70-M0087-26-EM078_EM_Airport_Patch_.pdf.PDF

PDF 176 KB Posted

Attached to
AIRPORT RUNWAY PATCH WORK
Solicitation number
70-M0087-26-EM078
Issued by
Santa Fe County, New Mexico

About this file

This document is an Emergency Procurement Request and Determination form submitted by the Santa Fe Regional Airport in Santa Fe, New Mexico for emergency runway patch work. On August 5, 2026, a blowout in the asphalt runway created a safety hazard that required the airport to close the runway until repairs were completed. The emergency work was approved via phone by Chief Procurement Officer Travis Dutton-Leyda on August 5, 2026, and formally submitted on August 6, 2026. The scope of work includes 3-inch asphalt patching across multiple sections (6'x26', 3'x26', 4'x58', 6'x8', 5'x23', 4'x9', 5'x14', and 4'x11'), mobilization, cold milling of 3-inch asphalt (87 square yards), and HMA SP IV installation (87 square yards). The contract is a one-time payment for emergency services with no renewal options. The work was completed on August 5, 2026, with the procurement request fully approved on August 6, 2026, following expedited reviews by the Procurement Analyst, Department Director, Chief Procurement Officer, City Attorney, and Finance Director.

The total contract amount is $21,172.29, comprised of a $10,000.00 mobilization fee, $870.00 for cold milling asphalt at $10.00 per square yard, and $8,700.00 for HMA SP IV at $100.00 per square yard, plus $1,602.29 in sales tax. The vendor is GM Emulsion, located at 5935 Agua Fria Street, Santa Fe, New Mexico 87507-9030, with NM Contractor's License 370602 and appropriate credentials. The invoice was issued on August 6, 2026, with payment due on September 1, 2026. Funding is provided through Fiscal Year 2027 budget. The Santa Fe Regional Airport identified this procurement as necessary to preserve and protect property, and plans to establish a blanket purchase order for future pavement maintenance to prevent similar emergency procurements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Back to All Requests

EMERGENCY_GM EMULSION_AIRPORT PATCH

2027-166-Request

Status:

Closed

Amount:

$21,172.29

Last Action:

Final Approval Received

Actions

Fully Approved Approved On 8/6/2026

EMERGENCY REQUEST AND DETERMINATION

Name of Request

EMERGENCY_GM EMULSION_AIRPORT PATCH

Created On

08/06/2026

Summary of Request

Approval of Emergency Procurement for the amount of $21,172.29 to GM Emulsions for emergency patch work on Airport runway.

Background

Emergency patch work was done to the runway at the Santa Fe Regional Airport on 8.5.26. This patch posed as a safety risk to incoming flights and required the Airport to close the runway until repairs were completed. Staff at the airport spoke to Travis Dutton-Leyda who approved this work to be done and submitted as an emergency within 72 hours.

No Category Codes

Requestor

KB Kelly Bynon

Approval Group

Airport

Creator

KB Kelly Bynon

Desired Delivery Date

08/05/2026

Fiscal Year

FY27

Purchase Details

Total Budget Amount $21,172.29

Emergency Assessment

Department Contact:

Kelly Bynon

Email:

kabynon@santafenm.gov

Phone Number

Create

8/7/26, 9:49 AM Request Approval https://procurement.opengov.com/governments/1784201/requisitions/65342 1/3 https://procurement.opengov.com/governments/1784201/requisitions https://procurement.opengov.com/

505-670-1103

Description of Goods/Service to be Procured:

Airport Runway Patch Work

Quantity of the Goods or Service 1 patch

Type of Good or Service Maintenance

Emergency Justification:

Preservation or Protection of Property

Term of Contract (Emergency) One-time payment

Conversion:

To Requisition

Vendor Name GM Emulsion

Vendor's Address 5935 Agua Fria St, Santa Fe, NM 87507-9030

Vendor's Email Address fred@gmemulsion.com

Scope of Work (Emergency) EMERGENCY RUNWAY PATCH COMPLETED ON AUGUST 5, 2026: 3" Asphalt Patching - 6'x26', 3'x26', 4'x58', 6'x8', 5'x23', 4'x9', 5'x14', and 4'x11', MOBILIZATION, COLD MILLING ASPHALT 3 Inch, and HMA SP IV

