This is a solicitation for Tank and Pump Systems to provide a standardized water supply in all new Manufactured Housing Units. The Federal Emergency Management Agency is seeking proposals for an Indefinite Delivery/Indefinite Quantity Multiple Award contract as a Total Small Business Set Aside. Offerors must provide 25 new Internal Tank and Pump Systems to be shipped to Cumberland, Maryland. The systems must meet requirements for water flow rate, pressure, dimensions, environmental tolerances, and operational protocols to ensure compliance with NFPA 13D and local codes. Documentation, labels, installation kits, warranties, and repair parts are required. Monthly testing and maintenance, as well as decommissioning, are addressed. Qualified offerors must demonstrate experience supplying similar systems. Proposals are due by the date specified in solicitation 70FB8024R00000009.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work for

Internal Tank and Pump System

1. General

Upon recommendation by the Fire Administrator, the FEMA Administrator directed the development and inclusion of Residential Fire Sprinkler System(s) (RFSS) in all new Manufactured Housing Units (MHUs) procured by FEMA. To provide a system capable of deployment anywhere in the contiguous United States, a standardized water supply system consisting of a water storage tank a pump, and ancillary controls must be provided.

2. Scope

FEMA will provide a Tank and Pump System (TPS) with each MHU to comply with the requirements of NFPA 13D and applicable local codes and ordinances. FEMA will use a TPS that is installed in a dedicated closet inside the MHU (i.e., an Internal TPS) to provide the required water supply and pressure for the residential fire sprinkler system.

Offerors must provide 25 new Internal TPS units.

TPS units must meet stringent requirements to ensure compliance of the overall system with the applicable codes and standards and with FEMA’s unique mission requirements.

The requirements for TPS units include minimum water flow rate, minimum water pressure, operational protocol, environmental requirements, dimensional requirements, and various related requirements. Detailed requirements for each of these elements, are presented in the following sections of this document.

A. General Requirements for TPS units

B. Requirements 25 new Internal TPS units.

These units shall be shipped to:

Cumberland THSS 11601 Pittsburg Plate Glass Road Cumberland, MD. 21502

A. General Requirements

A.1 Overview

• FEMA’s Tank and Pump Systems (TPS) are Life Safety systems subject to the jurisdiction and regulatory requirements of fire and life safety officials wherever the TPS has been deployed. Regulatory requirements vary across the Nation. The requirements in this Contract were developed to comply with as many of the extant regulatory requirements as possible.

• FEMA equips Manufactured Housing Units (MHUs) used as temporary housing for disaster survivors with residential fire sprinkler systems. The sprinkler systems are designed and installed to comply with National Fire Protection Association (NFPA) Standard for the Installation of Sprinkler Systems in One- and Two-Family Dwellings and Manufactured Homes-NFPA 13D. The systems must also comply with local codes and ordinances applicable in the jurisdictions where the MHU and TPS are installed.

• FEMA will provide a TPA with each MHU to ensure a consistent and adequate water supply for the residential fire sprinkler system to comply with the requirement od NFPA 13D and applicable local codes and ordinances.

• FEMA will use a TPS that is installed in a dedicated closet inside the MHU (i.e., an internal

TPS)to provide the required water supply and pressure for the residential fire sprinkler system.

• Offerors must provide the following:

25 new Internal TPS units.

The requirements for Internal TPS units have been revised from previous versions.

• FEMA can use this contract to meet requirements of the manufactured home mission, or any other legal mission assigned to FEMA.

A.2 Qualifications

Offerors must demonstrate a thorough understanding of the fire and life safety codes and standards applicable to the residential fire sprinkler systems, fire pumps, and related subsystems in order to be considered qualified to perform this work.

Offerors must submit detailed qualifications to show compliance with FEMA’s requirements as required below.

• New TPS units. Offerors proposing to provide new Internal TPS units shall provide evidence of not less than (10) years’ successful work in the provision of water supply systems for NFPA 13D compliant residential fire sprinkler systems.

B. INTERNAL Tank-and-Pump System Requirements

B.1: SYSTEM FEATURES AND DESIGN GOALS

• Design basis: The INTERNAL TPS shall be designed and constructed so that it is suitable for the intended use and so that maintenance can be accomplished with minimal effort.

The requirements herein are intended to allow the INTERNAL TPS installation into the MHU either at the MHU factory or at another location depending on FEMA’s operational needs.

• Production Capacity: The INTERNAL TPS should be engineered using components and sub-systems that will be readily available in the event of a disaster. Current planning scenarios call for a maximum delivery rate of 50 units per day from all sources. Offerors shall provide the maximum rate at which they can produce quality INTERNAL TPS units, as well as the time required to ramp up to that full production rate in the event of a short notice task order to provide INTERNAL TPS units.

• Applicable Standards: NFPA 13D, Standard for the Installation of Sprinkler Systems in One- and Two-Family Dwellings and Manufactured Homes, NFPA 70, National Electric Code, NPFA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems, 24 CFR 3285 Model Manufactured Home Installation Standard, 24 CFR 3280 Manufactured Home Construction and Safety Standards.

• Equipment life: All system components should be suitable to be stored as installed inside the MHU empty for 10 years in temperatures typically found inside the MHU during storage:

– 15°F to + 120°F. The system shall function as intended at any relative humidity between 5% RH and 100% RH. Design and installation must allow for thermal expansion and contraction of system components that will occur during storage without damage to the components.

