DEPARTMENT OF HOMELAND SECURITY (DHS)

Statement of Work (SOW) For Hygiene Kits

GENERAL INFORMATION

REQUIREMENT:

The Federal Emergency Management Agency (FEMA) request procurement of Hygiene Kits according to the list below. Request that 500,000 hygiene kits be delivered within 30 days of the date of award and delivered to the Maunabo Warehouse between the hours of 07:00 – 22:00 or Crowley Cross-Dock Facility between the hours of 08:00 – 15:00. The total amount of Hygiene Kits required is 500,000, however pricing is requested for delivery to Maunabo, PR and Jacksonville, FL. The location for and the amount of hygiene kits needed per location will be provided to the successful offeror at contract award.

Also, request that vendor options remain open to provide for any future request within the next ninety days.

Specification Requirements:

The hygiene kit provided by the contractor(s) shall contain all items and sizes as listed below:

Item
Details
Antibacterial Cleansing Wipes
Travel Pack of 15
Bar, Antibacterial Soap
1 oz. or less
Comb, Individual
Plastic, 5”
Deodorant, Unscented
1.5 oz. or less
Facial Tissue, 2 Ply
Travel Pack of 15
Hairbrush
Plastic with Medium Bristles
Hand & Body Lotion
2 oz. or Less
Hand Sanitizer
2 oz.
Razor, 3 Blade with Cover
Disposable
Shampoo
2 oz. or Less
Conditioner
2 oz. or Less
Shaving Cream
2.5 oz. or Less
Toothbrushes, Adult
Soft Brush, in Wrapper
Toothpaste
.85 oz. or Less
Mouthwash (Antiseptic)
1.5 oz. or Less
Washcloths
White, Cotton, 12" x 12"
Patch Handle Bag
Plastic, White, 15" x 18" x 4"

Period of Performance:

The full order must be delivered within 30 days of the date of contract award within the delivery schedule as stated below:

Days After Award
Amount Delivered
10
160,000 for a total of 160,000
20
160,000 for a total of 320,000
30
180,000 for a total of 500,000

If the above schedule cannot be met, the vendor must agree to ship incrementally, with the full order being delivered within 30 days after the award date.

Production/Delivery Schedule Requirements:

Maunabo Warehouse:

Carretera # 3 Barrio Vista Alegre Salide para Yabucoa (La Pica) Maunabo, Puerto Rico 00707

Crowley Cross-Dock Facility:

2061 Seaboard Coast Line Dr.

Jacksonville, FL 32209

Deliveries may need to be diverted from the original intended location, after award. If a diversion is required, the Contracting Officer Representative (COR) will notify the vendor via email. The locations where the deliveries may be diverted are listed below:

DC Ft WorthDC Atlanta
Fort Worth Federal Center3780 South Side
501 W Felix StIndustrial CT
Warehouse # 12Atlanta, GA 30354

Ft. Worth, TX 76115

DC MoffettDC Frederick
NASA Ames Research Center (ARC)4420 Buckeystown Pike
Building 144, Door #7FEDAAC Code 703230
Moffett Field, CA 94035Frederick, MD 21704

The Government reserves the right to require delivery of diverted Delivery orders to locations other than those listed above. However, it is anticipated that the above DC’s/ISB’s will be the alternate delivery destinations of the majority of the diverted Delivery orders.

Packaging Requirements:

The entire listed contents of each hygiene kit must be packaged and shipped together. For example, if there are 20 kits being shipped together, there should be 20 individually package kits. There should not be 20 combs packaged together, 20 toothbrushes packaged together, etc…

The contractor shall pack all hygiene kits into properly sealed triple-wall transportation worthy container (i.e. box). The contractor shall ensure all transportation containers are sealed and securely banded and placed on a standard wooden pallet. Due to many unknown circumstances which can arise during disaster response operations and recovery, it is possible the hygiene kits may be transported several times during their FEMA life cycle, and may be doubled stacked for storage. Also, the hygiene kits may be stored in a warehouse or outside with no protection from the elements. Stretch wrapping shall extend over the top of the packaged product by a minimum of six inches and contain no less than 10 layers. The contractor shall label each sealed tri-wall container box in accordance with the following minimum requirements:

(1) A statement identifying the commodity.

(2) The name and place of business of the manufacturer, packer, distributor.

(3) Net quantity of contents in terms of weight, measure, or numerical count (measurement must be in both metric and inch/pound units).

(4) Each tri-wall will be labeled with the FEMA logo

(5) Shelf life information including a) manufacturer, b) lot number, and c) expiration/use by date.

At a minimum, all contents of the kit shall have a shelf life/not expire for 12 months from the date of receipt by the government.

The finished product will be placed onto a 48 inch by 40 inch (48x40 inch) four-way wooden pallet. The over-all height of the pallet will not exceed 55 inches. Contractor (s) may suggest or recommend other techniques to preserve the integrity of the material as well as the finished pallet. This recommendation should be provided to the FEMA CO and COR.

Tracking:

The Contractor must have the capability to track shipments electronically (i.e. Global Positioning System GPS) and provide updates on a 24/7 basis. For example: FEMA may request diversion of shipment during response to disaster and would need to know current location of shipment in order to calculate accurate arrival time to diverted location.

Upon invoicing, the contractor shall provide an electronic spreadsheet showing details of commodity shipped from place of origin to destination. At a minimum the electronic spreadsheet must provide these details: Load number, BOL number, nomenclature and units shipped, carrier, truck number, trailer number, place of origin, and destination.

Drop Trailer:

During an emergency response, the Contractor must be able to accommodate request where delivery of commodities are dropped at the delivery destination and the tractor and driver are held for up to 30 days.