Detailed Justification:

There is currently a blowout in the asphalt at the airport causing safety concerns. Which ultimately led to the airport runway being closed until repairs can be completed. This work was deemed an emergency by CPO Travis Dutton-Leyda via a phone call on 8.5.26

Measures to Minimize the Duration and Impact of the Emergency Procurement This emergency procurement will be in place until the patch is completed and the runway is maintained. We will work with the Purchasing Division to establish a blanket purchase order as soon as possible.

Future Steps to Prevent Similar Emergency Procurements The Santa Fe Regional Airport will request a blanket purchase order for pavement maintenance to ensure the runway is suitable for aircrafts.

Attachments

Uploaded Documents

20260806-Invoice MidfieldEmerPatch.pdf

Workflow

8/7/26, 9:49 AM Request Approval https://procurement.opengov.com/governments/1784201/requisitions/65342 2/3 https://og-pro-production-req-attach-use1.s3.us-east-1.amazonaws.com/65342/67e7a171-b8e1-4094-abdd-dd14130f4c45_20260806-Invoice_MidfieldEmerPatch.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4DOSJOT4D%2F20260807%2Fus-east-1%2Fs3%2Faws4_request&X-Amz-Date=20260807T143105Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEI7%2F%2F%2F%2F%2F%2F%2F%2F%2F%2FwEaCXVzLWVhc3QtMSJGMEQCIDhLROQD3yB9U6X1E11ZOCqcK%2By46UhU7mX53rTqPQf4AiAzacjLEueUPYIYRH81pvIEvSXWAw5RrTAWhc%2FE1w2u3CqKBQhXEAIaDDg5MjM2NDY4NzY3MiIMmO6jD4S8jcp2pET7KucEvQd2hHOp06gIHTRM1In4U67UQSM6m6K7Xx1jkcj7naDMhRas8USbDMjbbKXcfUK43IjSO03D1YHOCbNCYmdqVBKx5ir%2BmSCeiW%2FBfLHGaIUjphYH5Rnl1T8gVpEIQkY8FfvgSwHvkQCM6E%2FYyiZ2uWeRdk44ZCTNcoLWB33EaF59dRG5r4mSl1%2FZE9imGea72XtHf6ATnpSnGguLlgZPPijBnPU5jwjQ59ljZndmLmFfCzeGpvaJVzLMDAxVbeA8nRZDAqh4cIrtFwiA7jtnCfb%2BBuMCKk7%2FZMPTIOlC2PUe6ebfBeP1kdqT74cP2Jc2dSg1jl2vfOixZuYeEnBuhxX%2F4d1T4SeiraHbukM%2Fj%2FEyqzvdukwnMWY0dv%2F7IY4FdLzYm2mqnSK0FsAIaoabJhqzXlqmb0pPIF8dW1%2BwanQ4pliR5waI4Wq0oAeuM7y2LnCXj9cGhnCJuaMXeYUNqHdYYJbbM1KI89GjKnEjSk73WYThLN%2FcXQg1C7gn%2Bvv%2BNecdkxtz7VHPUF8UBoFZqr5OxgbFF0HZlSef4croOqDBcQLe%2FlYk12AxRSjrwjjgGG9rPn3DX6M6IoBCeDbTuqWnFQFo0MqnHOyjmQMsJtUBOpaiVASTB4I0gGqXRYMx5x24wXzgGLqzcX2%2FXcfWJrIeik8%2B9oI221VGs0gNAJ82JpUE3gS3BLZDdBLixlbzmuTNiJdPkK3Kh77aG%2FvVE3yHWCISSdkePtqdBk7hMDhQxq%2BLIgKvWHyYMxPHHwM%2FA6qDyEzQ4VIUjzPrI5PW0G%2BFCtZNZyJgZDKjbozh%2B6t9LV8JpSmpMKTI19MGOpoBp4ZNKqLPzg10M8lIORxa%2FEjPEmkyPhPfdxKrIvoJ1xSsxTZlEE0q3eNWWI2YjxGT%2F7V51ZeLJSWeCau4MPzZ3kk0HanRBsuD8IsKnvmyrRxK1C4Q3bZzu0c0g7QCs63NevsXgbkHtm1Jz4YZimcuGHzheXY5BGfGtJ9uhFKGnuZP5vRzGw8AEA5DUjYhfccxQy7vYOjaPkTHeA%3D%3D&X-Amz-Signature=44f4f940a2f49f9bd80a48c6cf284bd75c7dbe3e5c7a39490e30e91c310f0280&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%2220260806-Invoice_MidfieldEmerPatch.pdf%22&x-id=GetObject