• Subsystems and Components Provided with the INTERNAL TPS. The INTERNAL TPS shall have the following subsystems and/or components:

• An interior Annunciator Panel

• A Control system with a Control Panel and all interconnecting wiring

• Pump, Tank, Test Loop, and interconnecting plumbing

• Exterior Alarm

• Subsystems and Related Components Provided and Installed by the MHU Manufacturer:

• Sprinkler system with drain line connected to the top of the Drain and Vent Manifold.

• Riser with connection point for the TPS.

• Two-gang back box, with connected 1 inch conduit stub routed from the Annunciator Panel location to the inside of the TPS closet. Annunciator panel has been relocated to the living room adjacent to the TPS closet, deleting the need for conduit.

• Vinyl siding mounting block, 6” x 6” square installed on the exterior of the MHU near the door to the TPS closet for exterior alarm. Installer will be required to drill a hole through

• the wall and the mounting block to install the exterior alarm; include this in the installation instructions.

• 4-pole, 30 Amp, 240VAC NEMA 14-30 dryer receptacle for electrical service to the TPS.

Receptacle shall be located 46-50 in. above floor, and 10-14 in. from exterior wall.

• 30A 240VAC circuit breaker for circuit serving TPS.

• Drain and vent manifold and floor drain inside the INTERNAL TPS closet. Floor drain inside the closet.

• Wall mounted room light, wall switch and convenience receptacle (120VAC) inside the TPS closet.

• Installation: The INTERNAL TPS should be capable of being installed in the TPS closet provided within the MHU. The system provided shall include an already connected tank and pump capable of being placed and secured inside the MHU with minimum training.

• System must be able to be installed in a MHU with the following door geometry: 35” clear width, 78” clear height, exterior-opening door.

• INTERNAL TPS must fit inside the TPS closet that has interior dimensions of 56” x 41”, leaving space for draining, riser connection, servicing, and electrical.

• INTERNAL TPS should be able to be installed in the TPS closet without dismantling either the MHU or the INTERNAL TPS.

• The INTERNAL TPS shall include features allowing the INTERNAL TPS to be secured to the wall framing and shall include features to prevent the tank or other system components from dislodging during transportation of the MHU.

• The INTERNAL TPS shall be designed and manufactured so that it can be installed, tested, and maintained using common hand tools. Any requirement for special tools must be approved by FEMA before proceeding with production. Any special tools required for installation or maintenance shall be provided in the parts kit with each INTERNAL TPS.

• The INTERNAL TPS shall have a remote Annunciator panel mounted on an interior wall of the MHU outside the INTERNAL TPS closet. The Annunciator panel shall be connected to the INTERNAL TPS System Control Panel via low-voltage cable. The Annunciator panel shall be plug-and-play and shall require no additional assembly or programming at the point of installation.

• The INTERNAL TPS shall include all materials, parts, and interconnections necessary to install a fully functional INTERNAL TPS inside any of FEMAs MHUs. Parts should be boxed and packaged together appropriately, according to their associated pieces.

• INTERNAL TPS Installation instructions shall include a procedure and process to verify that the Control Panel, Annunciator Panel and Exterior Alarm have been properly installed and are in working condition before the MHU is shipped. Include verification of this test on the Installation Checklist.

• INTERNAL TPS shall have provisions for installation and material handling that preclude, to the extent possible, installers using components of the TPS as handles to be pushed or pulled. Handles or straps with prominent warnings are acceptable.

• Design for Installation: The INTERNAL TPS shall be packaged and configured for simple installation and parts accessibility. Installation of the INTERNAL TPS will take place in two separate steps that will occur in separate locations and may occur several years apart.

• All parts shall be packaged in clearly labeled boxes that are securely attached to the INTERNAL TPS unit during shipping to prevent loss. After the completion of Step 1, the boxes containing parts and materials for Step 2 may be placed on the floor of the TPS closet and no longer need to be attached to the INTERNAL TPS unit.

• Installation Step 1 shall include placement of the INTERNAL TPS into the TPS closet, removal of the overwrap, and securing the unit to the designated tie-down points on walls of the TPS closet. Parts and instructions required to accomplish this process s shall be packaged in a box that is labeled “Parts and instructions for installation of TPS unit into an MHU”. This box shall contain only that which is necessary to accomplish this step; the empty box is to be discarded after installation. No electrical or plumbing connections to the MHU are to be included in this step.

• Installation Step 2 shall include all other installation, filling, and system commissioning activities that will be accomplished at the final installation site of the MHU. Parts and instructions required to accomplish this process s shall be packaged in a box that is labeled “Parts for installation and commissioning of the TPS at the final MHU installation site”.

• Design for Maintenance: The INTERNAL TPS should be designed to facilitate servicing by providing easy access to all system parts and components once installed inside the INTERNAL TPS closet.

• Design for Transportation: The INTERNAL TPS (empty) shall be designed and manufactured to withstand the vibration and stresses experienced during transport while inside a MHU for not less than 7,000 miles without damage.

B.2: ANNUNCIATOR PANEL

• A low-voltage Annunciator Panel shall be provided with the TPS. The Annunciator panel shall be mounted at the designated location on an interior wall and connected to the INTERNAL TPS Control Panel inside the INTERNAL TPS closet via a low-voltage cable during INTERNAL TPS installation. The Annunciator Panel will be installed at the location shown on the plans. The Annunciator panel shall be configured to mount to a standard ‘old-work’ style two-gang back box installed in the MHU by the MHU manufacturer.

