Solicitation Number: 70FBR919Q00000008 Building Materials Vendor Questions and Answers

Q1. Is Fast Pay available for this contract?

A1. No Q2. CLIN 0006 quantity 300 EA does that mean 300 boxes or 300 single nails? ( example 5 lb box contains roughly 300 nails attached is a picture of the product) 300 Boxes not 300 single nails.

1. Delivery Instructions mention (2) different places: Delivery Contact for Saipan is Jesse Aldan & Delivery Contact for Tinian is Marco Cruz however there is only one delivery location listed Warehouse B2 Commercial Port of Saipan, MP 96950. Can you clarify how many delivery locations and what material is designated for what locations if any. The only address for delivery is Warehouse B2 Commercial Port of Saipan, MP 96950. Material will be distributed from that location.

1. Who is responsible for offloading the trucks at the designed locations?

If the material is put into containers via shipped, the Saipan dock Staffing is supporting the removal of materials. Is the material arrives via truck to the delivery location staffing is onsite but no required to support. Only if/when available.

1. Are partial delivery acceptable? If so at what percentage?

Yes. 20% to start with.

1. If partial deliveries are accepted what is the required time line in between deliveries?

42 to 78 hours