Request Submitted

Created By

KB Kelly Bynon

Submitted by Kelly Bynon on 8/6/26 at 11:28am

CPD Analyst Initial Review

Approved

Procurement Analyst Senior

KM Kristy Miera

Approved by Kristy Miera on 8/6/26 at 1:38pm

Requesting Department Director

Approved

Department Director

Approved

Director Review

JD John Dickinson

Approved by John Dickinson on 8/6/26 at 2:12pm

CPO Review

Approved

0 of 1 Approvals Needed

Travis Dutton-Leyda Chief Procurement Officer (CPO)

JL JoAnn D. Lovato Montaño Procurement Manager

Approved by Travis Dutton-Leyda on 8/6/26 at 2:23pm

City Attorney

Approved

City Attorney

MM Marcos Martinez

Approved by Marcos Martinez on 8/6/26 at 2:44pm

Finance Director

Approved

Finance Director

MM Monica Mastas

Approved by Monica Mastas on 8/6/26 at 4:26pm

8/7/26, 9:49 AM Request Approval https://procurement.opengov.com/governments/1784201/requisitions/65342 3/3

INVOICE

GM Emulsion 5935 Agua Fria St Santa Fe, NM 87507-9030 fred@gmemulsion.com +1 (505) 471-9981 www.gmemulsion.com

Bill to

Desiree Ring Santa Fe Regional Airport jxdickinson@santafenm.gov dcring@santafenm.gov kabynon@santafenm.gov 121 Aviation Dr.

Invoice details

Invoice no.: MidfieldEmerPatch Terms: Due on receipt Invoice date: 08/06/2026 Due date: 09/01/2026

Job Number: 26076

# Product or service SKU Description Est. Total Invoiced Qty Rate Amount Remaining

SANTA FE REGIONAL AIRPORT - EMERGENCY PATCH COMPLETED ON AUGUST 5, 2026 - 3" Asphalt Patching - 6'x26', 3'x26', 4'x58', 6'x8', 5'x23', 4'x9', 5'x14', and 4'x11'

1. 621000 LS MOBILIZATION $10,000.00 $10,000.00 1 $10,000.00 $10,000.00 $0.00

2. 414130 SY COLD MILLING

ASPHALT 3 Inch

$870.00 $870.00 87 $10.00 $870.00 $0.00

3. 423270 SY HMA SP IV $8,700.00 $8,700.00 87 $100.00 $8,700.00 $0.00

Ways to pay

Note to customer Federal ID: ENI: 27-1902307, CRS: 03-181502-00-2, Duns: 830132820, NM Work Force Solution: 002461320120530, NM Contractor's License: 370602 (GA01, GA98, GB98, GF01, GF02, GF03, GF04, GF05, GF07, GF08, GF09, GS08), NM State Residence Certificate: L1391423280

View and pay

Subtotal $19,570.00

Sales tax $1,602.29

Total $21,172.29 mailto:fred@gmemulsion.com tel:5054719981 http://www.gmemulsion.com/ https://connect.intuit.com/portal/app/CommerceNetwork/view/scs-v1-0dbef4d903ff40a6a59fb5b0c2853675a235756168c540d0b1b6ae1802a3e5d7a1abfdfcd3894adf85641a22f9ca4fb9-1?locale=en_US&cta=pdfbutton

EM_Airport_Runway Patch.pdf
20260806-Invoice_MidfieldEmerPatch (1).pdf

File details come from the government source that posted it. Updated .