• It is intended that the information available at the Annunciator Panel be limited to that which is required for the MHU occupant.

• A sample Annunciator panel including all user interface elements shall be submitted for FEMA review and approval.

• Controls shall be logically laid out and simple to use. Labels should be in plain language and accompanied by pictograms appropriate for that control element or feature.

• The surface of the Annunciator panel should be as flush as possible, without protruding lamps, switches or other elements that could snag the clothing of a person walking past or that could be an invitation for tampering.

• Type: Annunciator panel may be analog or digital with an LCD display, or touchpad. Indicator lights may be individual LED lamps or integrated into an LCD display or touchpad screen.

Annunciator panel should be suitable to mount on a standard ‘old-work’ style two-gang back box.

Strobe lights shall not be provided for this purpose.

• Status Indicators: The Annunciator panel shall indicate the following conditions: “System Ready,” “Trouble” (to include water pressure insufficient, insufficient water flow, low water level in tank, low temperature in TPS closet, etc.), and “Pump Running.” Annunciation of the cause of the Trouble signal shall not be provided at the Annunciator panel, but it shall be clearly evident at the Control Panel.

• Audible Alarms: Annunciator panel shall have an audible alarm signal that alerts to the conditions listed below. The alarm is intended only to draw attention to the panel so that the occupants will become aware of a problem and call for maintenance. This is not intended to be a fire alarm; the smoke alarms in the home perform that function. The audible signal may be the same signal for each of the conditions that could initiate an alarm; a separate sound is not required to distinguish between a trouble alarm and a pump running alarm.

• Pump Running Alarm

• Trouble Alarm

• Visible Indicators: Annunciator panel shall have visible indicators to provide current system status. LED lamps or an LCD screen may be used (e.g., a digital thermostat or residential security system panel). The indicators shall be color-coded as listed below.

• A green System Ready indicator shall be illuminated to indicate all system components are ready for use and in their normal state. Indicator shall be suitable for 10 years constant ON use.

• An amber Trouble indicator shall illuminate (and the Trouble alarm shall sound) when: the system fails a test, when water pressure is insufficient, when the temperature inside the INTERNAL TPS closet is too low, and/or when the tank level is below the manufacturer minimum recommended tank level.

• A red Pump Running indicator shall illuminate (and the Pump Running Alarm shall sound) whenever the pump is running, after a programmed delay period has elapsed.

• Alarm Silence Switch: An alarm silence button shall be included in the Annunciator Panel and shall override the audible portion of both the Pump Running alarms (internal and external) and the Trouble alarm but shall not override the Alarm visual indicators. The Alarm Silence button shall be clearly labeled and easily discernable. Where an information panel is provided, include instructions for the occupant to “Call FEMA Maintenance Hotline” when the trouble alarm activates.

• Wiring harness: INTERNAL TPS manufacturer shall provide a wiring harness with pre-formed plug-in connectors to connect the INTERNAL TPS Control Panel to the Annunciator Panel. The wire and the attached connector shall be sized to pass through a 1- i n c h conduit easily. Provide sufficient wire and wire mounting clips to route the wire to the Annunciator panel.

B.3: WATER TANK

• Capacity: The tank shall have a minimum capacity of 220 gallons US.

• Manual Water Level Verification: It shall be easy to visually check the water level in the tank.

The tank shall have permanent markings clearly visible from the INTERNAL TPS closet door opening in a color that contrasts with the color of the tank to indicate maximum and minimum fill levels. Adhesive labels, if used, shall be capable of staying securely in place at 180°F. It is preferred but not required that the tank be fabricated of opaque material so that water level can be visualized through the wall of the tank.

• Automatic Water Level Indicator: The tank shall be equipped with an automatic water level sensing device that is monitored by the INTERNAL TPS control system. The water sensing device shall be installed in the water tank at a location that precludes maintenance personnel from using the piping, control panel, or other TPS components as steps when accessing the sensing device for maintenance. In prior designs, FEMA has experienced field personnel filling a tank to the indicated minimum water level only; this has often been followed by a low tank level up to two weeks after commissioning of the TPS due to water flow into the sprinkler system. Water level indicators that provide both high-level and low-level indication at the control panel (only) may be helpful to help avoid service calls after commissioning.

• Tank Fill: Water tank shall be designed to be filled manually using a garden hose connected to a standard hose bib on the outside of the MHU. The INTERNAL TPS tank fill connection shall be equipped with a swivel female connection, gasket, and valve to facilitate connection of the garden hose. A screw-in plug for the garden hose connection that is attached to the INTERNAL TPS with a tether is required to provide additional assurance against water leak. The Tank Fill connections shall be located not more than 16 inches above the bottom of the INTERNAL TPS so that it can be easily reached by installers standing on the ground. A hose that extends the Tank Fill connection to the outside of the MHU is preferred so that any spills or leaks in the connection will not run water inside the MHU.

• Filter: A sediment filter or spin-down filter shall be provided and installed as part of the tank fill plumbing to prevent passage of fine sand and grit into the INTERNAL TPS tank and pipe. Filters shall be rated no larger than 15-microns; screens, if used, shall be rated no smaller than +500-mesh. This can be a simple whole-house sediment filter from a home improvement store. The filter cartridge should be replaceable; screens, if used, should be capable of being cleaned.

