7-T602 4181-UC 06232025.pdf

PDF 84 KB Posted

Attached to
Contract T-602-DR Donation Road Bridge Replacement Project
Solicitation number
US.208105
Issued by
Erie County, Pennsylvania

About this file

This Utility Relocation Clearance Report is issued by the Pennsylvania Department of Transportation for Erie County, specifically for Greene Township, involving the utility Penelec/FirstEnergy along Route T-602. The document outlines the utility's plan for maintaining and relocating aerial lines within the project limits, with work scheduled to be completed by June 23, 2025. The report details the utility's operational approach, including de-energization during construction and coordination with the highway contractor, with work to be conducted during normal working hours and lasting no longer than four hours.

The report specifies that Penelec currently operates several primary circuits in the area with nominal voltage at 13,800V. The utility has outlined specific conditional restrictions, including the ability to re-energize facilities pending contractor notification and potential schedule adjustments due to emergency or severe weather. The relocation is classified as a "NOT AFFECTED" type, indicating the utility's facilities are not anticipated to be significantly impacted by the construction project. The document is prepared by Chris Beyer, with contact information provided, and requires approval of an occupancy permit and/or execution of a reimbursement agreement before proceeding with the proposed adjustments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A ppendix A

Publication

(D

M -5)

Figure A -1100

(09/14)

UTILITY RELOCATION

CLEARANCE REPORT

COUNTY _________________________________________

CITY, BORO, TWP ________________________________

ROUTE & SECTION ______________________________

FEDERAL PROJ. NO______________________________

Utility_

Date

Prepared by

Phone

Construction Contact

Phone

TYPE OF RELOCATION WORK (REF: DESIGN MANUAL PART 5)

1. PRIOR: Anticipated completion of work before the highway contractor’s Notice to Proceed is issued. Use actual or anticipated completion date.

2. RESTRICTIVE: To be completed by the UTILITY before highway contractor can operate without restriction. Number of calendar days required AFTER THE DATE OF NOTICE TO PROCEED AND AFTER CONTRACTOR NOTIFIES UTILITIES.

3. CONCURRENT: Simultaneous with, but not restricting. the contractors operation. Number of calendar days required.

4. COORDINATED: Phasing with a specific construction operations.. Number of calendar days required AFTER COMPLETION OF

SPECIFIC CONSTRUCTION OPERATIONS (e.g.: clearing & grubbing, rough grading, pipe hangers).

5. NOT AFFECTED: Identifies UTILITY with facilities in the construction area not anticipated to be affected. Specific information may be provided by the UTILITY.

6. INCORPORATED: Utility relocation work to be incorporated into the prime highway construction contract.

CONDITIONAL RESTRICTIONS AND TIME REQUIREMENTS: Identify conditions affecting the utility’s ability to perform work, i.e.: certain times of the day, week or year that a facility cannot shutdown, acquisition of R/W by the State, demolition of buildings, relocation of other utilities, etc. Show number of calendar days.

LIST EACH AREA OF INVOLVEMENT BELOW

ROUTE

STATION TO STATION

OR SEG. & OFFSET

TO SEG. & OFFSET

RT./

LT.

BRIEF DESCRIPTION OF ADJUSTMENT

TYPE OF

RELOCATION

EACH AREA

(SEE ABOVE)

DESCRIBE CONDITIONAL RESTRICTIONS OR

TIME REQUIREMENTS SPECIFY CONTRACTOR’S

OPERATION FOR COORDINATED WORK. SEE

NOTES ABOVE

CALENDAR

DAYS REQ’D OR

DATE OF

COMPLETION

The proposed adjustments described above are the necessary relocation adjustments to be undertaken by the above named utility to accommodate the construction of the above listed highway project. Contingent upon the approval of a necessary occupancy permit and/or execution of a reimbursement agreement and upon notice to proceed by the Department of Transportation, the above named utility agrees to proceed with these adjustments.

