Draft Statement of Work Summary

This is a Draft Statement of Work (SOW) issued by the Department of Homeland Security (DHS), Science and Technology Directorate, for integrated physical security upgrades at the Transportation Security Laboratory on the William J. Hughes Technical Center campus in Egg Harbor Township, New Jersey. The contract consolidates eight distinct work scopes into a single coordinated program with a six-month performance period from date of award. Work shall be performed during normal business hours (Monday–Friday, 7:00 a.m. to 3:30 p.m.) at the specified New Jersey location.

The scope encompasses: (Scope A) replacement of analog cameras with 46 IP cameras including eight multi-head 360-degree cameras, 32 dome cameras, five fisheye cameras, one dual-head camera, two camera poles, plenum-rated cabling, and buried fiber optic cabling for bunker cameras; (Scope B) replacement of ten video monitors (six 55-inch and four 43-inch) in security offices; (Scope C) video management system with 63 camera channel licenses, one base server license, four network video recorders with RAID storage, and staff training; (Scope D) Lenel OnGuard Visitor Management System implementation including pre-registration, check-in/check-out, ID scanning, badge printing, and integration; (Scope E) installation of 20 additional card readers integrated into the Lenel access control platform; (Scope F) replacement of 58 existing HID card readers with OSDP-capable encrypted units; (Scope G) delivery and setup of a single-wide portable field armory (40 ft L × 10 ft W × 10 ft H) built to NSWC 3046-93-2 specification, including power, HVAC, dehumidifiers, storage cabinet, workbench, eight weapon racks (storing 80 rifles and 64 pistols), four GAU-16 lockers (storing 20 rifles), crane offloading, and staff training; and (Scope H) Video Next CCTV system migration between Buildings 315 and 374 including replacement of two network video recorders, installation of one Cisco PoE+ switch, and reconfiguration of video-wall views with 30-day video retention. The contractor must conduct site investigation, produce marked-up floor plans, and coordinate final layouts with the Government. All systems require programming, testing, commissioning, and full demonstration of operation. Warranty is one year minimum from substantial completion of each scope with no charge for normal business hours warranty work. Labor costs are based on prevailing Davis-Bacon electrician wages for Atlantic County, New Jersey.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRAFT

70RSAT27RFI000004

Draft Statement of Work

United States Department of Homeland Security Science and Technology Directorate

Office of National Laboratories Transportation Security Laboratory

Integrated Physical Security Upgrades Draft Statement of Work

1. Background

The Department of Homeland Security (DHS), Science & Technology Directorate (S&T), Transportation Security Laboratory (TSL) on the William J. Hughes Technical Center campus in Egg Harbor Township, New Jersey, requires a coordinated set of physical security and site infrastructure upgrades. The work spans video surveillance modernization, access control, secure weapons storage, and a portable field armory.

This draft Statement of Work (SOW) consolidates several distinct but interrelated work scopes into a single contract so that the upgrades are engineered, installed, integrated, and commissioned as one coordinated program under unified management, scheduling, and acceptance.

2. Scope of Work

The scope of this contract is to furnish all engineering, labor, materials, equipment, programming, integration, testing, and startup necessary to deliver the following at the TSL Atlantic City campus (Buildings 315, 315-Lab, 318, 319, 374, the Entry/Exit Gates, and the Bunker area):

2.1 Scope A — Video Surveillance (Analog Camera Replacement)

Replace the existing analog cameras serving Buildings 315, 315-Lab, 318, 319, the Gates, and the Bunker with a new camera system, reusing existing network infrastructure, bunker camera poles, and conduit where present. The Contractor shall furnish and install:

● Eight (8) multi-head 360-degree cameras (e.g., AXIS P3738-PLE class or equivalent fully compatible with existing infrastructure) with mounting hardware;

● Thirty-two (32) dome cameras (e.g., AXIS P3265-LV class or equivalent fully compatible with existing infrastructure) with mounting hardware;

● Five (5) fisheye cameras (e.g., AXIS M4318-PLVE class or equivalent fully compatible with existing infrastructure) with mounting hardware;

● One (1) dual-head camera (e.g., AXIS P4705-PLVE class or equivalent fully compatible with existing infrastructure) with mounting hardware;

● Two (2) camera poles at the Entry/Exit Gates;

● One (1) lot of plenum-rated camera network cabling supporting approximately forty-six (46) cameras;

● Installation of buried fiber optic cabling for two cameras located in the bunker area 1000 feet from the

Building 315 security office; and

● Associated multi-head camera mounting (pendant, wall, corner, and pole adapters), surface-mount boxes, and Cat6 information outlets shall be provided.