• Winterization: Provide a means and detailed instructions to facilitate drainage of the water tank, pump, pipe, and hose when the INTERNAL TPS is decommissioned. Trace water may be left in the tank after drainage. No standing water shall remain in the pump, pipe, or hose after the system is drained. Provide pipe or tube and connectors to connect the Tank Drain to the Drain and Vent Manifold in the INTERNAL TPS closet (see Appendix 0).

• Tank Overflow and Vent: The tank shall have a permanently installed ½ inch or larger overflow line to divert excess water to the exterior of the MHU through the Drain and Vent Manifold. The water tank shall not be vented to the inside of the INTERNAL TPS closet. The tank shall be vented to the exterior of the MHU through the Drain and Vent Manifold.

The Drain and Vent Manifold provided by MHU manufacturer will have a 1-inch diameter female NPT connection for tank overflow and vent. INTERNAL TPS manufacturer shall provide all fittings.

and hose required to connect the tank overflow and the tank vent to the manifold. (See Appendix 0.)

• Tank Anchoring: The INTERNAL TPS manufacturer shall provide ratchet straps with double-J hook ends that will be used by installer to secure the TPS to the wall studs D-Ring tie down points provided in the TPS closet. Refer to Strapping Detail drawings in Appendix C.

• Tank Label: The water tank shall have a permanently affixed label stating in plain language (i.e., not using the word potable) that it is unsafe to drink the water inside. See Appendix B for required label.

B.4 PUMP

• Flow Rate: The minimum flow rate of the water delivered to the base of the sprinkler system riser shall be 30 GPM at 50 psi, measured at the end of the INTERNAL TPS connecting hose.

• Voltage: Pump motor shall be 60 HZ, single-phase, 240 Volt AC.

• Motor Enclosure: Pump motors shall be enclosed in a minimum NEMA Open Drip Proof (ODP) enclosure.

• Minimum Run Time: Pump controls shall include a minimum run time, timer. The minimum run time timer shall be set to 2 minutes unless the pump manufacturer recommends a different minimum run time.

• Priming: Pump shall be self-priming.

• Maximum static pressure: If the maximum static pressure of the water supply is more than 80 psi, a pressure-reducing valve must be employed on the INTERNAL TPS unit to limit the pressure to 80 psi while providing the required flow rate.

B.5: EXTERIOR ALARM

• Alarm Device: Provide a combination audible local alarm and visual notification appliance

(strobe), Potter model HS-24 or approved equivalent. Device shall be UL Listed for exterior installation. The housing of the alarm shall be red in color. Strobe output should be set at 15 Candela; horn mode should be set at Temporal 3, 2400 Hz. INTERNAL TPS manufacturer shall provide the alarm with the TPS. The TPS installer will install the alarm in accordance with TPS manufacturer installation instructions without the need to program the device (i.e., plug and play).

Note: The Alarm Device will be installed on a mounting block on the exterior of the MHU provided by the MHU manufacturer. TPS installation instructions shall include directions to drill the required size hole through the mounting block, wall sheathing, and drywall, with minimal disruption to the insulation inside the wall, as part of the TPS installation instructions.

• Wiring harness: INTERNAL TPS manufacturer shall provide a wiring harness with pre-installed plug-in connectors for connecting the TPS Control Panel to the Exterior Alarm that will be located on the exterior wall beside the door of the TPS closet opposite from the door hinges. Provide sufficient wire and wire mounting clips to route the wire along the wall of the TPS closet to the Exterior Alarm.

• Operation: The exterior Pump Running alarm shall operate when the pump runs for a fire event or during manual testing. A time delay shall be included in the control logic to allow the pump to run for pressure maintenance without activating the alarm.

• The alarm shall cease to operate when the pump ceases to run.

• The audible portion of the exterior pump-running alarm shall be silenced when the Alarm Silence button on either the Annunciator Panel or the Control Panel is activated.

• Both the exterior alarm and the pump running alarm on the Annunciator Panel should alarm simultaneously when the pump is running.

B.6: PLUMBING

• Connection to Sprinkler Riser: Provide a connection between the INTERNAL TPS and the sprinkler riser. The connection shall have a flexible hose or tube, 1-inch inside diameter or larger. The hose shall be long enough that the weight of the filled hose will bear on the floor instead of on the sprinkler riser; the sprinkler riser shall not be required to bear the weight of the filled TPS hose.

Include a 1-inch female Cam Locking connection on the hose to connect the TPS plumbing to the sprinkler riser provided by the MHU manufacturer in the home. Sprinkler connection in the MHU is an aluminum 1-inch male Cam-Locking fitting.

• Sprinkler system, point of connection, is located on the left side of the TPS closet (when viewing from TPS closet door), 2 – 4 inches above the finished floor, 16-20 inches from the exterior wall of the INTERNAL TPS closet.

• Cam-Locking connectors shall comply with the most current edition of Commercial Item Description A-A-59326, General Specification for Coupling Halves, Quick Disconnect, Cam- Locking Type. Connections shall be Class A, Style 2.

• Provide two spare gaskets for the Cam-Locking connector with the TPS parts kit.

• Gaskets shall be suitable for potable water service.

• Test loop: The INTERNAL TPS shall have a pump test loop that flows not more than 14 GPM to simulate activation of a single sprinkler. The orifice size in the test loop shall be determined based on the water pressure produced at the TPS.

• Test Sequence: INTERNAL TPS test sequence shall be initiated by operating the button or switch on the TPS control panel. Test sequence shall test the TPS controls and alarms and shall operate the pump. Operation of the test loop shall activate both the exterior alarm and interior pump running alarm and allow the water to return to the storage tank.

