RFI 70VT1523N00001

Equal Employment Opportunity (EEO) Process Review Questions

# Solicitation Document

Page Number and Section Question

1 Page 2; 4.3 Submission Instructions

The Government is requesting a rough order of magnitude (ROM) estimate to be submitted with the capabilities statement. Can the Government please confirm that the ROM is not included in the 10-page limit, and can be provided in a separate document (i.e., excel spreadsheet)?

Confirmed ROM is not part of the 10-page limit.

2 Page 3; Technical

Capabilities The Government noted “The descriptions should include schedule information for delivery of services.” Is the government looking for a timeline of events within the twelve-month period of performance and or does this include recommended additional time depending on the assets and/or capabilities required to complete the service?

The Government is looking for the vendor to provide capabilities to complete the service

3 Page 3; Technical Capabilities

The Government noted: “Interested parties should provide information on their ability to use existing assets…”. What assets are currently being used for this service?

This is a new requirement.

4 Page 4, Organization

Experience The sentence below states that references are optional, and they should be provided. Can the government clarify whether respondents are required to submit references "optionally up to three references for same or similar services and/or any product solution(s) should be provided.”

At this time references are only optional.

5 Page 4, Organization

Experience

If references are required, can the government confirm whether they want POC information or some form of validation from the company/agency receiving the work

Yes, confirmed.

6 Page 2, Section 4.2 RFI

Response Due Date April 24, 2023 is actually a Monday. Please clarify the due date and time of the RFI response.

Responses are due Monday, April 24, 2023, 4 PM EST. RFI Amendment has been posted to BETA SAM.

RFI 70VT1523N00001

# Solicitation Document

Page Number and Section Question

7 Is there a contractor currently performing the same or similar work (incumbent contract)?

No.