2.2 Scope B — Replacement Video Monitors

Replace the existing video monitors in the security offices of Buildings 315 and 374. The Contractor shall provide:

Draft Statement of Work

● Six (6) 55-inch monitors;

● Four (4) 43-inch monitors;

● Commercial-grade displays rated for 24/7 operation;

● Full HD or 4K, HDMI/DisplayPort inputs, narrow bezel, and compatible with the upgraded video management system (VMS) described in this statement of work; and

● Wall or articulating mounts, cabling, installation, and configuration.

2.3 Scope C — Video Management Servers and Licensing

Furnish, install, program, and configure the video management system (VMS) to record and distribute video on the existing video walls and workstations. Work includes:

● Sixty-three (63) VMS camera channel licenses;

● One (1) VMS base server license;

● Four (4) network video recorders (NVRs) with RAID storage;

● Programming and configuration of the VMS to record and distribute video to existing video walls and workstations; and

● Training on the operation and maintenance of the new system must be provided to TSL staff.

2.4 Scope D — Lenel OnGuard Visitor Management System

Replace the current visitor management process with Lenel OnGuard Visitor Management. Covers visitor pre-registration, check-in and check-out, ID/driver's license scanning, visitor badge printing, host notification, watch-list screening, and audit reporting. Includes the software license, a reception workstation or kiosk, a badge printer, an ID scanner, integration with OnGuard access control database, configuration, and data migration. Training on the operation and maintenance of the system must be provided to TSL staff.

2.5 Scope E — Access Control Expansion (Additional Card Readers)

Furnish, install, program, and integrate twenty (20) additional card readers into the facility access control system. Readers shall report to the Lenel-based access control platform consistent with the campus access control architecture (Lenel 2220/1320 controllers, hardened network switches, and fiber-optic backbone). Doors with card access shall report to all applicable card access systems.

2.6 Scope F — Card Reader Replacement (OSDP Encryption)

Supply and replace fifty-eight (58) HID card readers (e.g., HID 40KHNKS-03-0004XR class or equivalent fully compatible with existing infrastructure) at the Gates and Buildings 315, 315-Lab, 318, 319, and 374. Reconfigure reader programming to support OSDP end-to-end encryption and functionally test and label all fifty-eight (58) card readers. This scope is distinct from the additional-reader expansion in Scope C; Scope C adds new reader locations, while Scope D replaces existing readers with OSDP-capable, encrypted units.

Upon conversion, the former Ademco panels will no longer report to the FAA Visitor Center; alarms will be monitored locally.

2.7 Scope G — Portable Field Armory

Furnish and deliver one (1) single-wide portable field armory (approximately 40 ft L x 10 ft W x 10 ft H

Draft Statement of Work exterior), built to specification NSWC 3046-93-2, delivered to Egg Harbor Township, NJ. The unit shall include:

● 120–240 V / 100 A / single-phase / 60 Hz power, HVAC, and lighting;

● One (1) set of four (4) anchor brackets and two (2) NFPA ground kits;

● Two (2) desiccant-wheel-type dehumidifiers with humidistat (50 SCFM), 60 Hz, with prep;

● One (1) 36 in x 24 in x 72 in armory storage cabinet;

● One (1) 30 in x 60 in armory workbench with butcher-block top;

● Eight (8) multi-storage weapon racks (approx. 41 in W x 15 in D x 51 in H), configured to store a total of eighty (80) rifles (single cups and extended single clips) and sixty-four (64) pistols (shelves with dividers);

● Four (4) GAU-16 lockers (approx. 22 in W x 14 in D x 65.25 in H), configured to store twenty (20) rifles total (single cups and extended single clips);

● Associated inserts and hardware: barrel clips (extended single), standard single butt cups, shelf kits (8), and pistol dividers (8);

● Zinc-rich primer undercoat (approximately 1,980 SF) with standard urethane overcoat, certified C5M-grade coating per ISO 12944, for marine environments;

● Crane service to offload the unit from the truck and set in place (crane, operator, certified rigger, mobilization/demobilization; one trip, one day); and

● Training on the operation and maintenance of the system provided to TSL staff.

