RFQ 70RFP320QE3000002 Roanoke Questions and Answers.pdf
PDF 135 KB Posted
- Solicitation number
- 70RFP320QE3000002
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ 70RFP320QE3000002 Roanoke Addtl Question and Answers.pdf | ||
| 70RFP320QE3000002 Amend 2.pdf | ||
| 70RFP320QE3000002 Amend 1.pdf | ||
| RFQ 70RFP320QE3000002.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ 70RFP320QE3000002 – Roanoke Video Surveillance System Installation Questions and Answers
Question 1: Is conduit required for the data line that will run from the 1st floor to the 7th floor in the phone/data closet?
Answer: No.
Question 2: Does the Government have additional objectives beyond installing a new system--for example resolution, memory, coverage?
Answer: No. Please reference Section C.3.
Question 3: Are in-ceiling mounts or surface mounts desired for the indoor cameras?
Answer: Surface mounts are acceptable for this requirement. In addition, recessed is also an acceptable option.
Question 4: Can the Government provide a list of government furnished equipment (GFE) that will be available during the duration of the contract?
Answer: There is no government furnished equipment (GFE) for this requirement.
Question 5: Will remote access to the NVR server be allowed during installation and maintenance windows for software, maintenance and recording adjustments?
Answer: No, not at this time.
Question 6: Per Section E.9.2, the Contractor shall provide operator, administrator, and maintence training to required personnel. How many Government personnel will require training?
Answer: Please reference Section E.9.1, only the FPS COR/TPOC will require training.
Question 7: Can existing pathways be utilized in the riser closets if space is available?
Answer: Yes.
Question 8: Will conduit be required in riser closets?
Answer: Yes. However, with the exception of Question #1.
Question 9: If POE injector is needed beyond the MDF, will the Contractor be responsible for 120V power?
Answer: No. If POE injector is needed, a location with existing 120V power will be selected.
However, please reference Section E.3.5.
Question 10: If a Network switch or POE injector is required in the field, will a lockable cabinet be required?
Answer: Yes. However, please reference Section E.3.5.