• Strainers: Pressure gauges, pressure sensors, and other small-orifice devices shall be protected against clogging by a Y-strainer with a US 50 Mesh strainer to prevent clogging of the small passageways.

• Corrosion Prevention: In sections of pipe containing or leading to system control components, piping material and configuration shall be designed and fabricated to prevent corrosion inside the pipe during long periods of storage. The system shall be configured to permit complete drainage of the pipe by gravity when the drain valve(s) is open. The design basis shall include the presumption that some water remains inside the pipe after drainage and the design must preclude corrosion from this standing water.

• Horizontal runs of pipe in sections of pipe containing or leading to pressure sensors, gauges, solenoid valves, motor-operated valves, or other components intended to monitor or control the system are discouraged.

• The use of solenoid operated valves in the INTERNAL TPS system is prohibited.

• Tank Fill Connection/Valve: The tank fill connection and INTERNAL TPS piping shall be configured to permit pressurization of the MHU sprinkler system from a garden hose for low-pressure testing of the sprinkler system prior to INTERNAL TPS startup. The tank fill connection shall have a screw-in plug to prevent any leakage during operation; plug shall be attached to the TPS with a tether to lessen the chance of it being lost.

• Drain: The INTERNAL TPS shall be configured to permit removal of all water from the tank, pump, and piping by gravity flow without the need for electrical power to the unit. Drains shall be arranged to prevent water spilling inside the MHU.

The Drain and Vent Manifold provided by MHU manufacturer will have 1-inch diameter female NPT connections for tank drain. TPS manufacturer shall provide all fittings required to connect the INTERNAL TPS overflow to the manifold.

B.7: Pressure Sensors

• Either standard pressure switches or pressure transducers may be used in the TPS subject to the requirements below. Pressure sensors should have a fluid connection of not less than ¼ inch diameter.

• Replacement pressure sensors must be readily available. TPS manufacturer shall identify and successfully test not less than two commercially available sensors from different manufacturers that can be used in the TPS without the need to rewire or reprogram the PLC. These shall be listed in the parts breakdown in the O&M manual provided with the TPS, and the TPS manufacturer shall commit to maintaining in inventory of replacement sensors.

• Pressure sensors shall be installed in the TPS plumbing system in a position and location so that it is not possible for liquid water to pool inside the sensing port or opening of the sensor when the TPS is drained of water using the system drain valves and draining instructions provided in the operations and maintenance manual. The intent of this requirement is to reduce or eliminate the potential for damage to the sensor by either (1) microbial growth inside the sensing port or pipe leading to the port, or (2) the buildup of scale or mineral deposits inside the sensing port or pipe, or (3) freezing of trapped water.

FEMA has no control over the quality of water available at the installation sites, and experience has shown that each of these phenomena has occurred and resulted in failure of the sensor and/or the need for troublesome repairs.

• Where pressure transducers are used, the piping configuration shall be configured to reduce or eliminate direct pressure wave influx into the sensing port. One way to accomplish this, at the discretion of the TPS manufacturer, is to use a snubber fitting gauge protector to protect the pressure transducer from the hydrodynamic forces of pump startup. If snubber fittings are used, the TPS parts kit shall include not less than one spare snubber fitting for field replacement if the original snubber becomes clogged.

• If pressure transducers are used, the transducers shall not be installed into the TPS prior to shipment. New-in-box transducer(s) shall be shipped as part of the installation parts kit with each TPS unit, and the installation instructions for the transducers shall be integrated into the O&M manual.

o The pipe opening or port where the transducer is to be installed shall be shipped with a contrasting, brightly colored plug to seal the opening during storage and to make locating the proper opening easier during field installation.

o Pipe thread dope or tape that is required to ensure a leak-free transducer installation shall be pre-installed onto the transducer where the transducer has male threads.

Where a transducer has female threads, the dope or tape required for installation shall be packaged with the transducer.

o Recognizing the fact that the transducer can be easily damaged by over-torquing during installation, a brightly colored tag with appropriate cautionary statements and instructions shall be attached to the transducer by wire or plastic tie so that the installer must remove the tag before the transducer can be installed.

B.8: INTERNAL TPS Control Panel

• Control Panel: The INTERNAL TPS control panel shall be located inside the TPS closet and shall control all TPS functions and alarms. The control panel shall be positioned so that the operator’s controls face the door of the TPS closet.

All alarm and trouble conditions reported at the Annunciator Panel should also be reported at the Control Panel; different presentations are permissible. The information available at the Control Panel shall be more complete than that which is available at the Annunciator Panel, and that a maintenance technician shall be able to diagnose and troubleshoot the TPS from the Control Panel.

Audible alarms in the Control Panel are intended only for notification of the maintenance technician in the TPS Closet, not for MHU occupant notification.

• System Reset: The control system should automatically reset the INTERNAL TPS to normal operating mode following a test, activation, trouble alarm, pump running alarm, loss, and restoration of power (i.e., after a thunderstorm or maintenance activity), or other plausible system event. Provide a manual system reset switch on the Control Panel. Upon operation of the

TPS reset switch, the alarm silence feature shall be reset to normal status; any active alarm silence timer shall be cancelled unless the condition that triggered the alarm remains active after the reset.

• Startup: INTERNAL TPS shall not require any programming or adjustment at startup or reset.

Startup shall normally be accomplished by operation of main power switch on the Control Panel.