2.8 Scope H — Video Next CCTV Site Migration (Buildings 315 and 374)

Migrate the Video Next CCTV video management system between Building 315 and Building 374.

Work includes supplying and replacing two (2) Dell Video Next VMS rack-mounted network video recorders; supplying and installing one (1) Cisco 24-port PoE+ Layer 3 CCTV switch for the Building 374 cameras; supplying and replacing two (2) video-wall appliances (replacing unsupported Building 374 devices); migrating Building 315 and Building 374 cameras onto the new recorders; and reconfiguring video-wall views to preferred sequences. Video retention shall support thirty (30) days. Existing analog cameras will not be integrated and will remain a separate system. Training on the operation and maintenance of the migrated system must be provided to TSL staff.

3. Site Investigation and Design

The Contractor shall conduct a site walkdown and produce marked-up floor plans as bid/design documentation prior to installation. Final layouts for the command center, video wall, and workstations shall be coordinated with and approved by the Government. Design shall be consistent with the TSL security device and network riser as-built drawings referenced herein.

4. Integration Requirements

● The new IP video system shall integrate with the existing network backbone (fiber-optic riser, Cisco switching, and liquid/light interconnect units) without replacement of existing network infrastructure except as specified;

● Access control shall remain on the Lenel platform; new readers and doors shall report to the appropriate controllers and access systems; and

● Weapon racks and GAU-16 lockers shall be installed to match the portable armory configuration and the campus weapons inventory.

Draft Statement of Work

5. Government Furnished Property and Responsibilities

The Government shall provide:

● Clear and timely access to all work areas;

● Guard escorts during installation as required for secure areas;

● Any permits or fees associated with the work, unless otherwise negotiated;

● Lenel workstation software, as applicable, for installation by the Contractor; and

● Current points of contact and timely notice of personnel changes for long-lead items.

6. Place of Performance

Work shall be performed at the DHS S&T Transportation Security Laboratory on the William J. Hughes Technical Center campus in Egg Harbor Township, NJ.

7. Period of Performance

Six (6) months from date of award.

8. Hours of Operation

On-site installation work shall be performed during normal business hours, Monday–Friday, 7:00 a.m. to 3:30 p.m. unless otherwise authorized.

9. Testing, Commissioning, and Acceptance

● The Contractor shall program, test, and start up all installed systems and demonstrate full operation to the Government;

● Video system acceptance requires both the camera and server/licensing scopes to be complete and recording/distributing video on existing video walls and workstations;

● Access control acceptance requires verified reader operation and reporting to the Lenel platform; and

● The portable armory and weapon storage acceptance requires delivery, placement, and verification of configuration against specification.

● The Contractor shall account for extended lead times on all long-lead equipment and coordinate the master schedule accordingly.

10. Warranty

● Warranty of installation workmanship and supplied material shall be for a minimum of one (1) year from the date of substantial completion of each scope; and

● No charge shall apply for warranty work during normal business hours and days; premium charges may apply for authorized after-hours warranty work.

11. Assumptions and Clarifications

● Existing network infrastructure, bunker camera poles, and associated conduit are assumed to exist and be reusable; and

● Labor is based on prevailing Davis-Bacon electrician wages for Atlantic County, NJ, as applicable.

2.1 Scope A — Video Surveillance (Analog Camera Replacement)
2.2 Scope B — Replacement Video Monitors
2.3 Scope C — Video Management Servers and Licensing
2.4 Scope D — Lenel OnGuard Visitor Management System
2.5 Scope E — Access Control Expansion (Additional Card Readers)
2.6 Scope F — Card Reader Replacement (OSDP Encryption)
2.7 Scope G — Portable Field Armory
2.8 Scope H — Video Next CCTV Site Migration (Buildings 315 and 374)