progress Report
The Contractor must provide a Quarterly Progress Report (Deliverable 5) via electronic mail. This report must include a summary of all Contractor work performed, all direct costs by line item, an assessment of technical progress, schedule status, any travel conducted and any Contractor concerns or recommendations for the previous or future reporting period.
2.3.3 Final Report
The Contractor must provide a Final Report (Deliverable 6) via electronic mail. This report must include a summary of work performed, show research objectives have been met, and any data that was analyzed.
2.3.4 Deliverables Archive
The Contractor must provide a Deliverables Archive (Deliverable 7) in electronic format of all deliverables generated during the course of this tasking.
3.0 CONTRACTOR PERSONNEL
3.1 QUALIFIED PERSONNEL
The Contractor must provide qualified personnel to perform all requirements specified in this PWS.
3.2 KEY PERSONNEL
Before replacing any individual designated as Key by the Government, the Contractor must notify the Contracting Officer no less than 15 business days in advance, submit written justification for replacement, and provide the name and qualifications of any proposed substitute(s). All proposed substitutes must possess qualifications equal to or superior to those of the Key person being replaced, unless otherwise approved by the Contracting Officer. The Contractor must not replace Key Contractor personnel without approval from the Contracting Officer. The following Contractor personnel are designated as Key for this requirement. Note: The Government may designate additional Contractor personnel as Key at the time of award.
Lead Principal Investigator
3.3 LEAD PRINCIPAL INVESTIGATOR
LAST UPDATED: 04/22/2024 PAGE 4/9
The Contractor must provide a Lead Principal Investigator who must be responsible for all Contractor work performed under this PWS. The Lead PI must be a single point of contact for the Contracting Officer, COR, and GLCOE Project Lead. The name of the Lead PI, and the name(s) of any alternate(s) who must act for the Contractor in the absence of the Lead PI, must be provided to the Government as part of the Contractor's proposal. The Lead PI is further designated as Key by the Government. During any absence of the Lead PI, only one alternate must have full authority to act for the Contractor on all matters relating to work performed under this contract. The Lead PI and all designated alternates must be able to read, write, speak and understand English. Additionally, the Contractor must not replace the Lead PI without prior approval from the Contracting Officer.
3.3.1 The Lead Principal Investigator must be available to the COR and GLCOE Project Lead via telephone between the hours of 1000 and 1700 EST, Monday through Friday, and must respond to a request for discussion or resolution of technical problems within 72 hours of notification.
3.4 EMPLOYEE IDENTIFICATION
3.4.1 Contractor employees visiting Government facilities must abide by facility procedures and identification.This may include, but is not limited to an identification badge that, at a minimum, displays the Contractor name, the employee’s photo, name, clearance-level and badge expiration date. Visiting Contractor employees must comply with all Government escort rules and requirements. All Contractor employees must identify themselves as Contractors when their status is not readily apparent and display all identification and visitor badges in plain view above the waist at all times.
3.4.2 Contractor employees working on-site at Government facilities must comply with the site procedures and regulations. All Contractor employees must identify themselves as Contractors when their status is not readily apparent (in meetings, when answering Government telephones, in e-mail messages, etc.).
3.5 EMPLOYEE CONDUCT
Contractor’s employees must comply with all applicable Government regulations, policies and procedures (e.g., fire, safety, sanitation, environmental protection, security, “off limits” areas, and possession of weapons) when visiting or working at Government facilities. The Contractor must ensure Contractor employees present a professional appearance at all times and that their conduct must not reflect discredit on the United States or the Department of Homeland Security. The Lead PI must ensure Contractor employees understand and abide by Department of Homeland Security established rules, regulations and policies concerning safety and security.
3.6 REMOVING EMPLOYEES FOR MISCONDUCT OR SECURITY REASONS
The Government may, at its sole discretion (via the Contracting Officer Representative), direct the Contractor to remove any Contractor employee from DHS facilities for misconduct or security reasons.
