QUESTIONS & ANSWERS RFQ 19PE5026Q0022

1.-

Sharing pictures are not permitted. The site visit is specifically intended for vendors to identify such deficiencies first-hand.

Mainly the perimeter walls next to CAC#1 (Wall#9) and the wall between CAC#2 and CAC#3 (Wall#18).

Contractor is allowed to work on multiple fronts simultaneously. The Embassy will provide the necessary escorts

Yes.

Both standardized multidirectional scaffolding systems and steel scaffolding with certified platforms may be used, provided that the proposed system complies with all applicable safety regulations, load-bearing requirements, and relevant standards.

The contractor must submit the corresponding certification and technical documentation for review and approval prior to installation.

Contractor must submit the request in advance to Facility Manager approval. Facility

Manager will evaluate the request.

Contractor may use the exterior area around Embassy shops for storing materials. It is recommended to bring cabinets or boxes with padlocks for tools storage.