BY

(Signature)

TITLE

D-4181-UC (9-14)

DESIGNER IV

Christopher Beyer

COUNTY: ERIE
CITY BORO TWP: GREENE TWP
ROUTE SECTION: T-602
FEDERAL PROJ NO:
Utility: PENELEC/FIRSTENERGY
Date: JUNE 23, 2025
Prepared by: CHIRS BEYER
Phone: 814-868-8737
Construction Contact:
Phone_2:
ROUTERow1: T-602
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow1: STA 0063 TO STA 0067
RT LTRow1: RT
BRIEF DESCRIPTION OF ADJUSTMENTRow1: Aerial lines exist within limits of this project
TYPE OF RELOCATION EACH AREA SEE ABOVERow1: 5
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow1: Per OSHA 1926, Penelec currently operates several primary
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow1:
ROUTERow2:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow2:
RT LTRow2:
BRIEF DESCRIPTION OF ADJUSTMENTRow2: and to remain during construction
TYPE OF RELOCATION EACH AREA SEE ABOVERow2:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow2: circuits in this area , the nominal voltage are 13093v.
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow2:
ROUTERow3:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow3:
RT LTRow3:
BRIEF DESCRIPTION OF ADJUSTMENTRow3:
TYPE OF RELOCATION EACH AREA SEE ABOVERow3:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow3: Work schedule to be coordinated with other utilities
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow3:
ROUTERow4:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow4:
RT LTRow4:
BRIEF DESCRIPTION OF ADJUSTMENTRow4:
TYPE OF RELOCATION EACH AREA SEE ABOVERow4:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow4: De-energization will occur during Penelec normal
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow4:
ROUTERow5:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow5:
RT LTRow5:
BRIEF DESCRIPTION OF ADJUSTMENTRow5:
TYPE OF RELOCATION EACH AREA SEE ABOVERow5:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow5: working hours and will last no longer than four (4)
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow5:
ROUTERow6:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow6:
RT LTRow6:
BRIEF DESCRIPTION OF ADJUSTMENTRow6:
TYPE OF RELOCATION EACH AREA SEE ABOVERow6:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow6: hours. Penelec reserves the right to re-energize
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow6:
ROUTERow7:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow7:
RT LTRow7:
BRIEF DESCRIPTION OF ADJUSTMENTRow7:
TYPE OF RELOCATION EACH AREA SEE ABOVERow7:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow7: facilities, pending contractor notification, in the
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow7:
ROUTERow8:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow8:
RT LTRow8:
BRIEF DESCRIPTION OF ADJUSTMENTRow8:
TYPE OF RELOCATION EACH AREA SEE ABOVERow8:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow8: event of an emergency. Schedule may be impacted
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow8:
ROUTERow9:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow9:
RT LTRow9:
BRIEF DESCRIPTION OF ADJUSTMENTRow9:
TYPE OF RELOCATION EACH AREA SEE ABOVERow9:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow9: by severe weather. Contractor will be billed if
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow9:
ROUTERow10:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow10:
RT LTRow10:
BRIEF DESCRIPTION OF ADJUSTMENTRow10:
TYPE OF RELOCATION EACH AREA SEE ABOVERow10:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow10: additional work and/or 2nd relocation are required
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow10:
ROUTERow11:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow11:
RT LTRow11:
BRIEF DESCRIPTION OF ADJUSTMENTRow11:
TYPE OF RELOCATION EACH AREA SEE ABOVERow11:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow11: from previously approved relocation plan. A
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow11:
ROUTERow12:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow12:
RT LTRow12:
BRIEF DESCRIPTION OF ADJUSTMENTRow12:
TYPE OF RELOCATION EACH AREA SEE ABOVERow12:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow12: minimum of 8 week notice must be given prior
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow12:
ROUTERow13:
STATION TO STATION OR SEG OFFSET TO SEG OFFSETRow13:
RT LTRow13:
BRIEF DESCRIPTION OF ADJUSTMENTRow13:
TYPE OF RELOCATION EACH AREA SEE ABOVERow13:
DESCRIBE CONDITIONAL RESTRICTIONS OR TIME REQUIREMENTS SPECIFY CONTRACTORS OPERATION FOR COORDINATED WORK SEE NOTES ABOVERow13: to Penelec de-energization.
CALENDAR DAYS REQD OR DATE OF COMPLETIONRow13:
TITLE:

File details come from the government source that posted it. Updated .