Removal does not relieve the Contractor of the responsibility to continue providing the services required under the contract. The Contracting Officer Representative will provide the Contractor with a written explanation to support any request to remove an employee.
4.0 OTHER APPLICABLE CONDITIONS
4.1 PERIOD OF PERFORMANCE
The period of performance for this contract is one year from the date of award, or otherwise negotiated.
4.2 PLACE OF PERFORMANCE
LAST UPDATED: 04/22/2024 PAGE 5/9
The primary place of performance will be the Contractor’s facilities with infrequent visits to the co-collaborators federal facilities, as appropriate.
4.3 TRAVEL
Contractor travel may be required to support this requirement. All travel required by the Government outside the local commuting area(s) will be reimbursed to the Contractor in accordance with FAR 31.205- 46, Travel Costs. The Contractor must be responsible for obtaining COR approval (electronic mail is acceptable) for all reimbursable travel in advance of each travel event.
4.4 POST AWARD CONFERENCE
The Contractor must attend a Post Award Conference with the Contracting Officer, COR, and GLCOE Project Lead no later than 14 business days after the date of award. The purpose of the Post Award Conference, which will be chaired by the Contracting Officer, is to discuss technical and contracting objectives of this contract and review the Contractor's draft project plan. The Post Award Conference will be via teleconference.
4.5 PROJECT MANAGEMENT PLAN
The Contractor must provide a draft Project Management Plan for the Post Award Conference for Government review and comment. The plan, at a minimum, must include: (a) list of work to be performed;(b) project schedule; (c) description of intended results; (d) role of key personnel, if applicable and (e) how quality of service (project) will be maintained throughout the life of contract. The Contractor must provide a final Project Plan to the COR not later than 14 business days after the Post Award Conference.
4.6 DATA MANAGEMENT PLAN
The Contractor must provide a Final Data Management Plan to the COR and GLCOE Project Lead not later than 14 business days after the Post Award Conference. Raw data must be submitted to the GLCOE or appropriate Federal Data Repository through a Federal collaborator.
4.7 PUBLICATIONS/PRESENTATIONS
The Government requests a courtesy review prior to submitting for publication or conference presentations. The Contractor must add the following text:
4.7.1 Funding
“This work has been funded solely, or in part, by the U.S. Coast Guard Great Lakes Oil Spill Center of Expertise.”
4.7.2 Disclaimer
“The views expressed are those of the authors and do not necessarily reflect the views or policies of the U.S. Coast Guard or the Department of Homeland Security. Any mention of trade names, products, or services does not imply an endorsement or recommendation by the U.S. Government or the U.S. Coast Guard.”
4.8 QUARTERLY PROGRESS REPORTS
The Lead Principal Investigator must provide a quarterly progress report to the Contracting Officer, COR and GLCOE Project Lead via electronic mail. This report must include a summary of all Contractor work performed, all direct costs by line item, an assessment of technical progress, schedule status, any travel conducted and any Contractor concerns or recommendations for the previous or future reporting period.
4.9 PROGRESS MEETINGS
LAST UPDATED: 04/22/2024 PAGE 6/9
The Lead Principal Investigator must meet with the COR or GLCOE Project Lead, at a minimum, on a monthly basis to discuss progress, exchange information and resolve emergent technical problems and issues. These meetings will take place via virtual platform or in-person.
4.10 GENERAL REPORT REQUIREMENTS
The Contractor must provide all written reports in electronic format with read/write capability using applications that are compatible with DHS workstations (Microsoft Office Applications).
4.11 SECTION 508 COMPLIANCE
Section 508 of the Rehabilitation Act (classified to 29 U.S.C. § 794d) requires that when Federal agencies develop, procure, maintain, or use information and communications technology (ICT), it must be accessible to people with disabilities. Federal employees and members of the public with disabilities must be afforded access to and use of information and data comparable to that of Federal employees and members of the public without disabilities.