All system settings should be set at the factory. Time delays and other settings should be capable of being changed if field conditions required but shall require a manufacturer’s password that is not listed in the Operation and Maintenance manual. Pressure switches, water flow switches, thermostats, and any other device that can be adjusted shall be adjusted for proper operation at the factory. The startup instructions shall not require the installer to make any adjustments as a normal course of action. The troubleshooting section of the operation and maintenance manual should clearly describe when adjustments are necessary and how to perform them.

• Water Level Monitor: A Water Level monitor shall activate a Trouble Alarm when the water level falls below the INTERNAL TPS manufacturer’s recommended minimum tank level. (The visible and audible Trouble indicators shall both operate when the water level is low.)

• Diagnostics and Troubleshooting: A PLC based Control Panel shall provide trouble codes and other information that will be useful for diagnostic and troubleshooting. On analog panels, use LED lamps to indicate trouble conditions, in sufficient number, and with clear labels to aid in complete troubleshooting.

• Manual Test Feature: The Control Panel shall provide a system test feature that is manually activated via the appropriate switch. If the system fails the manual test, the Control Panel shall provide trouble code(s) or other means to identify the source of the failure.

• System Test Switch: Provide a System Test button or switch on the outside of the Control Panel.

System Test button shall activate the test loop to simulate the flow of one sprinkler, testing the pump start and the alarms. This switch does not require tamper protection. Automatic testing of the TPS unit is not desired. Test sequence program should permit the test sequence to continue if a non-fatal fault is discovered (i.e., system pressure low but greater than zero), and the system shall display the results of the test along with any fault codes.

• Alarm Silence Feature: An alarm silence feature shall be included that overrides the audible portion of both the Pump Running alarm and the Trouble alarm (at both the Annunciator Panel and at the External Alarm) but shall not override any of the Alarm visual indicators. Each activation of the Alarm Silence button shall silence the Alarm for 24 hours from the time of that activation. Multiple activations of the Alarm Silence button should not result in an increase in the period of time that the alarm is silenced, i.e., button presses are not additive. The Silence feature may be activated every 24 hours as needed. Provide alarm silence capability at both the Control Panel, and on the Annunciator Panel. The 24-hour clock shall be reset when the system reset button is activated (which may result in the alarm reactivating if the condition that tripped the alarm has not been remediated). Activation of the alarm silence button from the TPS control panel only shall silence both audible alarms for a period od 7 days or until the alarm is fixed and reset by a technician.

• Room Temperature Monitor: Provide a room-temperature monitoring capability with the TPS.

Attaching the sensor to the outside bottom of the control panel enclosure at the factory is preferred over a setup step that requires placement of the sensor. Temperature monitor shall be configured to activate the TPS Trouble Alarm when the temperature falls below 40°F. Provide a clear indication at the Control Panel of a low-temperature condition that initiates a Trouble alarm.

• Include a means to verify operation of the room temperature monitor; this can be as simple as a ‘stick-on’ thermometer on the control panel.

B.9: Interface with MHU electrical

• Point of Connection: AC power supply to the INTERNAL TPS shall be provided via a standard

4-pole, 30 Amp, 240 VAC, NEMA 14-30 dryer receptacle and plug.

MHU manufacturer will provide and install a 4-pole, 30 Amp, 240VAC NEMA 14-30 dryer receptacle for electrical service to the TPS. Receptacle shall be located 46-50 in. above floor, and 10-14 in. from exterior wall. INTERNAL TPS manufacturer to provide power cord set with plug to match the receptacle described.

All cords shall have adequate strain relief at each end to prevent damage.

• Plug-and-play: All low-voltage electrical components connected on site should include plug-and-play with locking connectors. Strain relief is required for each electrical connector to prevent damage to the wiring.

• System Control panel: Electrical connections that must be made during installation of the INTERNAL TPS at the System Control panel shall be simple plug-and-play. Locking type connectors are required to enhance system reliability. Detailed instructions shall be provided for any components requiring connection.

B.10: Documentation

• One copy of the complete INTERNAL TPS documentation shall be provided and placed inside the

Document Storage case on the inside door of the TPS closet during TPS installation.

• Provide a complete manual covering installation, activation, maintenance, troubleshooting, and decommissioning.

• Installation instructions shall be provided to cover the steps required to place the TPS into the TPS Closet and to secure it for transportation.

• Activation instructions shall be provided to cover the connection, filling, and testing of the TPS at the final installation site. Include detailed steps and a QA checklist. These instructions shall cover all steps required to fill, power-on, and test the TPS unit. Checks to verify the TPS is free of damage from shipping, and that the electrical and water connections are proper, shall be included. Include steps to perform both the low-pressure (garden hose pressure) test and the high-pressure test (INTERNAL TPS pump pressure).

• Maintenance instructions shall include detailed steps and a checklist to be used for monthly inspection and testing of the TPS unit. Include a step to document the maintenance on the Monthly Inspection and Test Record label (see below).

• Troubleshooting instructions shall cover common and probable problems that can occur during use of the TPS unit.

• Decommissioning instructions shall include: all requirements and a QA checklist for decommissioning the TPS so that the MHU can be transported and stored. Decommissioning instructions shall be predicated on the absence of electric power to the TPS during the decommissioning process. Deactivation instructions shall cover the removal of water from the tank and pump as well as any specific preparation required to transport the TPS and return it to long-term storage.

• Checklists shall be provided to guide each logical activity that may occur during the TPS lifecycle. Checklists shall be provided in two formats: integral with the operating manual, and as stand-alone separate documents so that they can be printed and maintained separate from the manual as needed. Required checklists are as follows:

• Installation,

• Periodic maintenance during storage,

• Activation and startup,

• Monthly maintenance and testing during active use,

• Decommissioning and preparation for shipment.

• Include a complete parts list including manufacturer, model number, and all other specifications required to procure repair or replacement parts for the INTERNAL TPS system.

• Include a list of the estimated time (in hours) required to perform replacement of those parts of the INTERNAL TPS unit that may need to be replaced in the field. At a minimum, include pump, pump motor (if available separately), valves, gauges, logic boards, alarms, flow sensor or switch, battery, and other TPS specific components.

• Include manufacturer’s cut sheets for each component to be used, clearly identifying the specific model or features to be used in the system.

• Include a list of all tools or equipment required for FEMA to install at final home location, operate, maintain, and decommission the provided sprinkler system. Where special tools are required, include manufacturer, model, size, and cut sheet.

• INTERNAL TPS documentation shall be submitted for review and comment by FEMA prior to delivery. Submittal shall be in MS Word format. The operating instructions shall be revised and resubmitted as necessary to incorporate FEMA review comments. After acceptance of the operating instructions by FEMA, one durable, printed copy shall be bound and provided in each TPS, and an electronic copy in MS Word format shall be provided to FEMA. Install the bound hard copy in document case on the door of the INTERNAL TPS closet.

B.11: Labels and Signs

• All signs or labels shall be securely attached so that they will not become dislodged during storage, transport, or use under the environmental conditions described in this document, for not less than 10 years. Adhesives shall be compatible and functional with the substrate on which they will be applied: vinyl siding in the case of the external alarm, polyethylene (or other plastic as appropriate) in the case of the water tank, etc.

• Control Valve Labels: All TPS control valves shall be labeled to note their function and normal position. Example: Tank Fill Valve – Normally Closed. Labeling shall be permanently affixed and durable. These labels should be affixed by the TPS manufacturer.

• Alarm Placard: TPS manufacturer shall provide a weather resistant placard or label approximately 5 inches tall by 7 inches wide in size. The placard or label shall have red letters on white background, and shall state:

“CALL FIRE DEPARTMENT WHEN THIS ALARM SOUNDS - FIRE SPRINKLER IN OPERATION”.

Placard or label shall be capable of being affixed to the vinyl siding with a pre-applied adhesive (i.e., peel-off) compatible with standard vinyl siding or with wood screws that are included in the TPS parts kit. Placard or label, adhesive, and lettering shall be of UV and weather resistant materials that shall not fade or fail over a 10-year exposure. The placard or label will be attached to the vinyl siding during installation of the TPS.

• Switches and Circuit Breakers shall each be clearly labeled to identify function and ON-OFF position.

• Trouble Alarm: The Alarm Silence Buttons shall be clearly labeled.

• Tank Labels: The water tank shall have permanently affixed labels or indicators showing minimum and maximum water levels. There shall be a warning sign or label permanently affixed to the water tank advising not to drink the water. See Appendix B for the required warning label.

• Inspection and Test Record. The TPS manufacturer shall provide a minimum 8½” x 11” monthly test and inspection label with adhesive backing. This label will be installed on the inside of the TPS closet door, near the bottom of the door, during TPS installation. Provide two labels with each TPS. Label shall be similar to that shown below and should have rows for 24 months’ test record on each label.

INTERNAL TPS Monthly Inspection and Test Record

Date

Technician Name Start

Pressure End

Pressure Monthly Test Repairs & Adjustments

Needed or Performed Pass Fail

B.12: Initializing the system

• Startup: startup should contain only the following steps: 1. fill the tank, 2. Low-pressure test, 3.

throw the master switch, 4. high-pressure test, and 5. final setup steps (as required).

B.13: Servicing/maintenance and decommissioning

• Decommissioning: Provide materials, method, and instructions to fully drain the tank, pipe, pump, and other wet components by gravity flow without the need to tip the tank. Instructions shall be provided for draining and decommissioning. Trace amounts of water (e.g., less than ½ inch) may remain in the tank after draining. All water must be removed from the pipe, hose, tubing, and pump, and from the sprinkler system prior to shipping. If a wet-vac is required to comply with this requirement, specify the need for a battery-powered wet-vac and include any necessary adaptor to the vac hose in the TPS parts kit.

• Removal/Replacement: the tank and pump shall be designed such that replacement is possible, and the unit can be removed from the TPS closet if necessary.

B.14: Quality Assurance

• INTERNAL TPS Manufacturer Testing: INTERNAL TPS manufacturer shall perform QA testing for the INTERNAL TPS in accordance with NFPA 13D, FEMA, and manufacturer requirements.

• Include a signed and dated certification of test completion with each TPS. Certification shall include details of tests performed and the results of each test.

• All water shall be removed from tank, pipe, and pump prior to transportation.

• MHU Manufacturer Testing: MHU manufacturer shall be responsible for hydrostatic testing of the sprinkler system. Hydrostatic test pressure shall not be applied to the water tank or INTERNAL TPS piping.

• All water shall be removed from tank, pipe, and pump prior to transportation.

• System Activation Testing: FEMA’s TPS installation contractor will be responsible for two-stage hydrostatic testing of the TPS and sprinkler system during the final installation of the MHU at a disaster site (i.e., low-pressure test followed by high-pressure test). Instructions for this testing shall be included in the Operation and Maintenance manual provided with the TPS. Low pressure testing is performed through the garden hose connection using the available water pressure from the domestic water system. The high-pressure test is performed using the INTERNAL TPS pump.