All products, platforms and services delivered as part of this work statement that, by definition, are deemed ICT must conform to the revised regulatory implementation of Section 508 Standards, which are located at 36 C.F.R. § 1194.1 & Appendixes A, C & D, and available at https://www.ecfr.gov/cgi-bin/text-idx?SID=e1c6735e25593339a9db63534259d8ec&mc=true&node=pt36.3.1194&rgn=div5. In the revised regulation, ICT replaced the term electronic and information technology (EIT) used in the original 508 standards. ICT includes IT and other equipment.
Exceptions for this work statement have been determined by DHS and only the exceptions described herein may be applied. Any request for additional exceptions must be sent to the Contracting Officer and a determination will be made according to DHS Directive 139-05, Office of Accessible Systems and Technology, dated November 12, 2018 and DHS Instruction 139-05-001, Managing the Accessible Systems and Technology Program, dated November 20, 2018, or any successor publication.
4.11.1 Section 508 applicability to Information and Communications Technology (ICT): Reports, Training Materials, and Presentations/Briefs
Applicable Exception: N/A Authorization #: N/A
Applicable Functional Performance Criteria: Does not apply
Applicable 508 requirements for electronic content features and components (including but not limited to Internet or Intranet website; Electronic documents; Electronic forms; Electronic surveys;
Electronic reports; Electronic training materials; Multimedia (video/audio); Interactive maps): All requirements in E205 apply, including all WCAG 2.0 Level A and AA Success Criteria apply as specified in E205
Applicable 508 requirements for software features and components: Does not apply
Applicable 508 requirements for hardware features and components: Does not apply
Applicable 508 requirements for support services and documentation: All requirements in Chapter 6 apply
4.11.2 Section 508 Accessibility Conformance Reports: For each ICT item offered through this contract (including commercially available products, and solutions consisting of ICT that are developed or modified pursuant to this contract), the Offeror must provide an Accessibility Conformance Report (ACR) to document conformance claims against the applicable Section 508 standards. The ACR must be https://uscode.house.gov/view.xhtml?req=(title:29%20section:794d%20edition:prelim)%20OR%20(granuleid:USC-prelim-title29-section794d)&f=treesort&edition=prelim&num=0&jumpTo=true https://www.ecfr.gov/cgi-bin/text-idx?SID=e1c6735e25593339a9db63534259d8ec&mc=true&node=pt36.3.1194&rgn=div5 https://www.ecfr.gov/cgi-bin/text-idx?SID=e1c6735e25593339a9db63534259d8ec&mc=true&node=pt36.3.1194&rgn=div5
LAST UPDATED: 04/22/2024 PAGE 7/9
based on the Voluntary Product Accessibility Template Version 2.0 508 (or successor versions). The template can be found at https://www.itic.org/policy/accessibility/vpat. Each ACR must be completed by following all of the instructions provided in the template, including an explanation of the validation method used as a basis for the conformance claims in the report.
5.0 GOVERNMENT FURNISHED RESORCES
The U.S. Coast Guard will not furnish any resources to the Contractor in support of this contract.
6.0 GOVERNMENT FURNISHED PROPERTY
The Contractor must furnish all facilities, materials, equipment and services necessary to fulfill the requirements of this contract.
7.0 GOVERNMENT ACCEPTANCE PERIOD
The COR will review deliverables prior to acceptance and provide the contractor with an e-mail that provides documented reasons for non-acceptance. If the deliverable is acceptable, the COR will send an e-mail to the Contractor notifying it that the deliverable has been accepted.
7.0.1 The COR will have the right to reject or require correction of any deficiencies found in the deliverables that are contrary to the information contained in the Contractor’s accepted proposal. In the event of a rejected deliverable, the Contractor will be notified in writing by the COR of the specific reasons for rejection. The Contractor may have an opportunity to correct the rejected deliverable and return it per delivery instructions.