B.15: Serial Numbers

• Each INTERNAL TPS shall have a unique serial number. Please include a serial number using the

Table below. Serial numbers should be placed on the INTERNAL TPS Control Panel in a color that contrasts with the color of the panel.

DESCRIPTOR SOURCE EXAMPLE

Last two digits from the year the contract was awarded FEMA 22

Hyphen Last four digits from contracted firm’s contract number FEMA XXXX

Three-character abbreviation assigned to contracted firm (Examples from FEMA 2015 INTERNAL TPS contract additional contractor abbreviations will be assigned if additional abbreviations are

FEMA DAR – Darley TAL – Talco Gen – General

Hyphen Last two digits from the year the task order was awarded (If there is no task order use XX)

FEMA 22

Hyphen Last four digits from the task order number (If there is no task order use XXXX)

FEMA 0000

Hyphen

Unique code assigned to requirement version FEMA C

Hyphen Incremental number assigned to each INTERNAL TPS produced under task order

Contractor 0073

Hyphen

The letters INTERNAL TPS to indicate that the product is a tank and pump system

FEMA TPS

Example for Darley 22-1000DAR-22-1000-C-0073-TPS Example for Talco 22-1000TAL-22-1000-C-0073-TPS Example for General 22-1000GEN-22-1000-C-0073-TPS

B.16: Responsibilities Summary

• The table below summarizes the responsibilities of the MHU manufacturer and the installer of the

MHU at the final installation site.

Installation Responsibilities

At MHU Final

Installation Site

At MHU

Plant

Provide & install locking circuit breaker for TPS circuit X Provide & install vinyl siding mounting block for exterior alarm device X Provide & install two-gang back box for Annunciator Panel mount X Provide & install 30A, 240V AC electric service to TPS closet X Provide & install sprinkler system, including connect sprinkler drain to Drain & Vent Manifold and install sprinkler spare parts box.

X

Hydrostatic test sprinkler system X Provide & install TPS closet, Floor Drain, Drain & Vent Manifold, Wall Anchors, Door Lock, Work Light and switch, Convenience Receptacle, and closet ventilation.

X

Install TPS into TPS closet X Install Annunciator Panel, Exterior Alarm Device, & Alarm Placard. X Make all TPS electrical and plumbing connections including Tank Drain, Tank Vent & Tank Overflow to Drain & Vent Manifold

X

Fill Tank, test and commission TPS system X

B.17: Parts List:

• The following is to be provided as part of the bid submission:

• A complete parts list including manufacturer, model number, and all other specifications required to procure repair or replacement parts for the TPS.

• Manufacturer’s cut sheets for each component to be used, clearly identifying the specific model or features to be used in the system.

• Documentation that components or parts that are required to be Listed by an independent testing laboratory are so Listed.

• A list of all tools or equipment required for FEMA to install at final home location, operate, maintain, and decommission the provided sprinkler system. Where special tools are required, include manufacturer, model, size, and cut sheet.

B.18: Parts and Installation Kit:

• The internal TPS shall be equipped with all parts and materials needed to install the unit and make it fully functional, with the exception of standard hand tools, garden hose to fill the tank, and water. All parts shall be new and unused, in original packaging.

• Parts and materials shall be neatly packaged to prevent damage during shipping and storage. Packaging shall be clearly labeled to permit verification and inventory.

• One spare snubber fitting for pressure transducer protection shall be provided if a snubber fitting has been factory installed to protect the transducer.

• One spare gasket for the camlock fitting shall be provided.

• Where a pressure transducer is used, the transducer in its factory packaging shall be included in the installation kit package.

B.19: Warranty

• INTERNAL TPS manufacturer shall warranty the INTERNAL TPS unit to be able to function as specified herein after not less than 5 years in storage at one of FEMA’s Manufactured Housing Storage Sites.

• INTERNAL TPS unit warranty period during use shall be not less than one year after initial activation at a disaster site, which may occur after 5 years in storage.

B.20: Repair Parts:

• Typical missions require a variety of repair parts for TPS units that were found to be nonfunctional on TPS startup. Manufacturers shall maintain an adequate level of spare parts to be shipped to field installation sites upon request.

• OEM parts shall be available for not less than ten years from the date of delivery. Where an original part or component becomes obsolete, manufacturer will develop and provide substitute parts or components suitable to retain the original functionality of the TPS unit.

Sprinkler System Connection Point 2-3 in. above floor, 16-20 in. from exterior wall.

(MHU manufacturer)

(MHU manufacturer)

TPS Unit as close to corner as possible.

Not more than 3 in. from either wall.

(MHU manufacturer)

16 – 20 in.

12 ±2 in.

3 in. max.

3 in. max.

Floor Drain

(MHU manufacturer) mounting block for alarm.

Sheet Notes:

Locate wall mounted closet light 72 ±2

Spare sprinkler cabinet to be mounted 6

B.21: INTERNAL TPS and TPS Closet Design Concept & Coordination Schematics

TPS Closet Coordination Schematic

Figure A-1. INTERNAL TPS Closet Coordination

Support Structure

Figure A-2. TPS Closet Drain & Vent Manifold

Connection Port for Sprinkler System Drain

Rigid pipe support attached to wall stud

Connection Port for Water Tank Overflow and Tank Vent

Connection…