7.0.2 The COR will have 5 business days to review deliverables and make comments. The Contractor must have 5 business days to make corrections and redeliver.
7.0.3 All other review times and schedules for deliverables must be agreed upon by the parties based on the final approved Project Management Plan. The Contractor must be responsible for timely delivery to Government personnel in the agreed upon review chain, at each stage of the review. The Contractor must work with personnel reviewing the deliverables to assure that the established schedule is maintained.
https://www.itic.org/policy/accessibility/vpat
LAST UPDATED: 04/22/2024 PAGE 8/9
8.0 DELIVERABLES
The Contractor must consider items Items in italics are deliverables or events that must be reviewed and/or approved by the COR prior to proceeding to next deliverable or event in this PWS.
ITEM PWS
REFERENCE DELIVERABLE / EVENT DUE BY
DISTRIBUTION
1 2.1, 4.4 Post Award Conference Meeting Minutes
Five (5) days following meeting
GLCOE Project Lead
2 2.1.1, 4.5 Final Project Management Plan
Fourteen (14) days following Post Award Conference
COR, Contracting Officer, GLCOE Project Lead
3 2.1.2, 4.6 Final Data Management Plan
Fourteen (14) days following Post Award Conference
COR, Contracting Officer, GLCOE Project Lead
4 2.3.1, 4.9 Progress Meeting Minutes Five (5) days following meeting
GLCOE Project Lead, COR
5 2.3.2, 4.8 Quarterly Progress Reports Every three (3) months GLCOE Project Lead, COR
6 2.3.3 Final Report Before Project Closeout
COR, GLCOE
Project Lead
7 2.3.4 Deliverables Archive Before Project Closeout COR, Contracting Officer, GLCOE Project Lead
Updated 6/24/15
9.0 PERFORMANCE REQUIREMENTS SUMMARY (PRS).
The PRS establishes key elements of Contractor performance that represent “mission essential” service requirements, which are identified in the table below in the “Service Output” column. The “Performance Objective” column represents the standard against which Contractor performance will be measured in relation to accomplishment of the corresponding service output. The performance objective or “standard” describes the minimum acceptable level of service by the Contractor for satisfactory performance. The “Acceptable Quality Level (AQL)” column displays the maximum allowable deviation from the performance objective, which, if exceeded, evokes the negative incentive specified in the table below.
Service Output Performance Objective Acceptable Quality Level
(AQL)
Positive Incentive Negative incentive
1. Quality and Timely Deliverables (PWS 8.0)
Research, develop, prepare, compile and submit quality deliverables. Must not require substantive corrections or revisions.
No deviation unless approved in advance by the COR.
Contractor’s ability to meet performance requirements will be reflected in the Contractor’s past performance evaluation.
Failure to meet schedule or provide acceptable deliverables will result in corrective action as determined appropriate by the Contracting Officer in consultation with the COR. The range of possible actions include but are not limited to re-performance of work, withholding payment, renegotiating the schedule, and partial or total termination for convenience/default.
2. On-Time Monthly & Quarterly Progress Reports
(PWS 2.5)
No progress report is delayed by more than one business day.
3. Effective Resource Planning (PWS 2.1.1, 2.1.2)
Manage, retain, and reference project documents that are compiled throughout the performance period. Contractor will be flexible to the government’s evolving requirements and adaptations.
| FOR |
| 1.4 APPLICABLE DOCUMENTS |
| 2.0 SPECIFIC REQUIREMENTS/TASKS |
| 2.2 TASK TWO. LABORATORY STUDY. |
| 2.2.1 Photochemical Weathering of Oil |
| Known quantities of oil will be exposed to tightly controlled spectra of light in known light intensities for set durations at controlled temperatures. The spectra and intensity of light exposures will be well monitored and characterized to assure dat... |
| 3.0 CONTRACTOR PERSONNEL |
| 5.0 GOVERNMENT FURNISHED RESORCES |